Jerry Brooks v. Melissa Ibsen

CourtCourt of Appeals of Tennessee
DecidedJune 25, 2001
DocketE2000-02870-COA-R3-CV
StatusPublished

This text of Jerry Brooks v. Melissa Ibsen (Jerry Brooks v. Melissa Ibsen) is published on Counsel Stack Legal Research, covering Court of Appeals of Tennessee primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Jerry Brooks v. Melissa Ibsen, (Tenn. Ct. App. 2001).

Opinion

IN THE COURT OF APPEALS OF TENNESSEE AT KNOXVILLE Assigned on Briefs June 25, 2001 Session

JERRY BROOKS v. MELISSA TERRY IBSEN, ET AL.

Appeal from the Chancery Court for Union County No. 3605 Billy Joe White, Chancellor

FILED AUGUST 24, 2001

No. E2000-02870-COA-R3-CV

Jerry Brooks (“Plaintiff”) contracted with Joe Ibsen d/b/a Century Wholesale Pool Supply, Inc. (“Defendant”), for the installation of a swimming pool. Plaintiff received a limited warranty. After the swimming pool developed several cracks and the parties could not reach agreement on the proper way to repair the pool, Plaintiff had the pool repaired in the manner recommended by an engineer he had retained. This lawsuit followed. The Trial Court awarded Plaintiff $61,531.28 in damages. We reduce the judgment to $51,371.28 and affirm as modified.

Tenn. R. App. P. 3 Appeal as of Right; Judgment of the Chancery Court Affirmed as Modified; Case Remanded.

D. MICHAEL SWINEY, J., delivered the opinion of the court, in which HERSCHEL P. FRANKS , J., and CHARLES D. SUSANO, JR., J., joined.

Steven G. Shope, Knoxville, Tennessee, for the Appellants Melissa Terry Ibsen, Joe Ibsen d/b/a Century Wholesale Pool Supply, Inc., and Century Pool Supply Company.

David H. Stanifer, Tazewell, Tennessee, for the Appellee Jerry Brooks. OPINION

Background

Plaintiff contracted with Defendant for the purchase and installation of a swimming pool. Plaintiff received a limited warranty wherein Defendant guaranteed “all pool work to be free from defect for one year from date of completion when subject to normal use and care . . . .” Defendant agreed to remedy “any breach without charge.” Plaintiff began experiencing problems with the swimming pool shortly after completion, eventually resulting in this lawsuit. In his complaint, Plaintiff alleges breach of contract and a violation of the Tennessee Consumer Protection Act.

Plaintiff testified that the contract price for the pool was approximately $36,960, but that he had additional work done which put the price over $40,000.00. All payments were made to Defendant except the final payment of $3,660.00. According to Plaintiff, before he and his family even used the pool, they noticed several cracks which Plaintiff estimated to be a total of 100 lineal feet. The following weekend, Defendant went to Plaintiff’s residence to inspect the pool. At that time, Defendant believed that the cracks were in the outer plaster surface and not in the underlying concrete. Defendant told Plaintiff he would take care of the problem. Plaintiff and his architect met with Defendant and an agreement was worked out on how to fix the pool. The agreement provided, in relevant part, that at the end of the summer, the cracks and any leaks would be repaired. If plaster crack repairs were not acceptable to Plaintiff, an epoxy coating would be provided at no additional cost. While Defendant originally believed the cracks were not in the gunite and only affected the outer plaster, the agreement stated that the gunite would be inspected for cracks when the repairs were undertaken.

According to Plaintiff, when the pool eventually was inspected, it was determined that the cracks went through to the gunite. Plaintiff gave Defendant permission to begin repairing the pool. Defendant continued to assure Plaintiff the problem would be resolved. While Defendant was in the process of replacing the pool bottom, but before the new concrete had been poured, Plaintiff had some concerns about how the pool was being repaired. Plaintiff’s architect inspected the pool and recommended that Plaintiff contact “someone else.” Plaintiff then contacted Jack Llewellyn (“Llewellyn”), an engineer with Foundation Systems Engineering, P.C. Llewellyn did not agree with Defendant on the proper way to repair the pool. Llewellyn’s proposed method for repairing the pool was much more expensive. Plaintiff then sent a letter to Defendant inviting him to obtain the services of an engineer. Plaintiff also suggested that if Defendant did obtain the services of an engineer, and the two engineers could not reach an agreement on how to proceed, then the two engineers could select a third engineer to resolve the matter.

When the parties were unable to reach an agreement on what was necessary to repair the pool properly, Plaintiff obtained two estimates and had the pool repaired according to the recommendation of Llewellyn, utilizing the company that gave the lower estimate. Llewellyn had some concerns about movement in the walls of the pool and recommended that the pool be

-2- completely redone. In order to reduce the cost of having the walls of the pool torn out and replaced, Plaintiff had a new pool installed over the old pool, resulting in a somewhat smaller pool. Plaintiff also incurred some excavation costs because dirt needed to be hauled off once the original pool bottom was removed. The contract price to have the new pool installed over the old pool was $32,236.00. The excavation costs were $10,136.89, which included having the dirt removed. Plaintiff also paid Llewellyn a total of $16,658.44. According to Plaintiff, this was for “all of their total engineering systems and design work, everything that they did towards finding the problem and making recommendations for rebuilding the pool, and studies. I think they did some core drilling.” Plaintiff’s architect was paid $3,931.05. Plaintiff also incurred $1,003.94 in expenses for the purchase and installation of a pool shower and faucet as called for in the original contract with Defendant but which had not been installed. Plaintiff also spent $282.39 for electrical work which Defendant never completed. Plaintiff further claimed that he had to replace part of the concrete deck because of cracking and had other parts of the deck reworked because it was defective, which cost an additional $4,008.95. Plaintiff’s total claimed damages were $68,257.66, excluding his claim for attorney fees.

At trial, Defendant stipulated that Llewellyn was a licensed engineer and qualified as an expert. Llewellyn testified that he specializes in geo-technical soils and foundations. Llewellyn tested the soil the day before the concrete was to be poured by Defendant in hopes of repairing the pool. Llewellyn stated that the soil was soft in consistency and was not suitable to support a concrete slab. According to Llewellyn, a portion of the pool was bearing directly on the soft soil and had settled, causing the cracks to develop with resulting water loss. Llewellyn testified that Plaintiff needed to either completely remove and replace the pool, or build a new pool inside the existing pool. Regardless of which option was chosen, he felt that the soft soil would have to be removed or the same problem would develop again. Llewellyn also concluded that the walls of the original pool were not thick enough, and he believed the pool walls may have moved. Merely patching or reinforcing the existing walls would not be sufficient due to the inadequate design of the walls. Llewellyn testified that he disagreed with several of the recommendations made by Defendant’s expert, Mr. R.A. Nack (“Nack”)1. For example, Nack proposed underpinning only a section of the pool with rock, which would have resulted in a portion of the pool being on rock and another portion on soil. This could result in more cracks because the pool would settle differently if it rested on two different surfaces.

Defendant testified that initially he believed the cracks were cosmetic. Once the pool started losing water, however, he knew the cracks were in the concrete bottom. Defendant does not know what caused the cracks in the pool. Defendant has repaired cracks in swimming pools on numerous occasions. The procedure he uses to repair cracks is to cut back the plaster to determine if the cracks extend down to the gunite.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Brooks v. Brooks
992 S.W.2d 403 (Tennessee Supreme Court, 1999)
Action Ads, Inc. v. William B. Tanner Co.
592 S.W.2d 572 (Court of Appeals of Tennessee, 1979)
Morrow v. Bobbitt
943 S.W.2d 384 (Court of Appeals of Tennessee, 1996)
Nelson v. Wal-Mart Stores, Inc.
8 S.W.3d 625 (Tennessee Supreme Court, 1999)
Town of Alamo v. FORCUM-JAMES COMPANY
327 S.W.2d 47 (Tennessee Supreme Court, 1959)
Barnhill v. Barnhill
826 S.W.2d 443 (Court of Appeals of Tennessee, 1991)

Cite This Page — Counsel Stack

Bluebook (online)
Jerry Brooks v. Melissa Ibsen, Counsel Stack Legal Research, https://law.counselstack.com/opinion/jerry-brooks-v-melissa-ibsen-tennctapp-2001.