Jeppesen v. FCL Builders, LLC

2026 IL App (1st) 250171-U
CourtAppellate Court of Illinois
DecidedMarch 27, 2026
Docket1-25-0171
StatusUnpublished

This text of 2026 IL App (1st) 250171-U (Jeppesen v. FCL Builders, LLC) is published on Counsel Stack Legal Research, covering Appellate Court of Illinois primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Jeppesen v. FCL Builders, LLC, 2026 IL App (1st) 250171-U (Ill. Ct. App. 2026).

Opinion

2026 IL App (1st) 250171-U SIXTH DIVISION

March 27, 2026

No. 1-25-0171

NOTICE: This order was filed under Supreme Court Rule 23 and is not precedent except in the limited circumstances allowed under Rule 23(e)(1). ______________________________________________________________________________

IN THE APPELLATE COURT OF ILLINOIS FIRST DISTRICT ______________________________________________________________________________ CANDI JEPPESEN, as Administrator of the estate of Eric ) Appeal from the Circuit Court Jeppesen, deceased, ) of Cook County. ) Plaintiff-Appellee, ) ) v. ) ) No. 22 L 861 FCL BUILDERS, LLC, ) ) Honorable Defendant-Appellant. ) Patrick J. Sherlock, ) Judge, presiding. ) FCL BUILDERS, LLC ) ) Third-Party Plaintiff-Appellant ) v. ) ) INDUSTRIAL CORK COMPANY, INC. ) ) Third-Party Defendant-Appellee ) _______________________________________________ ) No. 1-25-0171

PRESIDING JUSTICE C.A. WALKER delivered the judgment of the court. Justices Hyman and Gamrath concurred in the judgment.

ORDER

¶1 Held: We dismiss the appeal because appellant’s claim is moot.

¶2 In the wrongful death suit giving rise to this appeal, plaintiff-appellee Candi Jeppesen (as

administrator of the estate of her deceased husband, Eric Jeppesen) sued defendant-appellant FCL

Builders, LLC (FCL), following a workplace accident that led to Eric’s death. FCL filed a third-

party complaint against appellee Industrial Cork Company, Inc. (Cork), Eric’s employer, seeking

contribution per section 2 of the Illinois Joint Tortfeasor Contribution Act (the Act) (740 ILCS

100/2 (West 2022)). The third-party suit also involved claims for breach of an alleged subcontract

between Cork and FCL. Alongside her suit against FCL, Candi maintained a worker’s

compensation case against Cork, which Cork and Candi ultimately agreed to settle. Following that

settlement, Cork moved for a good faith finding under section 2(c) of the Act (740 ILCS 100/2(c)

(West 2022)), along with a corresponding request to dismiss FCL’s contribution claim per the Act.

The circuit court granted the motion and dismissed FCL’s contribution claim against Cork

accordingly, prompting this appeal. For the reasons below, the appeal is dismissed.

¶3 BACKGROUND

¶4 Candi, as special administrator of Eric’s estate, filed the opening complaint in this matter

on January 27, 2022, naming FCL as the lone defendant. Therein, she raised claims of wrongful

death, alleging that FCL was “in charge” of a construction project on the 3400 block of East 118th

Street in Chicago, on which FCL contracted with Cork, Eric’s employer, for certain work on the

project. Candi alleged that Eric “fell to his death” on January 7, 2022, while working for Cork on

the FCL project. She further alleged the fall was the “direct and proximate result” of one or more

2 No. 1-25-0171

of a list of eleven alleged negligent acts by FCL, including failing to “provide adequate fall

protection” and the failure to provide adequate warnings and training. Candi amended the

complaint on April 18, 2022. While pursuing her claims against FCL, Candi also maintained a

worker’s compensation case against Cork.

¶5 On May 23, 2022, FCL filed a third-party complaint against Cork, raising a contribution

claim. In support, FCL alleged that Eric was at all relevant times “under the direction, supervision,

and control of Cork.” By virtue of this, Cork owed a duty of care to Eric, but breached that duty

by acting negligently in eight distinct ways, including by creating a dangerous condition and failing

to adequately train, warn, or supervise. These actions entitled FCL “to contribution from Cork in

an amount commensurate with its degree of fault.”

¶6 FCL filed an amended third-party complaint on October 31, 2022, adding claims II and III

for breach of an alleged subcontract between FCL and Cork.

¶7 During the ensuing litigation, Cork moved to dismiss claims II and III on multiple occasions,

which the circuit court granted, allowing FCL to file amended complaints each time. In these

motions, Cork maintained that no valid subcontract existed between FCL and Cork. Ultimately,

on September 26, 2024, after Cork moved to dismiss counts II and III in FCL’s third amended

third-party complaint, the court ordered that FCL’s contract claims (and the issue of whether a

contract existed) be mediated. FCL’s contribution claim remained pending.

¶8 On November 12, 2024, Cork moved for a good faith finding and dismissal of FCL’s

contribution claim, relaying that Cork and Candi had reached a settlement in the worker’s

compensation action. The terms of the settlement were “a lump sum” of $1 million and a waiver

of Cork’s workers’ compensation lien (purportedly over $200,000). This constituted “adequate

consideration” to satisfy the Act, which, Cork argued, meant the circuit court should find the

3 No. 1-25-0171

settlement in good faith and then dismiss FCL’s contribution claim as barred by the Act. See 740

ILCS 100/2(c) (West 2022).

¶9 The circuit court granted Cork’s motion on November 14, 2024. During argument on the

motion, FCL’s attorney objected and asked for a briefing schedule. The court responded, “I don’t

think we need briefing on this.” Cork’s attorney stated that the settlement was “in furtherance of”

the Act’s goals of “equitable apportionment” and “encouragement of settlements.” FCL’s counsel

responded that it had its “own separate claims against” Cork that went “well beyond” the Act. The

court concluded, “I have reviewed the arguments of counsel and the motion for good-faith finding.

The Court finds that the settlement was made in good faith and will grant the motion.” FCL’s

attorney also relayed during the hearing that FCL had reached a settlement agreement with Candi.

¶ 10 FCL moved for reconsideration on December 13, 2024, arguing that the circuit court had

misapplied the law. In support, it contended Cork’s settlement did not sufficiently apportion

damages based on FCL’s and Cork’s relative culpability, in part because the alleged subcontract

included a waiver of Cork’s liability cap under Kotecki v. Cyclops Welding Corp., 146 Ill. 2d 155

(1991). FCL repeated the allegations in its third-party complaint that Cork was “responsible for

Eric’s actions and safety on the job site.” Finally, it described the facts of the case as “Eric

somehow went off the interstitial ceiling ledge while working within the scope of his employment

with Cork.” In light of this, FCL argued, it was not equitable that Cork paid only $1 million in its

settlement, while FCL paid the much larger sum of $6.5 million.

¶ 11 On January 2, 2025, the circuit court denied the motion to reconsider “for the reasons stated

on the record.” No transcript of this hearing appears in the record on appeal. FCL filed their notice

of appeal on January 31, 2025.

4 No. 1-25-0171

¶ 12 On February 14, 2025, Candi filed a petition to approve settlement, relaying that she had

reached settlement agreements with both FCL and Cork, both of which she attached to the petition.

The FCL settlement stated, in relevant part, that Candi understood and agreed that by signing the

document “she forever releases FCL Builders, LLC and Amerisure Mutual Insurance Company”

for the January 7, 2022 incident, but that the agreement was not to be construed as “releasing or

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Solimini v. Thomas
688 N.E.2d 356 (Appellate Court of Illinois, 1997)
Pearson Brothers Co. v. Allen
476 N.E.2d 73 (Appellate Court of Illinois, 1985)
Kotecki v. Cyclops Welding Corp.
585 N.E.2d 1023 (Illinois Supreme Court, 1992)
Bowers v. Murphy & Miller, Inc.
650 N.E.2d 608 (Appellate Court of Illinois, 1995)
Dixon v. Chicago & North Western Transportation Co.
601 N.E.2d 704 (Illinois Supreme Court, 1992)
Guerrero v. Sebastian Contracting Corp.
746 N.E.2d 846 (Appellate Court of Illinois, 2001)
People v. Wells
2023 IL 127169 (Illinois Supreme Court, 2023)

Cite This Page — Counsel Stack

Bluebook (online)
2026 IL App (1st) 250171-U, Counsel Stack Legal Research, https://law.counselstack.com/opinion/jeppesen-v-fcl-builders-llc-illappct-2026.