JH Kelly, LLC v. Tianwei New Energy Holdings Co.

68 F. Supp. 3d 1194, 2014 U.S. Dist. LEXIS 159416, 2014 WL 5816097
CourtDistrict Court, D. Idaho
DecidedNovember 10, 2014
DocketCase No. 1:13-cv-00368-BLW
StatusPublished

This text of 68 F. Supp. 3d 1194 (JH Kelly, LLC v. Tianwei New Energy Holdings Co.) is published on Counsel Stack Legal Research, covering District Court, D. Idaho primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
JH Kelly, LLC v. Tianwei New Energy Holdings Co., 68 F. Supp. 3d 1194, 2014 U.S. Dist. LEXIS 159416, 2014 WL 5816097 (D. Idaho 2014).

Opinion

MEMORANDUM DECISION AND ORDER

B. LYNN WINMILL, Chief Judge.

INTRODUCTION

Beginning in 2007, Plaintiff JH Kelly, LLC was the general contractor in charge [1196]*1196of building a manufacturing plant for a Chinese corporation. Construction ceased in 2012 when funding for the plant dried up. At that time, JH Kelly was owed approximately $25 million for work it had done on the plant. JH Kelly sued Tianwei New Energy Holdings Co., Ltd., a surety for the Chinese corporation, and several of the corporation’s officers and directors, defendants Tao Zhang, Wei Xia, Scott Paul, and Daui Liu, to recover the outstanding debt.

Central to JH Kelly’s complaint are allegations that Defendants knowingly misrepresented that Tianwei would fund thé project through to completion. By making those misrepresentations, Defendants allegedly committed fraud, violated state and federal racketeering law, and, in the alternative, negligently misled JH Kelly into believing it would be paid for its work. Because JH Kelly has not alleged facts that show that Tianwei’s stated commitment to the project was false, the Court will dismiss JH Kelly’s fraud and racketeering claims. JH Kelly’s negligence claim fails because it is not cognizable under Idaho law.

BACKGROUND

Hoku Corporation and its subsidiary, Hoku Material, Inc., (collectively “Hoku”) are Chinese corporations focused on developing clean energy projects. As part of its solar initiative, Hoku decided to construct a polysilicon manufacturing plant in Poca-tello, Idaho. Hoku hired Plaintiff JH Kelly as general contractor to build the plant, and construction commenced on August 8, 2007.

In early 2008, Tianwei committed to purchase Hoku’s polysilicon for ten years. The total purchase price was $468 million, and Tianwei paid $79 million upfront. By fall of 2008, however, the market for polys-, ilicon crashed. Shortly after the crash, Tianwei and Hoku entered into a financing arrangement whereby Tianwei became the majority shareholder and “funding arm of Hoku.” Amend. Compl., Dkt. 35, ¶ 19. As such, Tianwei exercised a significant degree of control over Hoku and the construction of the plant. Tianwei installed Zhang, Liu, Xia, and Paul, all of whom had ties to Tianwei, as directors and officers for Hoku. See id. ¶¶ 20-21.

By July 2010, Hoku had fallen behind in paying JH Kelly for its work building the plant. When JH Kelly raised concerns about the late payments with Defendants, they assured JH Kelly that they “wfould] ensure sufficient funds [were] in place till completion of the project.” Id. ¶26. A pattern of similar occurrences repeated for about one year. Each time payments fell behind, Defendants reiterated Tianwei’s financial strength and full commitment to the project. See id. ¶¶ 27, 33, 35.

In October 2011, Hoku stopped making payments to JH Kelly. See id. ¶ 50. In the months that followed, Defendants repeatedly assured JH Kelly that “Tianwei ... had in place all required financing for completion of the [p]roject, and that it was strictly a matter of “when, not if” the funds would be sent. Id. ¶ 35;. see also id. ¶ 39 (“Hoku/Tianwei [was] not a credit risk.”); id. ¶ 42 (“Tianwei ‘will ensure that sufficient funds are in place till completion of the project.’ ”). Defendants blamed the delay on various procedural hurdles, such as difficulty transferring funds from China to the United States. By the end of 2011, however, Hoku owed JH Kelly approximately $25 million. As a result, JH Kelly permanently stopped work on the plant on March 30, 2012.

JH Kelly filed its original complaint alleging common law fraud and violations of Idaho’s Racketeering Act, I.C. §§ 18-7801-18-7805, and the Racketeer Influenced and Corrupt Organizations Act (“RICO”), 18 U.S.C. §§ 1961-1968. On Defendants’ motion, the Court dismissed [1197]*1197the original complaint with leave to amend. Dkt. 34. JH Kelly had “not sufficiently alleged that [Defendants’ representations that Hoku or Tianwei intended to pay [JH Kelly] for its work on the project were false, much less that at the time they allegedly made these representations^ D]efendants knew they were false.” Id. at 8. Absent fraud, JH Kelly’s state and federal racketeering claims failed as well. Id. at 9.

Subsequently, JH Kelly filed an amended complaint, again alleging fraud and state and federal racketeering claims. JH Kelly added a claim for negligence based upon “Defendants’ omissions and/or misrepresentations” over the amount of financing in place for the project. Amend. Compl., Dkt. 35, ¶ 74. Defendants have moved to dismiss JH Kelly’s amended complaint for, among other things, failure to state a claim.

LEGAL STANDARD

Federal Rule of Civil Procedure 8(a)(2) requires only “a short and plain statement of the claim showing that the pleader is entitled to relief,” in order to “give the defendant fair notice of what the ... claim is and the grounds upon which it rests.” Bell Atlantic Corp. v. Twombly, 550 U.S. 544, 555, 127 S.Ct. 1955, 167 L.Ed.2d 929 (2007). While a complaint attacked by a Rule 12(b)(6) motion to dismiss “does not need detailed factual allegations,” it must set forth “more than labels and conclusions, and a formulaic recitation of the elements of a cause of action will not do.” Id. To survive a motion to dismiss, a complaint must contain sufficient factual matter, accepted as true, to “state a claim to relief that is plausible on its face.” Id. at 570, 127 S.Ct. 1955. A claim has facial plausibility when the plaintiff pleads factual content that allows the court to draw the reasonable inference that the defendant is liable for the misconduct alleged. Id. at 556, 127 S.Ct. 1955. The plausibility standard is not akin to a “probability requirement,” but it asks for more than a sheer possibility that a defendant has acted unlawfully. Id. Where a complaint pleads facts that are “merely consistent with” a defendant’s liability, it “stops short of the line between possibility and plausibility of ‘entitlement to' relief,’” Id. at 557, 127 S.Ct. 1955.

The Supreme Court identified two “working principles” that underlie Twombly in Ashcroft v. Iqbal, 556 U.S. 662, 678, 129 S.Ct. 1937, 173 L.Ed.2d 868 (2009). First, the court need not accept as true, legal conclusions that are couched as factual allegations. Id. Rule 8 does not “unlock the doors of discovery for a plaintiff armed with nothing more than conclusions.” Id. at 678-79, 129 S.Ct. 1937. Second, to survive a motion to dismiss, a complaint must state a plausible claim for relief. Id. at 679, 129 S.Ct. 1937. “Determining whether a complaint states a plausible claim for relief will ... be a context-specific task that requires the reviewing court to draw on its judicial experience and common sense.” Id.

DISCUSSION

1. Common Law Fraud

In addition to Rule 8, JH Kelly’s fraud claim is governed by

Related

Sedima, S. P. R. L. v. Imrex Co.
473 U.S. 479 (Supreme Court, 1985)
Bell Atlantic Corp. v. Twombly
550 U.S. 544 (Supreme Court, 2007)
Ashcroft v. Iqbal
556 U.S. 662 (Supreme Court, 2009)
Securities & Exchange Commission v. Todd
642 F.3d 1207 (Ninth Circuit, 2011)
In Re Glenfed, Inc. Securities Litigation
42 F.3d 1541 (Ninth Circuit, 1994)
Mia Fontana v. D.E. Haskin
262 F.3d 871 (Ninth Circuit, 2001)
Turner v. Cook
362 F.3d 1219 (Ninth Circuit, 2004)
Aardema v. U.S. Dairy Systems, Inc.
215 P.3d 505 (Idaho Supreme Court, 2009)
Duffin v. Idaho Crop Improvement Ass'n
895 P.2d 1195 (Idaho Supreme Court, 1995)
Just's, Inc. v. Arrington Construction Co.
583 P.2d 997 (Idaho Supreme Court, 1978)
Weatherhead v. Troll-Master, Inc.
851 P.2d 993 (Idaho Court of Appeals, 1992)
Tusch Enterprises v. Coffin
740 P.2d 1022 (Idaho Supreme Court, 1987)
In Re Atlas Mining Co., Securities Litigation
670 F. Supp. 2d 1128 (D. Idaho, 2009)
Blahd v. Richard B. Smith, Inc.
108 P.3d 996 (Idaho Supreme Court, 2005)
Gillespie v. Mountain Park Estates, L.L.C.
132 P.3d 428 (Idaho Supreme Court, 2006)
Glanzer v. . Shepard
135 N.E. 275 (New York Court of Appeals, 1922)
Fecht v. Price Co.
70 F.3d 1078 (Ninth Circuit, 1995)
Miller v. Yokohama Tire Corp.
358 F.3d 616 (Ninth Circuit, 2004)
Denny v. Barber
576 F.2d 465 (Second Circuit, 1978)

Cite This Page — Counsel Stack

Bluebook (online)
68 F. Supp. 3d 1194, 2014 U.S. Dist. LEXIS 159416, 2014 WL 5816097, Counsel Stack Legal Research, https://law.counselstack.com/opinion/jh-kelly-llc-v-tianwei-new-energy-holdings-co-idd-2014.