Jerry T. Beech Concrete Contractor, Inc. v. Larry Powell Builders, Inc.

CourtCourt of Appeals of Tennessee
DecidedMarch 4, 2003
DocketM2001-02709-COA-R3-CV
StatusPublished

This text of Jerry T. Beech Concrete Contractor, Inc. v. Larry Powell Builders, Inc. (Jerry T. Beech Concrete Contractor, Inc. v. Larry Powell Builders, Inc.) is published on Counsel Stack Legal Research, covering Court of Appeals of Tennessee primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Jerry T. Beech Concrete Contractor, Inc. v. Larry Powell Builders, Inc., (Tenn. Ct. App. 2003).

Opinion

IN THE COURT OF APPEALS OF TENNESSEE AT NASHVILLE January 9, 2003 Session

JERRY T. BEECH CONCRETE CONTRACTOR, INC. v. LARRY POWELL BUILDERS, INC., ET AL.

Appeal from the Chancery Court for Davidson County No. 99-725-III Ellen Hobbs Lyle, Chancellor

No. M2001-02709-COA-R3-CV - Filed March 4, 2003

In this appeal from the trial court’s award of attorneys fees, Appellant seeks review of the trial court’s refusal to award the full amount of fees sought. We modify the trial court’s findings and affirm as to the amount of the award.

Tenn. R. App. P. 3 Appeal as of Right; Judgment of the Chancery Court Affirmed as Modified

WILLIAM B. CAIN , J., delivered the opinion of the court, in which BEN H. CANTRELL , P.J., M.S., and PATRICIA J. COTTRELL, J., joined.

Timothy W. Burrow, Nashville, Tennessee, for the appellant, Jerry T. Beech Concrete Contractor, Inc.

John R. Reynolds, Nashville, Tennessee, for the appellees, Larry Powell Builders, Inc.

OPINION

This is the second appeal in an action brought by a contractor to receive the balance alleged to be due under a construction contract. Jerry T. Beech Concrete Contractor, Inc. (Beech) originally sued Larry Powell Builders, Inc. (Powell Builders) for breach of the payment provisions of a construction job contract. Powell Builders answered Beech’s complaint and counter-claimed for breach of contract. In its counter-claim it asserted a set off due to charges back and failure of Beech to perform the construction in a workmanlike manner. After a bench trial, the Davidson County Chancery Court held that the job contract was actually a bid for services, rather than a written contract. As a result, the attorney fee provisions of the job contract were unenforceable. On appeal, this Court modified and remanded the case finding, in pertinent part, as follows: The Chancellor disallowed attorney fees because the only terms in the “Job Contract” which the parties discussed and acted on and indicated acceptance of are the price and performance specifications. We have found that the evidence preponderates against the finding that the document styled “Job Contract” was merely a bid, and not a contract. We further find that the contract was not divisible, and that it was accepted in its entirety. Accordingly, the provision of the contract “If client fails to pay as agreed, Jerry Beech Concrete is entitled to receive attorney fees and all costs associated with the collection of this debt including any costs extended by Jerry Beech Concrete to enforce this agreement” is enforceable as contractual in nature. See, Owen v. Stanley,739 S.W.2d 782 (Tenn. App. 1987); Remco Equipment Sales, Inc. v. Manz, 952 S.W.2d 437 (Tenn. App. 1997). The case is remanded for a determination of a reasonable fee in accordance with Connors v. Connors, 594 S.W.2d 672 (Tenn. 1980), In re: Estate of Davis, 719 S.W.2d 575 (Tenn. App. 19 and Disciplinary Rule 2-106 of the code of Professional Responsibility, Rule 8 of the Rules of the Supreme Court.

Jerry T. Beech Concrete Contractor, Inc. v. Larry Powell Builders, Inc., et al., No. M2000-01704- COA-R3-CV, 2001 WL 487574 at *2 (Tenn. Ct. App. May 9, 2001).

Consistent with this Court’s disposition, Plaintiff filed its Motion To Assess Attorneys Fees and Costs on August 20, 2001. Plaintiff supported the motion with a memorandum of law and affidavit which documented counsel’s representation of Beech throughout the claim and in defense of Powell Builder’s counter-claim. Appellant asserted its entitlement to a fee of $34,344.44. Powell Builders responded with two affidavits, one from Powell Builders’ counsel and one from counsel David Young Parker, characterizing Beech’s claim as an action to collect a debt, for which the “standard fee for counsel” represented a 25 to 40% contingency fee arrangement. After considering the affidavits filed and the testimony given, the trial court rendered its Memorandum and Order on September 25, 2001. In that Memorandum and Order, the trial court awarded $12,262.80 in attorneys fees, holding in pertinent part:

After considering the affidavits, the testimony of Mr. Parker and reviewing DR2-106 of Rule 8 of the Supreme Court Rules, the Court concludes that the plaintiff is entitled to recover $12,262.80 in attorney’s fees.

In arriving at this conclusion, the Court has made the following analysis under the factors listed in DR2-106:

1. The time and labor required, the novelty and difficulty of the questions involved, and the skill requisite to perform the legal service properly – The affidavit of plaintiff’s counsel establishes that the plaintiff spent in excess of 250 hours at a rate of $125.00 per hour. Given the pretrial motions the Court presided over and the length of the trial, and the vast knowledge of plaintiff’s counsel of the law and fact, there is no doubt those hours were actually spent. The Court also finds

-2- that the plaintiff’s rate is reasonable. The case was of medium to low complexity. There were some issues on the licensure claim which were somewhat challenging because of the absence of much case law, but that is often true. The case was not novel nor complex.

2. The likelihood, if apparent to the client, that the acceptance of the particular employment will preclude other employment by the lawyer–not applicable

3. The fee customarily charged in the locality for similar legal services–The proof established that the hourly rate charged by the plaintiff’s counsel of $125.00 per hour is not out of line with fees charged in this locality. The affidavit and testimony of attorney Parker, though, called into question the reasonableness of charging $34,344.44 in fees when the ultimate recovery of the plaintiff was $5,657.00.

4. The amount involved and the results obtained–The amount involved for the plaintiff was $10,000.00. The plaintiff also had to defend against a $50,000.00 counterclaim. The plaintiff recovered $5,657.00. That the plaintiff did not recover the entire $10,000.00 means that there was some validity to the counterclaim. That the recovery was only $5,657.00 calls into question a fee of $34,344.44 unless there were novel issues or unique circumstances.

5-8. Factors 5 through 8 are not in issue except as to factor 7 concerning the experience, reputation and ability of plaintiff’s counsel. Plaintiff’s counsel is an architect and former contractor who specializes in construction litigation.

The Court concludes that it would be excessive in this case to require the defendant to pay $34,344.44 in attorney’s fees. Although the Court does not doubt that plaintiff’s counsel spent in excess of 250 hours on this lawsuit, the case was not novel nor difficult. Computing 40% of the recovery of $5,657.00 equates to $2,262.80. There should be added to that an attorney’s fee for the time expended in defending the counterclaim. The Court determines that no more than 80 hours were justified in defending the counterclaim. At the rate of $125.00 an hour, a $10,000.00 fee is awarded on the defense of the counterclaim.

It is therefore ORDERED that the plaintiff is awarded $12,262.80 in attorney’s fees.

It bears noting that the trial court did not find the amount of hours to be reasonable. The trial court only found the rate to be reasonable and that the hours were “actually spent.” The court does compliment counsel on his command of the “law and fact” of the case; however, the court found the case to be of “medium to low complexity.” Further, and most importantly, the trial court found that

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Alexander v. Inman
974 S.W.2d 689 (Tennessee Supreme Court, 1998)
Fell v. Rambo
36 S.W.3d 837 (Court of Appeals of Tennessee, 2000)
Ware v. Paxton
266 S.W.2d 218 (Court of Appeals of Texas, 1954)
Gilman v. Commissioner of Internal Revenue
53 F.2d 47 (Eighth Circuit, 1931)
Connors v. Connors
594 S.W.2d 672 (Tennessee Supreme Court, 1980)
Folk v. Folk
357 S.W.2d 828 (Tennessee Supreme Court, 1962)
Remco Equipment Sales, Inc. v. Manz
952 S.W.2d 437 (Court of Appeals of Tennessee, 1997)
Williams v. State
719 S.W.2d 573 (Court of Criminal Appeals of Texas, 1986)
Owen v. Stanley
739 S.W.2d 782 (Court of Appeals of Tennessee, 1987)
Lowery v. Fuller
281 S.W. 968 (Missouri Court of Appeals, 1926)
World Exploration Co. v. Hoera-Rosenthal Safe Co.
34 S.W.2d 703 (Court of Appeals of Texas, 1930)
Ehlinger v. Clark
8 S.W.2d 666 (Texas Supreme Court, 1928)
Weitzner v. Commissioner
12 B.T.A. 724 (Board of Tax Appeals, 1928)
Inman v. Texas Land & Mortgage Co.
78 S.W.2d 1032 (Court of Appeals of Texas, 1935)
Dover v. Dover
821 S.W.2d 593 (Court of Appeals of Tennessee, 1991)
Saleno v. City of Neosho
27 L.R.A. 769 (Supreme Court of Missouri, 1895)
State v. Latham
136 Tenn. 30 (Tennessee Supreme Court, 1916)
Roberts v. Vaughn
142 Tenn. 361 (Tennessee Supreme Court, 1919)
Folk v. Folk
355 S.W.2d 634 (Tennessee Supreme Court, 1962)
Clinton Mining & Mineral Co. v. Beacom
264 F. 228 (W.D. Pennsylvania, 1920)

Cite This Page — Counsel Stack

Bluebook (online)
Jerry T. Beech Concrete Contractor, Inc. v. Larry Powell Builders, Inc., Counsel Stack Legal Research, https://law.counselstack.com/opinion/jerry-t-beech-concrete-contractor-inc-v-larry-powell-builders-inc-tennctapp-2003.