Jenks v. Daniel

7 N.W.2d 286, 304 Mich. 239, 1943 Mich. LEXIS 439
CourtMichigan Supreme Court
DecidedJanuary 4, 1943
DocketDocket No. 110, Calendar No. 42,182.
StatusPublished
Cited by2 cases

This text of 7 N.W.2d 286 (Jenks v. Daniel) is published on Counsel Stack Legal Research, covering Michigan Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Jenks v. Daniel, 7 N.W.2d 286, 304 Mich. 239, 1943 Mich. LEXIS 439 (Mich. 1943).

Opinions

Stake, J.

Defendant appeals from a decree determining that his material and labor lien against' plaintiff’s property was void and determining the amount of his claim against plaintiff to be $1,624.47.

On August 31, 1940, plaintiff entered into a written contract with defendant, a general building contractor, for the construction of a four-store building on certain land owned by plaintiff in Port Pluron. The contract (prepared by an architect) provided that defendant would furnish all work and materials and “do everything required by this agreement, the general conditions of the contract, the specifications and the drawings.” The contract also provided, in part:

“It is understood and agreed that time is the essence of this contract and that work shall be commenced immediately upon the execution thereof and that the building shall be completed and final certificate of architect issued within 90 days from date hereof. All expediting shall be the contractor’s responsibility. * * *
“The owner shall pay the contractor for the performance of the contract, subject to additions and deductions provided therein, in current funds as follows:
‘ ‘ Thirty thousand and no/100 dollars. * * *
“Payment shall be made in full upon completion of building and issuing of architect’s certificate.
“If owner decides to place a construction loan on this building and make payments to the contractor as follows: $10,000 when roof is on; $10,000 upon *242 completion of plastering and balance at completion of building, the owner is to receive a credit of $1,000 from contract price. * * *
“Before issuance of final certificate the contractor shall submit evidence satisfactory to the architect that all pay rolls, material bills, and other indebtedness connected with'the work have been paid.
“If after the work has been substantially completed, full completion thereof is materially delayed through no fault of the contractor, and the architect so certifies, the owner shall, upon certificate of the architect, and without terminating the contract, make payment of the balance due for that portion of the work fully completed and accepted. Such payment shall be made under the terms and conditions governing final payment, except that it shall not constitute a waiver of claims. * # *
“Whereas certain changes of plans as drawn have been discussed and agreed upon and plans are now in the contractor’s hands pending the incorporation of said changes therein; now, therefore, it is understood and agreed that the supervising architect shall have final and complete authority to approve or disapprove of the revisions and changes in the plans. # * *
“Contractor agrees to have on the job at all times ' during the construction, when contractor is not personally present, a foreman with the express authority and direction of contractor to receive and carry out instructions of the supervising architect. ’ ’

To finance the cost of such building plaintiff obtained a first mortgage “construction loan” from an insurance company, and the evidence shows that defendant knew of such method of financing. Defendant commenced construction work in September, 1940. The roof having been completed, plaintiff, in accordance with the contract, on November 15,1940, paid defendant $10,000. On December 5, 1940, the plastering having been finished, plaintiff paid de *243 fendant the further sum of $10,000. That part of the building referred to as stores three and four was completed by December 7,1940. In April, 1941, plaintiff made additional payments amounting to $4,000, which made a total of $24,000 paid to defendant on the contract price of $30,000.

The insurance company which made the construction loan required that an architect from Detroit do the architectural work. A Detroit architect and defendant, a Detroit contractor, accordingly were employed. Plaintiff’s son acted as her agent throughout the contract negotiations and during the building construction. Plaintiff als.o employed a supervising architect from Port Huron. A representative of the Detroit company, which arranged for plaintiff’s construction loan, also acted as plaintiff’s agent in renting the stores in the building and in connection with certain phases of the construction work.

It appears that soon after the contract was made in August, 1940, trouble arose between the parties. There were many changes in the plans and specifications for construction of the building. There were delays in the construction, and the parties blamed each other for such delays. There were disputes as to extras charged by defendant and as to credits claimed by plaintiff. During the winter of 1941 there was trouble between the parties over changes in the building plans, plaintiff’s alleged failure to make further payments, defendant’s failure to complete the building, the unpaid bills of subcontractors, and also over the quality of defendant’s construction work. The building had not been entirely completed by April 1, 1941, and on April 16th plaintiff wrote defendant as follows:

“Your refusal to come to Port Huron to supervise the finishing of the last store, and your obvious *244 hindrance to my effort to complete the job myself has placed me in the position of having to treat your contract as being breached.
“From the very beginning, you have broken the contract by your failure to provide the adequate supervision specifically set forth in the contract. By reason of this breach, the job has dragged and it has been necessary for my son and the architect to supply the supervision which you have failed to give.
“Early last week you were made an additional payment of $4,000, not required by the contract, but given with the understanding that you would cooperate by immediately preparing the last store for its tenant. This, you have utterly failed to do.
“There are numerous other instances of breaches of your contract which I can and will cite you, if necessary.
“If you wish to discuss this matter any further, please contact Mr. Wyeth (supervising architect) by telephone and arrange an immediate appointment so that my son can be present and go over the matter with you. ’ ’

Subsequent to writing the above letter plaintiff completed certain minor details of the building construction at her own expense. On June 21,1941, defendant filed a material and labor lien against the land and building (3 Comp. Laws 1929, § 13105 ei seq. [Stat. Ann. § 26.285 et seq.]). In such lien he claimed that the sum of $4,998.44 was due from plaintiff for material and labor furnished. In his lien defendant stated “that the last of such labor was performed and materials were furnished on the 22d day of April, 1941.”

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Wayne Prosecuting Attorney v. National Memorial Gardens, Inc.
115 N.W.2d 312 (Michigan Supreme Court, 1962)
Yeager v. Daniel
15 N.W.2d 694 (Michigan Supreme Court, 1944)

Cite This Page — Counsel Stack

Bluebook (online)
7 N.W.2d 286, 304 Mich. 239, 1943 Mich. LEXIS 439, Counsel Stack Legal Research, https://law.counselstack.com/opinion/jenks-v-daniel-mich-1943.