Jetty, Inc. v. Hall-McGuff Architects

595 S.W.2d 918, 1980 Tex. App. LEXIS 3174
CourtCourt of Appeals of Texas
DecidedMarch 12, 1980
DocketA2068
StatusPublished
Cited by5 cases

This text of 595 S.W.2d 918 (Jetty, Inc. v. Hall-McGuff Architects) is published on Counsel Stack Legal Research, covering Court of Appeals of Texas primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Jetty, Inc. v. Hall-McGuff Architects, 595 S.W.2d 918, 1980 Tex. App. LEXIS 3174 (Tex. Ct. App. 1980).

Opinion

J. CURTISS BROWN, Chief Justice.

Hall-McGuff Architects (appellee), a partnership of licensed architects, sued Jetty, Inc. and Jetty-Fagg, Inc. (appellants) to recover for architectural services in connection with the preparation of plans for an office building project for appellants. Trial was to the court, which rendered judgment in favor of Hall-McGuff against both appellants along with attorney’s fees and interest. Appellants bring this appeal.

On November 7,1974, Jetty, Inc., a wholly owned subsidiary of Jetty-Fagg, Inc., and Hall-McGuff entered into a written contract wherein Hall-McGuff agreed to prepare, plans and specifications for the construction of an office building, Mr. Jetty, president and chairman of Jetty-Fagg and president of Jetty, Inc., testified that the building had to have 10,000 square feet of net leaseable office space. The building was going to house the offices of Jetty, Inc. and Jetty-Fagg, with additional space to be leased out.

The contract provided that the architect’s fee would be nine percent of the total construction cost of the building. The work by Hall-McGuff was to be done in five phases: 1) schematic design, 2) design development, 3) construction documents, 4) bidding and negotiations, and 5) actual construction. If the building was not actually built, Hall-McGuff would receive a certain percentage of the nine percent fee, based on how many phases were completed. Mr. McGuff testified that phase four had been completed, and thus, according to the contract, Hall-McGuff was entitled to 80% of the 9% fee, based on the estimated total construction cost.

Under phase one, Hall-McGuff submitted schematic drawings for appellants’ approval. Mr. Jetty approved these drawings, which depicted 10,000 square feet of leasea-ble space, plus approximately 2,400 square feet of common areas, such as restrooms, corridors and lobbies. Mr. Jetty assented to *920 this, realizing that the extra square feet were necessary. The schematic drawings also showed the parking lots, walkways and other external aspects of the building. Mr. Jetty also requested that a covered walkway or colonnade, and a second story deck also be added to the design. This was done and appellee then proceeded to the design development phase.

Under this next phase, more detailed drawings, prepared from the approved schematic sketches, were submitted for approval. These drawings showed a total square footage of 13,398 feet, not including the colonnade or deck or any of the external areas such as the parking lots. A cost estimate of $497,775.00 was also included. Although Mr. Jetty testified that the cost was too high, he told Mr. McGuff to proceed with phase three.

Pursuant to phase three, Mr. McGuff prepared the final architectural drawings, to be used in procuring bids on the building. Mr. McGuff testified that during this time, January through March of 1975, he- was never told to stop work on the project. Mr. Cope, an employee of Jetty-Fagg, Inc., approved these plans. A revised estimate of $477,600.00 was then sent to appellants.

In phase four, Hall-McGuff assisted appellants in obtaining bids for the project. Again, Mr. McGuff testified that no one at Jetty, Inc. or Jetty-Fagg, Inc. expressed any disapproval with the plans or the project.

In April of 1975, after the phase three drawings were submitted, Hall-McGuff received the last payment from appellants. As late as June, 1975, Mr. McGuff testified that Mr. Canant, an executive of Jetty-Fagg, told Mr. McGuff that the invoices would soon be paid. However, in September, Hall-McGuff was informed that it would not be paid for any of the invoices.

Since findings of fact or conclusions of law were neither requested or filed, it must be presumed on appeal that the trial court made such implied findings as were necessary to support the judgment. Goodyear Tire & Rubber Co. v. Jefferson Construction Co., 565 S.W.2d 916 (Tex.Sup.1978). Moreover, in reviewing the record we may only consider evidence favorable to the judgment and disregard all evidence or inferences to the contrary. Goodyear Tire & Rubber Co. v. Jefferson Construction Co., supra, at 918. And, finally, the judgment must be affirmed if it may be upheld on any legal theory that has support in the evidence. Lassiter v. Bliss, 559 S.W.2d 353 (Tex.Sup.1978).

Appellants’ main contention is that Hall-McGuff breached the contract, which caused a total failure of consideration by the appellee and thereby excused appellants from making any further payments. Appellants claim that Hall-McGuff breached the contract by designing a building that would cost more than appellants had wanted or was larger than expected. Article 3.5 of the contract stated that any fixed limit of cost “shall be in writing signed by the parties.” There is no such writing in the record. Although the record indicates that there was some dispute as to what the cost would be, there is sufficient evidence in the record to support the court’s implied finding that the parties had not agreed on a fixed limit of construction cost.

The fact that the building may have cost more than the owner wanted is not material when there has been no fixed cost in the contract. Moore v. Bolton, 480 S.W.2d 805 (Tex.Civ.App.—Houston [14th Dist.] 1972, writ ref’d n. r. e.).

Appellants also complain that the documents submitted under the design development stage deviated from what the contract called for. These plans provide for a project of approximately 43,000 square feet, including about 22,000 square feet, for the office building and about 21,000 square feet for the external areas. Included within the 22,000 square foot figure for the building is the 8,000 square feet colonnade and deck, specifically requested by Mr. Jetty. Approximately 3,000 square feet in the building was necessary for the requisite common areas, such as restrooms, lobbies, stairways and utility space. This leaves 10,000 square feet of usable office space, which is what *921 the contract required. These common areas are obviously necessary in any modern office building and were approved by appellants.

As to the external aspects of the project, since the building was to be built on an undeveloped lot, it obviously had to have the necessary facilities incident to a modern office building, such as parking lots and walkways. These facilities are necessary for the building to be of any use at all and are required before a building permit could be issued. Furthermore, these areas were shown on all of the drawings approved by appellants. Mr. Jetty even discussed the parking lot requirements with Mr. McGuff.

Appellants next urge that the court erred in allowing recovery under a subsequent oral contract. They claim that such oral contract is impermissible under the contract, the Parol Evidence Rule, and for lack of new consideration. However, as stated above, the designs and plans prepared by Hall-McGuff were in accordance with the written contract. And there is sufficient evidence to support the implied finding that there had been no subsequent oral contract.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Clark v. Walker-Kurth Lumber Co.
689 S.W.2d 275 (Court of Appeals of Texas, 1985)
Texas Industries, Inc. v. Lucas
634 S.W.2d 748 (Court of Appeals of Texas, 1982)

Cite This Page — Counsel Stack

Bluebook (online)
595 S.W.2d 918, 1980 Tex. App. LEXIS 3174, Counsel Stack Legal Research, https://law.counselstack.com/opinion/jetty-inc-v-hall-mcguff-architects-texapp-1980.