Jersey Central Power & Light Company v. Federal Energy Regulatory Commission

589 F.2d 142
CourtCourt of Appeals for the Third Circuit
DecidedFebruary 8, 1979
Docket78-1185
StatusPublished

This text of 589 F.2d 142 (Jersey Central Power & Light Company v. Federal Energy Regulatory Commission) is published on Counsel Stack Legal Research, covering Court of Appeals for the Third Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Jersey Central Power & Light Company v. Federal Energy Regulatory Commission, 589 F.2d 142 (3d Cir. 1979).

Opinion

589 F.2d 142

JERSEY CENTRAL POWER & LIGHT COMPANY, Petitioner,
v.
FEDERAL ENERGY REGULATORY COMMISSION, Respondent,
Allegheny Electric Cooperative, Inc., Intervenor,
Boroughs of Madison, Butler, Lavallette, and Seaside
Heights, New Jersey, Intervenors.

No. 78-1185.

United States Court of Appeals,
Third Circuit.

Argued Oct. 6, 1978.
Decided Dec. 8, 1978.
As Amended Feb. 8, 1979.

James B. Liberman, Leonard W. Belter, Donald K. Dankner, Debevoise & Liberman, Washington, D. C., for petitioner.

Robert R. Nordhaus, Gen. Counsel, Howard E. Shapiro, Sol., Lynn N. Hargis, Atty., Washington, D. C., for respondent, Federal Energy Regulatory Commission.

William C. Wise, Robert Weinberg, Washington, D. C., for intervenor, Allegheny Electric Cooperative, Inc.

William I. Harkaway, Belnap, McCarthy, Spencer, Sweeney & Harkaway, Washington, D. C., for intervenors, Boroughs of Madison, Butler, Lavallette, and Seaside Heights, N. J.

Before ROSENN and WEIS, Circuit Judges and HANNUM, District Judge.*

OPINION OF THE COURT

WEIS, Circuit Judge.

The fuel adjustment clause is a controversial reaction to some of the problems created by the energy crisis. The interpretation by the Federal Energy Regulatory Commission of an electrical utility's tariff containing such a provision is the subject of this petition for review. We conclude that the Commission committed no error in construing the clause as one calling for current charges rather than for past expenses. Accordingly, since there was no "billing lag," the utility was not entitled to employ a phase-in arrangement in a new tariff to recover "unbilled" expenses.

In response to rapidly escalating fuel costs, Jersey Central Power & Light Company prepared and filed a tariff with the Federal Power Commission1 incorporating a fuel adjustment clause for charges to be collected from its wholesale customers.2 The clause became effective on December 2, 1973, and read in pertinent part:

"An energy cost adjustment factor shall be applied to each kilowatt-hour supplied under this tariff. This energy cost adjustment determined . . . in accordance with the formula set forth below, shall be applied to all kilowatt-hours supplied during the billing month."

There followed a formula that included as factors the cost of fuel and sales in current and base periods, taxes, and a component for adjustment of losses to the delivery voltage. In defining current sales and fuel costs, the tariff stated that these "factors are to be determined as the three month totals for the period ending with the second calendar month preceding the billing month."

With some revisions not material here, Jersey Central billed its customers under the new arrangement until July 27, 1976, when the company filed a proposed new schedule of wholesale electric rates, including a three-step increase in the base cost component of the fuel adjustment clause. This phase-in mechanism3 was designed to recover "unbilled fuel costs" still owed by customers, according to the utility, under the superseded adjustment clause. The contention was that such a device, similar in effect to temporary surcharges, was needed to recoup fuel costs already incurred. Because the original fuel adjustment charge was based on a time period ending two months before the billing date, the company asserted that a billing lag had resulted.

The boroughs of Lavallette, Madison, Butler, and Seaside Heights, and Allegheny Electric Cooperative, Inc., wholesale customers of Jersey Central, intervened and urged rejection of the proposed fuel adjustment clause as an attempt to retroactively recover fuel costs which the original clause had failed to include. Subsequently, the customers sought severance and summary disposition of the phase-in question in light of Public Service Co. of New Hampshire, Opinion Nos. 790 and 790-A, FERC Docket ER76-285 (1977), Petition for review filed, No. 77-1592 (D.C.Cir.), a decision of the Commission holding illegal a utility's proposed surcharge to recover unbilled fuel costs in a comparable situation. The Commission then issued an order summarily rejecting the phase-in aspect of Jersey Central's rate-filing, finding that this arrangement could not be distinguished from an illegal surcharge. After the Commission denied its application for rehearing, Jersey Central filed this petition for review.

The company contends that its prior fuel adjustment clause was designed to permit recovery for the actual monthly excess fuel costs for the period ending two months before the billing date. Thus, it maintains that when it adopted its new clause on September 27, 1976, there occurred a short fall in its collection for the months of June through September. According to the company, unbilled fuel costs incurred in those months, which were due to be collected under the old fuel clause in the months of October to December, 1976, would not be recouped under the new clause without the phase-in procedure.

The Commission, however, takes the position that the 1973 tariff did no more than establish a formula, based on past experience, I. e., costs incurred during a prior test period, to compute what was in effect an approximation of the excess and still unknown fuel costs for the billable month. It insists that the company did receive the proceeds of the fuel adjustment charge for every month it had been in effect. Under this view, once Jersey Central had collected its adjustment charge for a particular month, the company had assessed all it was entitled to collect, and there were no unbilled fuel costs still owed by the customer. The Commission contends that because the adjustment rate may have been inadequate to some extent in recapturing costs is not justification for a retroactive charge. Its position is that there was no billing lag and therefore no basis for the phase-in procedure.

The legality of the 1976 clause therefore hinges on the one adopted in 1973. Since the dispute centers on the interpretation of the 1973 tariff, the appropriate place to begin is with its wording, bearing in mind the construction should be that reasonably communicated to those governed by it, and any doubt as to the meaning should be resolved against the filing utility. Cf. United States v. Missouri-Kansas-Texas Railroad, 194 F.2d 777 (5th Cir. 1952). See also Great Northern Railway v. Merchants Elevator Co., 259 U.S. 285, 290-91, 42 S.Ct. 477, 66 L.Ed. 943 (1922).

The tariff required that an adjustment factor be "applied to all kilowatt-hours supplied during the billing month." This is inconsistent with the company's premise that the charge was to be a pass-on of Actual past costs incurred.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
589 F.2d 142, Counsel Stack Legal Research, https://law.counselstack.com/opinion/jersey-central-power-light-company-v-federal-energy-regulatory-ca3-1979.