Jensen v. Union Paving Co.

229 P.2d 121, 103 Cal. App. 2d 164, 1951 Cal. App. LEXIS 1139
CourtCalifornia Court of Appeal
DecidedMarch 29, 1951
DocketCiv. No. 14482
StatusPublished
Cited by2 cases

This text of 229 P.2d 121 (Jensen v. Union Paving Co.) is published on Counsel Stack Legal Research, covering California Court of Appeal primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Jensen v. Union Paving Co., 229 P.2d 121, 103 Cal. App. 2d 164, 1951 Cal. App. LEXIS 1139 (Cal. Ct. App. 1951).

Opinion

PETERS, P. J.

—This is a case where the evidence, the findings and portions of the judgment are most confusing, ambiguous, and, in some respects, inconsistent. The facts are as follows:

Plaintiff L. C. Jensen and defendant Union Paving Co. are duly licensed contractors. Union, on August 10, 1946, [165]*165entered into a contract with South San Francisco to construct certain improvements for the city in accordance with certain plans and specifications. The defendant United Pacific Insurance Company executed a bond as surety for Union to guarantee payment by Union for materials, work or labor performed under the contract. The bond also provided for a reasonable attorney's fee. On August 24, 1946, Jensen, as a subcontractor, entered into a contract with Union to install the portion of the main improvement consisting of certain sewers and storm drains for a total contract price of $41,325.80. This contract is in the form of a letter signed by Jensen and accepted by C. L. Corson for Union. It reads as follows:

“Dear Sir:
“I agree to install sewers and storm drains in Brentwood, South San Francisco, for the following prices. [Here are set forth in detail the work and unit prices totalling $41,325.80.]
“These prices include furnishing all labor, materials and equipment necessary to install the work according to plans and specifications.
“Monthly progress payments in the amount of 90% of the work completed are to be made and final payment is to be made 30 days after the acceptance of the work by the engineer in charge.
Tours very truly,
L. C. Jensen”

The complaint alleges that Union failed to make the contract payments; that the reasonable value of the work done by Jensen, with extras, is $53,269.14; that $26,449.54 has been paid; that a balance of $26,819.60 is due and owing, plus a reasonable attorney !s fee. The second amended answer of the two defendants denies that Union failed to perform its part of the contract and alleges that Jensen performed only a part of his contract; that the reasonable value of the work performed by Jensen does not exceed $32,276.44, and that $30,661.19 has been paid to Jensen. The answer then, by way of “setoff and counterclaim” alleges that, in certain respects, Jensen breached his contract by refusing to perform and complete the work called for by the' contract, and that defendants were required to correct these defects to their damage in the amount of $6,308. The specific items, nine in number, are set forth in the pleading. Because some of these items will be referred to later in this opinion, they should here be summarized. They are:

1. Masonry work on all manholes and catchbasins was [166]*166installed below the required elevation and had to be corrected at a cost of $350.
2. Raising manholes at a cost of $783.83.
3. Cost of supplying missing manhole frames and covers— $127.12.
4. A trench over the 48-inch storm sewer was not back-filled in accordance with plans and specifications, and that portion which was on Hazelwood Drive and Maywood Way easterly settled. Jensen refused to remedy this, and Union removed the defective filling, rebackfilled and repaved at a cost of $2,448.35.
5. Jensen failed and refused to remove surplus material after backfilling the 48-inch sewer, and Union did so at a cost of $967.20.
6. Stakes were damaged by reason of the reexcavating of the 48-inch sewer, and had to be replaced at a cost of $36.
7. Catchbasins on two corners of Maywood Way and Wild-wood Drive were not constructed to conform with the lines and grades as shown on the plans. Jensen refused to correct this, and .Union rebuilt them to conform to the plans at a cost of $112.10.
8. Jensen damaged certain sidewalks, which had to be corrected at a cost of $85.
9. The backfilling in connection with the trench over the 48-inch sewer, at the extreme northwest portion of Wildwood Drive at the parking lot near Hazelwood Drive settled due to improper compaction, which Union had to remedy at a cost of $1,398.40.

On these pleadings the cause proceeded to trial. At the commencement of the trial the parties stipulated that there was a duly executed contract between the city and Union, a copy of which was admitted into evidence; that the defendant insurance company executed a material and labor bond which provides for a reasonable attorney’s fee; that all work performed and here involved was performed pursuant to the Improvement Act of 1911; and that plaintiff had filed a verified claim with the city. At the trial the main issues revolved around the precise amount already paid to Jensen, the necessity for and the value of certain work performed by Union in correcting what it claimed were defects in Jensen’s work, and the value of the work performed by Jensen. The evidence on these issues was most confusing. The trial judge ordered the plaintiff to prepare proposed findings, and then filed a memorandum opinion in which he stated, in part:

“. . . The Court feels that the only reason Union Paving [167]*167Co. did not make payments to Plaintiff is because of Plaintiff’s failure to complete the work; and, in the opinion of the Court, the amount due Plaintiff could not be determined until a trial had been had. However, the Court feels that Plaintiff is entitled to the fair value of the work done by him after deducting credits to which Defendant is entitled which net sum is the amount of $10,069.05.
“ Therefore, the Court will enter judgment for Plaintiff for $10,069.05 plus an attorney fee in the sum of $1,000.00, costs and interest from the date of entry of judgment.”

Findings were prepared and signed and judgment entered in favor of plaintiff on July 27, 1949, for $10,069.05 plus the $1,000 attorney’s fee. Notice of entry of judgment was mailed to defendants July 29, 1949. On August 8, 1949, defendants moved for a new trial on the grounds of insufficiency of the evidence, that the decision is against the law, errors in law, and newly-discovered evidence. The motion was supported by affidavit, and plaintiff filed a counter affidavit. The court failed to pass on this motion for a new trial within 60 days from the service of notice of the entry of judgment as required by section 660 of the Code of Civil Procedure. After the 60-day period had expired the trial court attempted to reopen the case by a minute order dated October 3, 1949. That order reads as follows:

“ (Motion for a New Trial heretofore submitted)
“In lieu of granting a new trial, the court vacates and sets aside the findings and judgment and reopens the case for further proceedings and the introduction of additional evidence on (1) the sewer repair bill in the sum of $1,398.40, (2) the payments received by check by plaintiff and (3) the reasonable costs of remedying the other items of work referred to in Par. VIII (8) of defendants’ 2nd amended answer. Deft, are granted leave to further amend said answer by pleading said items and the alleged reasonable costs of remedying same.”

This order was ineffective.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Estate of Shepard
221 Cal. App. 2d 70 (California Court of Appeal, 1963)
Snapp v. State Farm Fire & Casualty Co.
206 Cal. App. 2d 827 (California Court of Appeal, 1962)

Cite This Page — Counsel Stack

Bluebook (online)
229 P.2d 121, 103 Cal. App. 2d 164, 1951 Cal. App. LEXIS 1139, Counsel Stack Legal Research, https://law.counselstack.com/opinion/jensen-v-union-paving-co-calctapp-1951.