Jerry's Hardware, L.L.C., plaintiff-appellee/cross-appellant v. Hillcrest Partners, a General Partnership, Charles A. Ruhl Jr., and Steven Fry, defendant-appellants/cross-appellees.

CourtCourt of Appeals of Iowa
DecidedJuly 22, 2015
Docket14-1625
StatusPublished

This text of Jerry's Hardware, L.L.C., plaintiff-appellee/cross-appellant v. Hillcrest Partners, a General Partnership, Charles A. Ruhl Jr., and Steven Fry, defendant-appellants/cross-appellees. (Jerry's Hardware, L.L.C., plaintiff-appellee/cross-appellant v. Hillcrest Partners, a General Partnership, Charles A. Ruhl Jr., and Steven Fry, defendant-appellants/cross-appellees.) is published on Counsel Stack Legal Research, covering Court of Appeals of Iowa primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Jerry's Hardware, L.L.C., plaintiff-appellee/cross-appellant v. Hillcrest Partners, a General Partnership, Charles A. Ruhl Jr., and Steven Fry, defendant-appellants/cross-appellees., (iowactapp 2015).

Opinion

IN THE COURT OF APPEALS OF IOWA

No. 14-1625 Filed July 22, 2015

JERRY’S HARDWARE, L.L.C., Plaintiff-Appellee/Cross-Appellant,

vs.

HILLCREST PARTNERS, a general partnership, CHARLES A. RUHL JR., and STEVEN FRY, Defendant-Appellants/Cross-Appellees. ________________________________________________________________

Appeal from the Iowa District Court for Scott County, Marlita A. Greve

(Settlement Conference; First and Second Motions to Continue), J. Hobart

Darbyshire (Third Motion to Continue), Henry Latham (Fourth Motion to

Continue), and Mary E. Howes (Trial and Post-Trial Motions), Judges.

Hillcrest Partners, Charles Ruhl, and Steven Fry appeal the district court’s

ruling awarding Jerry’s Hardware, L.L.C. damages after breach of the parties’

lease agreement. AFFIRMED ON APPEAL; AFFIRMED ON CROSS-APPEAL.

Gary D. McKenrick of Cartee & McKenrick, P.C., Davenport, for

appellants.

Elliott R. McDonald III and Ryan F. Gerdes of McDonald, Woodward

& Carkson, P.C., Davenport, for appellee.

Considered by Vogel, P.J., and Potterfield and Mullins, JJ. 2

POTTERFIELD, J.

Hillcrest Partners, Charles Ruhl, and Steven Fry (collectively “Hillcrest”)

appeal the district court’s ruling awarding Jerry’s Hardware, L.L.C. (“Jerry’s”)

damages after Hillcrest’s breach of the parties’ lease agreement. Jerry’s cross-

appeals the denial of two categories of claimed damages.

I. Factual and Procedural Background

On June 29, 2009, Jerry Richard, the owner of Jerry’s, and Hillcrest

signed a letter of intent to lease a retail unit of Hillcrest’s upcoming Crown Ridge

Plaza (Phase II) construction project. Jerry intended to rent a unit in which he

would open an Ace Hardware store. The parties entered into a lease agreement

on October 1, 2009. The lease agreement included the following terms:

3. TERM . . . The “Commencement Date” of the Term of this Lease shall be the date of substantial completion of the Premises . . . , which is expected to be on or about March 5, 2010. In the event the Premises is not substantially completed by such date, Tenant shall receive one (1) day of abated Base Rent for each day after March 5, 2010 until the Premises is substantially completed. In the event the Premises is not substantially completed on or prior to March 12, 2010, Tenant shall receive two (2) days of abated Base Rent for each day after March 12, 2010, until the Premises is substantially completed. . . . .... 38. CONDITIONS PRECEDENT The parties’ performance and obligations under this Lease are subject to the following conditions [precedent]: A) The Landlord’s acceptance shall be subject to the Landlord securing financing for Crow Ridge Phase II at terms acceptable to Landlord on or before September 1, 2009.[1]

1 The deadlines and the conditions were incorporated directly from the letter of intent. The deadlines had passed when the lease itself was signed. If any of the conditions 3

B) The Tenant’s acceptance shall be subject to Tenant securing financing for Tenant’s business need at terms acceptable to Tenant on or before September 1, 2009. C) The Tenant’s acceptance shall be subject to Tenant’s approval by Ace Hardware Corporation to operate an Ace Hardware store in the premises on or before August 2, 2009. The parties agree to use all commercially reasonable efforts in satisfying the above conditions. If any of the conditions are not satisfied or waived on or before the dates set forth above, this Lease may be terminated by such party upon written notice to the other.[2]

After signing the lease agreement, Jerry began to make arrangements to

move into the leased space by developing the store’s floor plan with Ace

Hardware representatives and by purchasing fixtures, equipment, and inventory

for the store at a lump sum cost of $100,000. Jerry made Hillcrest aware of the

impending purchases at the time the parties entered into the lease. The fixtures,

equipment, and inventory were put in storage pending the completion of

construction.

Hillcrest never began construction. On May 14, 2010, Jerry sent a letter

through his attorney to Hillcrest requesting an explanation for Hillcrest’s failure to

begin construction. The letter explicitly noted Jerry was “not interested in

exercising his option to terminate the lease.” Hillcrest did not respond to the

letter. On September 7, 2010, Jerry sent a second letter through his attorney to

Hillcrest itemizing his losses resulting from Hillcrest’s failure to perform. Hillcrest

were not met, the parties were permitted to terminate their agreement but not contractually prohibited from entering into the lease agreement on October 1, 2009. 2 Because this clause is expressly permissive, the three conditions in the lease are not in fact conditions precedent, which are not permissive, in spite of the lease’s misuse of the legal term. See Khabbaz v. Swartz, 319 N.W.2d 279, 284 (Iowa 1982) (“Nonperformance of a condition precedent vitiates a contract or a proposed contract.”). 4

did not respond to the second letter.3 Nor did Hillcrest exercise its option to

terminate the agreement.

Jerry eventually leased an alternate location on January 20, 2012, to

“mitigate [his] losses.” The new location is less visible and sees less incidental

traffic than the planned Crown Ridge Plaza location. Additionally, the Crown

Ridge Plaza location was to be constructed according to particular electrical

specifications to support Ace Hardware requirements. When Jerry leased the

new location, he was required to pay out-of-pocket to have the location’s

electrical system retrofitted to match those requirements at an expense of

$26,000.

Some of the fixtures, equipment, and inventory that Jerry had purchased

in anticipation of a March 2010 opening did not comply with Ace Hardware’s

requirements for new stores in 2012. Jerry was required to purchase a new paint

system at an expense of $9000 and new signage, shelving, point of sale

systems, and other equipment at a cost of $38,666.28. He had also paid

unanticipated storage costs starting on March 5, 2010, when he had planned on

removing his inventory from storage and moving it into the Crown Ridge Plaza

location. The additional storage lasted nearly two years and cost Jerry

$26,778.49.

Jerry’s filed suit against Hillcrest on January 2, 2013. A bench trial was

scheduled for December 10, 2013. Hillcrest filed a motion to continue the trial on

3 Hillcrest sent a letter to Jerry to “update [him] on the positive progress” made on the Crow Ridge Plaza project. The letter does not substantively respond to either of Jerry’s letters. Hillcrest’s letter is not dated, but the substance of the letter indicates it was sent after November 1, 2010. 5

October 21, 2013, claiming it had some indication from Jerry’s that it might not

continue to pursue the action.4 On November 7, the district court denied the

motion, but it did continue discovery deadlines to allay the concerns of Hillcrest’s

counsel. On November 14, 2013, Hillcrest’s counsel moved to withdraw from the

case after a previously unnoticed conflict of interest came to light. At the same

time, Hillcrest moved again to continue the trial. On November 19, the district

court granted the motion to withdraw but denied the motion to continue, finding,

“Defendants still have enough time and have had enough time to obtain other

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Royal Indemnity Co. v. Factory Mutual Insurance Co.
786 N.W.2d 839 (Supreme Court of Iowa, 2010)
Land O'Lakes, Inc. v. Hanig
610 N.W.2d 518 (Supreme Court of Iowa, 2000)
Meier v. SENECAUT III
641 N.W.2d 532 (Supreme Court of Iowa, 2002)
Falczynski v. Amoco Oil Co.
533 N.W.2d 226 (Supreme Court of Iowa, 1995)
Pillsbury Co., Inc. v. Wells Dairy, Inc.
752 N.W.2d 430 (Supreme Court of Iowa, 2008)
Kuehl v. Freeman Bros. Agency, Inc.
521 N.W.2d 714 (Supreme Court of Iowa, 1994)
Bates Advertising USA, Inc. v. 498 Seventh, LLC
850 N.E.2d 1137 (New York Court of Appeals, 2006)
Hawkeye Bank & Trust Co. v. Michel
373 N.W.2d 127 (Supreme Court of Iowa, 1985)
Khabbaz v. Swartz
319 N.W.2d 279 (Supreme Court of Iowa, 1982)
Hawkeye Bank & Trust, National Ass'n v. Baugh
463 N.W.2d 22 (Supreme Court of Iowa, 1990)
Schick v. Davenport Realty Co.
205 N.W. 782 (Supreme Court of Iowa, 1925)
Woodbury Co. v. Dougherty & Bryant Co.
143 N.W. 416 (Supreme Court of Iowa, 1913)

Cite This Page — Counsel Stack

Bluebook (online)
Jerry's Hardware, L.L.C., plaintiff-appellee/cross-appellant v. Hillcrest Partners, a General Partnership, Charles A. Ruhl Jr., and Steven Fry, defendant-appellants/cross-appellees., Counsel Stack Legal Research, https://law.counselstack.com/opinion/jerrys-hardware-llc-plaintiff-appelleecross-appellant-v-hillcrest-iowactapp-2015.