Jereb v. Riss & Co.

149 N.E.2d 12, 78 Ohio Law. Abs. 65, 1958 Ohio App. LEXIS 938
CourtOhio Court of Appeals
DecidedMarch 13, 1958
DocketNo. 24183
StatusPublished

This text of 149 N.E.2d 12 (Jereb v. Riss & Co.) is published on Counsel Stack Legal Research, covering Ohio Court of Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Jereb v. Riss & Co., 149 N.E.2d 12, 78 Ohio Law. Abs. 65, 1958 Ohio App. LEXIS 938 (Ohio Ct. App. 1958).

Opinions

OPINION

By HORNBECK, J.

This is an appeal from orders of the trial judge in refusing to sustain motions of defendant to direct a verdict or enter judgment in its behalf at the end of the plaintiff’s case and at the end of all of the evidence and to sustain defendant’s motion for judgment notwithstanding that the jury failed to reach a verdict.

Plaintiff’s action was for damages for the wrongful death of her decedent claimed .to have been caused by the negligence of the defendant. Four specifications of negligence were alleged; three were submitted to the jury. The jury reported that it could not agree and was discharged.

Five errors are assigned which we will state as we discuss them.

At the outset, we note that there is dispute in the record on every material issue in this case. In deciding the assignments, we consider the evidence in its most favorable light to the plaintiff.

The first assignment of error is: There was no proof that Riss was negligent.

Was there an issue as to the negligence of the defendant. Edward Ryan testified for the plaintiff. He was a guard for the Cleveland Cap Screw which occupied a building located immediately across the street to the north and east of the place on the street where plaintiff’s decedent was. struck. On the night of November 27, 1952, Thankksgiving, he was on the ground floor of the west end of the building in which he [67]*67worked. He says that there was a barricade extending into and along the street; that decedent was walking around it, about one foot from the curb; that he had proceeded from 15 to 20 feet to the east when he was struck; that when he stepped off the curb, two cars were approaching from the west at a distance of 300 feet; that when these cars were first seen, one was back of the other; that they were moving very fast and seemed to be racing. When they had reached a distance of about 300 feet from decedent, the car to the rear passed the car ahead on its right, swerved to the right and to the curb, struck plaintiff’s decedent, whose body went up to the windshield, was thrown about 100 feet into' a field and was killed almost instantly.

It is undisputed that in October and November of 1952, the defendant, a transport company, was a lessee of one-half of the premises at 17800 Gt. Clair Avenue, Cleveland, Ohio. The lessor was the Transport Manufacturing & Equipment Company, a non-resident owner of the property. There were other transport companies leasing the other half and operating their businesses on the property. The building on the property was about 1000 feet from St. Clair Avenue and in front of it was a large parking space. Because of a faulty condition of a west driveway from the street into the premises and a part of the parking space, it was determined that it should be replaced. Incident to this work, it became necessary to tear up the apron and sidewalk in front of the premises and it also had to be replaced. The condition of the sidewalk before its replacement does not definitely appear. The contract for the job was, according to the testimony of defendant, let to an independent contractor by the owner, Transport Manufacturing & Equipment Company, and paid for by it prior to the death of plaintiff’s decedent.

After work was begun on the job, application was made to the City of Cleveland, Department of Public Service, for a permit to lay the sidewalk. Of course, no permit was required as to the laying of the driveway on the premises proper. This application for a permit was made and signed by “H. P. White, Term. Mgr.” (meaning terminal manager), for defendant company. The permit was issued authorizing “Rise and Company to lay concrete sidewalk or driveway on 17800 St. Clair Avenue * * * owned by same,” the amount of the work to be 250 square feet. (Emphasis ours.) At the end of this permit and as a part thereof, was this language:

“The undersigned hereby agrees to all conditions of this permit as above stated, and to provisions on reverse side of this permit.”
“The city to be held harmless for all damage to person or property, and from all costs that may, in any manner, or at any time arise through the granting of this permit, or in the performance of any work done under the same.”

Ryan said that a barricade 20 to 25 feet long was placed in front of the driveway of the premises into the terminal and another on both !■ .les cf the sidewalk 6 to 8 feet long extending about one foot beyond 1 ■? curb and into the street.

The claim of the plaintiff is that the “defendant managed, con[68]*68trolled and operated the premises” in front of which the barricade was placed and was obligated to replace the sidewalk and in so doing caused a dangerous condition to obtain in the three particulars asserted in the petition.

The barricade, as erected, required pedestrians, when they came up to it from the west moving east, either to go around to the south end over the property of the defendant, or to walk around the barricade to the north and into the street. The nearest cross-walk to the west was about one-half mile away. There was testimony that the way around and over the property to the south of the sidewalk was difficult to traverse because of deep ruts and mud. Thus, pedestrians had to make a choice as to their route around the barricades.

It cannot be said, as a matter of law, that the decedent did not have the right to walk in front of the barricade where he was killed which would take him into the street. Nor, can it be said, as a matter of law, that there was no issue for the jury whether the barricade, as constructed, created a dangerous condition for pedestrians having to pass around it. If the defendant was in possession and control of the premises and under legal obligation to construct the sidewalk, and in so doing an independent contractor was employed to lay this sidewalk and in placing the barricades requiring pedestrians to walk into the street created a dangerous condition, defendant would not be absolved, as a matter of law, from all liability for that condition.

Warden v. Penna. Rd. Co., 123 Oh St 304, 175 N. E. 207:

“1. Where a person employs a contractor upon construction in a place where the public may lawfully pass which work requires precautions to be taken to safeguard the public against danger, such person owes a duty to see that reasonable precautions are taken, and becomes liable jointly with the contractor for the failure of the latter to exercise due care.
“2. Whether danger to the public is likely to attend the doing of the work is a question of fact to be submitted to the jury under proper instructions.”

To like effect, Richman Brothers Company v. Miller, 131 Oh St 424, 3 N. E. 2d 360:

“3. The duty to refrain from interfering with the right of the public to safe and unimpeded use of highways and street is one of which an employer cannot divest himself by committing the work to a contractor.”

The second assignment of error is that “Plaintiff failed to rebut inferences that decedent was guilty of contributory negligence or assumption of risk.”

Assumption of risk is not in this case. Logsdon v. Main-Nottingham Investment Company, 103 Oh Ap 233, 141 N. E. 2d 216, and cases there cited.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Logsdon v. Main-Nottingham Investment Co.
141 N.E.2d 216 (Ohio Court of Appeals, 1956)
Hrovat v. Cleveland Ry. Co.
180 N.E. 549 (Ohio Supreme Court, 1932)
Gedra v. Dallmer Co.
91 N.E.2d 256 (Ohio Supreme Court, 1950)
Warden v. Pennsylvania Rd.
175 N.E. 207 (Ohio Supreme Court, 1931)
Richman Bros. v. Miller
3 N.E.2d 360 (Ohio Supreme Court, 1936)
Hamden Lodge No. 517 v. Ohio Fuel Gas Co.
189 N.E. 246 (Ohio Supreme Court, 1934)
Taylor v. Standard Oil Co.
130 N.E.2d 391 (Ohio Court of Appeals, 1954)

Cite This Page — Counsel Stack

Bluebook (online)
149 N.E.2d 12, 78 Ohio Law. Abs. 65, 1958 Ohio App. LEXIS 938, Counsel Stack Legal Research, https://law.counselstack.com/opinion/jereb-v-riss-co-ohioctapp-1958.