Rel: November 22, 2024
Notice: This opinion is subject to formal revision before publication in the advance sheets of Southern Reporter. Readers are requested to notify the Reporter of Decisions, Alabama Appellate Courts, 300 Dexter Avenue, Montgomery, Alabama 36104-3741 ((334) 229-0650), of any typographical or other errors, in order that corrections may be made before the opinion is printed in Southern Reporter.
SUPREME COURT OF ALABAMA OCTOBER TERM, 2024-2025
_________________________
SC-2024-0253 _________________________
Jerry & John Woods Construction, Inc.
v.
John David Jordan and Carol S. Jordan
Appeal from Dallas Circuit Court (CV-22-900161)
COOK, Justice.
In May 2022, Jerry & John Woods Construction, Inc. ("Woods
Construction"), entered into a contract with John David Jordan and Carol
S. Jordan for the construction of a house and a metal building. After the SC-2024-0253
Jordans allegedly failed to pay Woods Construction for the work it had
performed, the company sued them in the Dallas Circuit Court, asserting
claims of breach of contract and unjust enrichment.
The Jordans eventually moved to dismiss the claims against them
or, in the alternative, for a summary judgment in their favor on the basis
that Woods Construction's failure to maintain the required residential-
home-builder's license barred it from bringing civil claims against the
Jordans. The Jordans also asserted counterclaims on the basis that the
work completed by Woods Construction was done improperly and
negligently. Woods Construction opposed the Jordans' motion, asserting
that it was not barred from recovering the cost of constructing the metal
building, which, it argued, is not a residential home.
Following a hearing, the circuit court entered a summary judgment
in favor of the Jordans on Woods Construction's claims after finding that,
under § 34-14A-14(d), Ala. Code 1975, a part of Alabama's Home Builders
Licensure Act ("the Licensure Act"), § 34-14A-1 et seq., Ala. Code 1975,
Woods Construction, as a residential home builder without the proper
license, was barred from bringing a civil action against the Jordans to
enforce the construction contract between them.
2 SC-2024-0253
As explained below, although the circuit court certified its judgment
as final pursuant to Rule 54(b), Ala. R. Civ. P., that certification was
improper, and therefore this appeal is due to be dismissed.
Facts and Procedural History
As stated previously, in May 2022, the Jordans entered into a
contact with Woods Construction to construct a house and a metal
building on their property. Per the terms of the contract, the Jordans
agreed to pay Woods Construction $330,000 to build those structures.
According to Woods Construction, the Jordans were required to pay the
company the "first draw of $85,000." Although the Jordans contend that
they paid the first payment, Woods Construction asserts that the Jordans
refused to pay and that, as a result, "the project was put on hold until
payment was made."
In March 2023, Woods Construction commenced this action against
the Jordans, asserting breach-of-contract and unjust-enrichment claims
as a result of the Jordans' alleged failure to make the requested payment.
The company also sought compensatory damages plus any applicable
interest and costs. Woods Construction also filed a "Notice of Lis
Pendens/Lien" in the Dallas Probate Court.
3 SC-2024-0253
On July 17, 2023, the Jordans filed a motion to dismiss or, in the
alternative, for a summary judgment. In their motion, the Jordans
asserted that, at the time Woods Construction began building the house
and metal building on their property, the company was not properly
licensed with the Alabama Home Builders Licensure Board ("the Board")
in accordance with § 34-14A-5(a)(1), Ala. Code 1975, which provides that
"[a]ll residential home builders shall be required to be licensed by the
Home Builders Licensure Board annually."
According to the Jordans, because Woods Construction did not have
the requisite license, the company could not maintain its action against
them. See § 34-14A-14(d) (providing that "[a] residential home builder,
who does not have the license required, shall not bring or maintain any
action to enforce the provisions of any contract for residential home
building which he or she entered into in violation of [the Licensure Act]"
(emphasis added)). As a result, the Jordans argued that they were
entitled either to have Woods Construction's claims against them
dismissed or, in the alternative, to a summary judgment in their favor.
In support of their assertions, the Jordans purportedly attached
"Exhibit B" to their motion, which included a copy of § 34-14A-14; the
4 SC-2024-0253
affidavit of J.R. Carden, Jr., the Executive Director of the Board; the
Board's investigative file regarding Woods Construction; and an
"Administrative Resolution" from the Board. In the resolution, Woods
Construction admitted that it had engaged in residential construction at
the Jordans' property without a license, in violation of the Licensure Act,
and, thus, agreed to pay a $1,000 fine.
At the same time the Jordans filed their motion, the Jordans also
filed an answer to Woods Construction's complaint, in which they denied
all the allegations against them and repeated their arguments in support
of their motion. They also asserted breach-of-contract and negligence
counterclaims. Specifically, the Jordans alleged that Woods Construction
had breached the contract at issue and had been negligent "by failing to
properly comply with the terms of the contract and by failing to perform
the construction work in a good, proper, and workmanlike manner." They
sought compensatory damages in excess of $250,000.
After the Jordans amended their motion, Woods Construction filed
a brief in opposition to that motion on August 17, 2023. Woods
Construction first argued that it could not properly defend itself against
the arguments made in the Jordans' motion because the primary exhibit
5 SC-2024-0253
on which they had relied -- Exhibit B -- was not attached to either their
original or their amended motion. 1 Even so, Woods Construction
attempted to refute the arguments made in the Jordans' motion.
Although Woods Construction acknowledged that it could not sue the
Jordans to recover the costs it had incurred building the Jordans' house
because it lacked the required home-builder's license, it asserted that it
did not need such a license to build the Jordans' metal building and, thus,
could move forward with its action against the Jordans to recover the
costs it had incurred building that structure.
At some point, the circuit court entered an order denying the
Jordans' motion to dismiss but resetting their motion for a summary
judgment for a hearing on December 8, 2023, and that hearing was held.
According to the Jordans, during the hearing, Woods Construction
"requested additional time to respond to the Motion for Summary
1It appears to this Court that Exhibit B was not originally attached
Free access — add to your briefcase to read the full text and ask questions with AI
Rel: November 22, 2024
Notice: This opinion is subject to formal revision before publication in the advance sheets of Southern Reporter. Readers are requested to notify the Reporter of Decisions, Alabama Appellate Courts, 300 Dexter Avenue, Montgomery, Alabama 36104-3741 ((334) 229-0650), of any typographical or other errors, in order that corrections may be made before the opinion is printed in Southern Reporter.
SUPREME COURT OF ALABAMA OCTOBER TERM, 2024-2025
_________________________
SC-2024-0253 _________________________
Jerry & John Woods Construction, Inc.
v.
John David Jordan and Carol S. Jordan
Appeal from Dallas Circuit Court (CV-22-900161)
COOK, Justice.
In May 2022, Jerry & John Woods Construction, Inc. ("Woods
Construction"), entered into a contract with John David Jordan and Carol
S. Jordan for the construction of a house and a metal building. After the SC-2024-0253
Jordans allegedly failed to pay Woods Construction for the work it had
performed, the company sued them in the Dallas Circuit Court, asserting
claims of breach of contract and unjust enrichment.
The Jordans eventually moved to dismiss the claims against them
or, in the alternative, for a summary judgment in their favor on the basis
that Woods Construction's failure to maintain the required residential-
home-builder's license barred it from bringing civil claims against the
Jordans. The Jordans also asserted counterclaims on the basis that the
work completed by Woods Construction was done improperly and
negligently. Woods Construction opposed the Jordans' motion, asserting
that it was not barred from recovering the cost of constructing the metal
building, which, it argued, is not a residential home.
Following a hearing, the circuit court entered a summary judgment
in favor of the Jordans on Woods Construction's claims after finding that,
under § 34-14A-14(d), Ala. Code 1975, a part of Alabama's Home Builders
Licensure Act ("the Licensure Act"), § 34-14A-1 et seq., Ala. Code 1975,
Woods Construction, as a residential home builder without the proper
license, was barred from bringing a civil action against the Jordans to
enforce the construction contract between them.
2 SC-2024-0253
As explained below, although the circuit court certified its judgment
as final pursuant to Rule 54(b), Ala. R. Civ. P., that certification was
improper, and therefore this appeal is due to be dismissed.
Facts and Procedural History
As stated previously, in May 2022, the Jordans entered into a
contact with Woods Construction to construct a house and a metal
building on their property. Per the terms of the contract, the Jordans
agreed to pay Woods Construction $330,000 to build those structures.
According to Woods Construction, the Jordans were required to pay the
company the "first draw of $85,000." Although the Jordans contend that
they paid the first payment, Woods Construction asserts that the Jordans
refused to pay and that, as a result, "the project was put on hold until
payment was made."
In March 2023, Woods Construction commenced this action against
the Jordans, asserting breach-of-contract and unjust-enrichment claims
as a result of the Jordans' alleged failure to make the requested payment.
The company also sought compensatory damages plus any applicable
interest and costs. Woods Construction also filed a "Notice of Lis
Pendens/Lien" in the Dallas Probate Court.
3 SC-2024-0253
On July 17, 2023, the Jordans filed a motion to dismiss or, in the
alternative, for a summary judgment. In their motion, the Jordans
asserted that, at the time Woods Construction began building the house
and metal building on their property, the company was not properly
licensed with the Alabama Home Builders Licensure Board ("the Board")
in accordance with § 34-14A-5(a)(1), Ala. Code 1975, which provides that
"[a]ll residential home builders shall be required to be licensed by the
Home Builders Licensure Board annually."
According to the Jordans, because Woods Construction did not have
the requisite license, the company could not maintain its action against
them. See § 34-14A-14(d) (providing that "[a] residential home builder,
who does not have the license required, shall not bring or maintain any
action to enforce the provisions of any contract for residential home
building which he or she entered into in violation of [the Licensure Act]"
(emphasis added)). As a result, the Jordans argued that they were
entitled either to have Woods Construction's claims against them
dismissed or, in the alternative, to a summary judgment in their favor.
In support of their assertions, the Jordans purportedly attached
"Exhibit B" to their motion, which included a copy of § 34-14A-14; the
4 SC-2024-0253
affidavit of J.R. Carden, Jr., the Executive Director of the Board; the
Board's investigative file regarding Woods Construction; and an
"Administrative Resolution" from the Board. In the resolution, Woods
Construction admitted that it had engaged in residential construction at
the Jordans' property without a license, in violation of the Licensure Act,
and, thus, agreed to pay a $1,000 fine.
At the same time the Jordans filed their motion, the Jordans also
filed an answer to Woods Construction's complaint, in which they denied
all the allegations against them and repeated their arguments in support
of their motion. They also asserted breach-of-contract and negligence
counterclaims. Specifically, the Jordans alleged that Woods Construction
had breached the contract at issue and had been negligent "by failing to
properly comply with the terms of the contract and by failing to perform
the construction work in a good, proper, and workmanlike manner." They
sought compensatory damages in excess of $250,000.
After the Jordans amended their motion, Woods Construction filed
a brief in opposition to that motion on August 17, 2023. Woods
Construction first argued that it could not properly defend itself against
the arguments made in the Jordans' motion because the primary exhibit
5 SC-2024-0253
on which they had relied -- Exhibit B -- was not attached to either their
original or their amended motion. 1 Even so, Woods Construction
attempted to refute the arguments made in the Jordans' motion.
Although Woods Construction acknowledged that it could not sue the
Jordans to recover the costs it had incurred building the Jordans' house
because it lacked the required home-builder's license, it asserted that it
did not need such a license to build the Jordans' metal building and, thus,
could move forward with its action against the Jordans to recover the
costs it had incurred building that structure.
At some point, the circuit court entered an order denying the
Jordans' motion to dismiss but resetting their motion for a summary
judgment for a hearing on December 8, 2023, and that hearing was held.
According to the Jordans, during the hearing, Woods Construction
"requested additional time to respond to the Motion for Summary
1It appears to this Court that Exhibit B was not originally attached
to the Jordans' motion but was, instead, filed with the circuit court after Woods Construction filed its brief in opposition to their motion. We note, however, that that exhibit was available for Woods Construction to consider and review many months before the summary-judgment hearing and before the circuit court entered a summary judgment. It thus appears that Woods Construction could have properly defended itself against the Jordans' motion. 6 SC-2024-0253
Judgment."
Then, on March 4, 2024, the Jordans filed a "Motion for Ruling on
Defendants' Pending Motion for Summary Judgment." The Jordans
argued that their summary-judgment motion was due to be granted
because Woods Construction had acknowledged in the administrative
resolution that it had violated § 34-14A-5(a)(1) and it had not provided
any additional response to the pending motion pursuant to its request at
the summary-judgment hearing.
The circuit court then entered a summary judgment in favor of the
Jordans on Woods Construction's claims against them and declared the
company's "Notice of Lis Pendens/Lien" null and void. In that same order,
the circuit court also made clear that the Jordans' counterclaims against
Woods Construction would remain pending. It further certified its order
as final pursuant to Rule 54(b) after finding that there was no just reason
for delay. Woods Construction appealed.
Standard of Review
In reviewing a circuit court's order certifying its judgment as final
pursuant to Rule 54(b), Ala. R. Civ. P., the standard of review is as
follows:
7 SC-2024-0253
" 'Whether the action involves separate claims and whether there is a final decision as to at least one of the claims are questions of law to which we will apply a de novo standard of review. Whether there was "no just reason for delay" is an inquiry committed to the sound discretion of the trial court, and, as to that issue, we must determine whether the trial court exceeded its discretion.' "
Rogers v. Cedar Bluff Volunteer Fire Dep't, 387 So. 3d 131, 135 (Ala.
2023) (quoting Scrushy v. Tucker, 955 So. 2d 988, 996 (Ala. 2006)).
Discussion
Woods Construction raises several arguments on appeal as to why
§ 34-14A-14(d) does not bar it from bringing claims to recover the cost of
constructing the metal building. However, we cannot consider the merits
of its arguments because, as explained below, the circuit court's Rule
54(b) certification was improper and, thus, Woods Construction's appeal
is due to be dismissed.
Although neither party challenges on appeal the appropriateness of
the circuit court's Rule 54(b) certification, it is well settled that this Court
is " ' " duty bound to notice ex mero motu the absence of subject-matter
jurisdiction." ' " Rogers, 387 So. 3d at 135 (quoting Baldwin Cnty. v. Bay
Minette, 854 So. 2d 42, 45 (Ala. 2003), quoting in turn Stamps v.
Jefferson Cnty. Bd. of Educ., 642 So. 2d 941, 945 n.2 (Ala. 1994)).
8 SC-2024-0253
"Without subject-matter jurisdiction, this Court has no authority to
consider the merits of an appeal." Id. (citing Loachapoka Water Auth.,
Inc. v. Water Works Bd. of Auburn, 74 So. 3d 419, 422 (Ala. 2011)).
Accordingly, before this Court can reach the merits of any of Woods
Construction's arguments on appeal, we must first determine whether
the circuit court properly certified its summary judgment in favor of the
Jordans as final under Rule 54(b). See Loachapoka, 74 So. 3d at 422.
Generally, a trial court's judgment is not final unless it resolves all
claims against all parties. Cox v. Parrish, 292 So. 3d 312, 315 (Ala. 2019).
Rule 54(b) provides a limited exception to this general rule and states, in
relevant part:
"When more than one claim for relief is presented in an action, whether as a claim, counterclaim, cross-claim, or third-party claim, or when multiple parties are involved, the court may direct the entry of a final judgment as to one or more but fewer than all of the claims or parties only upon an express determination that there is no just reason for delay and upon an express direction for the entry of judgment."
Nevertheless, "[b]ecause this Court disfavors piecemeal appellate review,
we have consistently cautioned trial courts that certifications under Rule
54(b) should be entered only in exceptional cases." Cox, 292 So. 3d at 315.
This Court has previously discussed factors to be taken into account
9 SC-2024-0253
when reviewing a judgment certified as final pursuant to Rule 54(b) to
determine whether the trial court exceeded its discretion in finding that
there was "no just reason for delay." For example, in some cases, we have
considered whether " ' the issues in the claim being certified and a claim
that will remain pending in the trial court " ' are so closely intertwined
that separate adjudication would pose an unreasonable risk of
inconsistent results.' " ' " Rogers, 387 So. 3d at 135-36 (quoting Schlarb v.
Lee, 955 So. 2d 418, 419-20 (Ala. 2006), quoting in turn Clarke-Mobile
Counties Gas Dist. v. Prior Energy Corp., 834 So. 2d 88, 95 (Ala. 2002),
quoting in turn Branch v. SouthTrust Bank of Dothan, N.A., 514 So. 2d
1373, 1374 (Ala. 1987)).
This Court has also considered " 'whether the resolution of claims
that remain pending in the trial court may moot claims presented on
appeal.' " Rogers, 387 So. 3d at 136 (quoting Lighting Fair, Inc. v.
Rosenberg, 63 So. 3d 1256, 1264 (Ala. 2010)). For example, in Lighting
Fair, a dispute arose among certain materialmen, the homeowners, a
construction company, and a bank regarding the alleged failure to pay
for the materials used in a home-construction project. The homeowners
asserted cross-claims against the construction company and the bank.
10 SC-2024-0253
Relying on a provision in the construction contract, the trial court ordered
the homeowners to arbitrate their claims against the construction
company. While the arbitration proceeding was pending, the trial court
entered a summary judgment in favor of the bank and the homeowners
on the materialmen's claims and in favor of the bank on the homeowners'
cross-claims. The trial judge certified its summary judgments as final
pursuant to Rule 54(b). This Court concluded that the resolution of the
arbitration proceeding could cause some of the claims at issue on appeal
to become moot. Accordingly, this Court held that the trial court had
erred in certifying its judgments as final and dismissed both appeals.
Our Court has maintained this position in some of our more recent
decisions. See, e.g., Rogers, 387 So. 3d at 136 (holding that, because the
resolution of the appellant's claim against the employee still pending in
trial court could moot the appellant's claim against the employer asserted
under a theory of respondeat superior, the trial court had erred in
certifying its summary judgment in favor of the employer as final); Cox,
292 So. 3d at 316 (holding that, because the resolution of the appellees'
declaratory-judgment claim still pending in trial court could moot the
appellant's counterclaim, the trial court had exceeded its discretion in
11 SC-2024-0253
certifying judgment dismissing that counterclaim as final pursuant to
Rule 54(b)).
As stated previously, here, Woods Construction sued the Jordans,
asserting breach-of-contract and unjust-enrichment claims arising out of
the Jordans' alleged failure to pay for work completed by the company.
The Jordans filed two counterclaims against Woods Construction -- one
alleging breach of contract and one alleging negligence -- based on the
company's alleged failure "to properly comply with the terms of the
contract and … to perform the construction work in a good, proper, and
workmanlike manner." According to the Jordans, because Woods
Construction had failed to perform the agreed-upon work in a proficient
manner, their duty to pay under the contract was never triggered.
Thus, both the claims asserted by Woods Construction and the
counterclaims asserted by the Jordans concern the same contract, the
same construction work, and the same buildings on the same real
property. In other words, the factual underpinnings of Woods
Construction's adjudicated claims against the Jordans are the same as
those of the Jordans' unadjudicated counterclaims against Woods
Construction, and, therefore, their claims are "inextricably intertwined"
12 SC-2024-0253
with one another. See Fuller v. Birmingham-Jefferson Cnty. Transit
Auth., 147 So. 3d 907, 913 (Ala. 2013) (citing Speigel v. Trustees of Tufts
Coll., 843 F.2d 38, 45 (1st Cir. 1988)) (holding that an appeal from a
judgment certified as final pursuant to Rule 54(b) was not appropriate
when "[t]he factual underpinnings of the adjudicated claims are the same
as those of the unadjudicated counterclaim").
Moreover, as in Lighting Fair, supra, the circuit court's resolution
of the Jordans' counterclaims may moot Woods Construction's arguments
on appeal because, in deciding the Jordans' counterclaims, the circuit
court must determine whether Woods Construction first breached the
contract by improperly constructing the Jordans' house and metal
building. If Woods Construction is found to have breached the contract
by improperly constructing the Jordans' house and metal building, then
Woods Construction would necessarily lose on the merits of its own
claims, arising from its allegation that the Jordans failed to pay for the
potentially faulty construction. As a result, Woods Construction would
have no claims that could potentially be barred by its failure to obtain
the residential-home-builder's license, which is the basis on which the
circuit court entered the summary judgment. In other words, Woods
13 SC-2024-0253
Construction's arguments on appeal would be moot and there would be
no need for us to review the circuit court's summary judgment in favor of
the Jordans on the basis that Woods Construction, as a residential-home
builder without the proper license, was barred from bringing a civil action
against the Jordans to enforce the contract.
Because the review of the issues decided by the circuit court on
summary judgment would require this Court to resolve claims that are
potentially moot, we conclude that the circuit court exceeded its
discretion in finding that there was no just reason for delay and in
certifying its judgment as final pursuant to Rule 54(b). Accordingly,
Woods Construction's appeal is due to be dismissed as having been taken
from a nonfinal judgment. Dzwonkowski v. Sonitrol of Mobile, Inc., 892
So. 2d 354, 363 (Ala. 2004) ("A nonfinal judgment will not support an
appeal.").
Conclusion
Because the circuit court's Rule 54(b) certification was improper,
we dismiss the appeal.
APPEAL DISMISSED.
Parker, C.J., and Shaw, Wise, Bryan, Mendheim, Stewart, and
14 SC-2024-0253
Mitchell, JJ., concur.
Sellers, J., concurs in the result.