Jeffrey Mfg. Co. v. Central Coal & Iron Co.

93 F. 408, 1899 U.S. App. LEXIS 2880
CourtU.S. Circuit Court for the District of Kentucky
DecidedApril 1, 1899
StatusPublished
Cited by4 cases

This text of 93 F. 408 (Jeffrey Mfg. Co. v. Central Coal & Iron Co.) is published on Counsel Stack Legal Research, covering U.S. Circuit Court for the District of Kentucky primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Jeffrey Mfg. Co. v. Central Coal & Iron Co., 93 F. 408, 1899 U.S. App. LEXIS 2880 (circtdky 1899).

Opinion

EVANS, District Judge.

On the 5th day of June, 1896, the complainant and defendant entered into a contract whereby the former was to furnish to the latter, f. o. b. cars at Central City and Ben[409]*409der. Ky., certain machinery and'mate-rials specified in the contract., for the agreed price of $15,500, to be paid in 00 equal monthly notes, to be dated 60 days from the starting of the power plant, provided that the entire plant was up to the requirements of the contract: and all but the first two of the notes were to hear interest from date, until paid, at the rate of 6 per cent, per annum. The parts of the contract important to be considered here are in the following language:

“The foundations, power house, and material for the same, will he put in pla»>, ready for the apparatus, by the purchaser. They shall he constructed from plans furnished by the Jeffrey Manufacturing Company, and shall meet vie approval of the company’s engineer. All steam and water connections shall be brought inside the building by the purchaser, and, unless otherwise «ogignated, shall bo continued to the apparatus of the purchaser. The Jeffrey Manufacturing Company will furnish expert attendants as follows: Expert to superintend installation and erection of plant, covering a time not to exceed tío days. The Jeffrey Manufacturing Company guaranty the above apparatus from inherent mechanical and electrical defects of labor and material, and will replace any part shown to he defective within one year from installation. The above apparatus will be delivered in season for starting the plant 90 days from date of approval of this contract.”

The contract was executed on the 5th day of June by the complainant, through its executive officer for this purpose, the vice president of the company, and by the defendant. On the next day the president of, the complainant began a vigorous and peremptory effort, by correspondence, and by at least one visit -to Louisville, to induce the defendant to modify the contract so as to make the notes agreed to be given for the price payable in gold. Otherwise, he demanded that there should be a cancellation of the instrument. Ho persistent was this effort, that it lasted up to about the 9th of August, 1896, though the defendant, from the beginning to the end of Hie effort, emphatically declined and refused to consent to any change or alteration of the agreement whatever. Meantime little or nothing was done* by either party towards performing the contract, except that a desultory correspondence was carried on between some of the subordinate officers of the respective companies about the plans to be furnished by the complainant. The evidence leaves it uncertain whether there was any great interest manifested on either side to secure a speedy or expeditious execution of the agreement; and the correspondence between the two subordinate officers, so far as could be seen, resulted only in the furnishing by the complainant of a blue-print plan for the foundations and the power house to be constructed for the reception of die machinery. A corrected copy of this seems to have reached the defendant about the 17th day of August, 1896. There is no dispute that the machinery and materials were supplied, nor fhal: they were put in working order at Render by October 14, 1896, and at Central City by the 31st day of the same month. It is admitted, and, indeed, proved by defendants’ witnesses, that the machinery and materials were ascertained to be fully up to the requirements of the contract, if not, indeed, superior do those requirements; and, after a thorough test, it was all fully accepted about the 18th of January, 1897.

[410]*410■Analyzing the contract between 'the parties, and considering it as far as it appears to be important to do so in this case, it will be seen that it required the complainant — First, to furnish the machinery and materials specified; second, to furnish plans for the construction of the foundations and power house; third, to furnish an expert to superintend the installation and erection of the plant, covering a time not to exceed 60 days; fourth, to deliver the apparatus in season for starting the plant 90 days from the approval of the contract; and, fifth, to guaranty the apparatus to be free from defects, etc. On the part of the defendant, it will be seen to require — First, that it put in place, ready for the apparatus, the foundations and power house, and furnish all material for the construction of the same; second, that the construction of the foundations and power house should be done according to plans to be furnished by complainant; and, third, that it should execute to complainant the 30 notes for the purchase money within 60 days from starting the plant. The proof is clear that the machinery and material were furnished by the complainant, but that they were not delivered in season for starting the plant 90 days from June 5, 1896. The proof shows that the machinery and materials furnished were- up to contract requirements, and satisfied the guaranty of the complainant. The proof is also clear that the plan for the construction of the foundation and power house was not supplied in accurate- form until in August, 1896, and that the expert to superintend the installation and erection of the plant was furnished by the cpmplainant. There can be no doubt, from the evidence, that defendant did not put in place, ready for the apparatus, the foundation and power house which it was to erect, and for which it alone was to furnish the material, until after the 5th day of September, 1896, and that its reason for doing this was largely, if not altogether, based upon the supposition that the correspondence between the presidents of the two companies in reference to a modification of the contract made it unwise for the defendant to proceed in this work, though, of course, some of the delay may have resulted from the failure of the complainant to supply the plans called for by the contract. It is a fact admitted upon the record that the defendant did not execute the notes representing the unpaid part of the price of the machinery and materials. Upon this state of facts, the complainant seeks the judgment of the court for $10,450, being the part of the agreed price which yet remains unpaid, and for which notes were not given, together with interest thereon from the time the notes should have been executed; and, upon the averments of the bill, it also claims a mechanic’s lien upon the property described in the pleadings, and prays for a judgment enforcing it. By its answer the defendant seeks to recoup the damages it claims to have sustained by reason of the failure of the complainant to deliver the machinery and material in season for starting the plant 90 days from the 5th of Juné, 1896. It insists that its failure' to construct the foundations and power house was the result of a failure on the part of the complainant to furnish plans, and, furthermore, was particularly the result of the complainant’s announce[411]*411ment that it did not intend to perform its part of the contract unless certain alterations of it were agreed to. The defendant also insists in the answer that its damages amounted to the sum of $5,175.03, made up of the various items set forth in that pleading; but on the hearing its counsel abandoned all claims to damages, except the following, namely: The difference in cost of mining coal during parts of September and October, 1896, amounting to $3,106.96; the difference in the cost of hauling, $782; and the difference in the cost of pumping, §138.75; making a total of $4,027.71.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Alabama Vermiculite Corporation v. Patterson
124 F. Supp. 441 (W.D. South Carolina, 1954)
Pickens County v. National Surety Co.
13 F.2d 758 (Fourth Circuit, 1926)
Murray Co. v. Citizens' Oil Mill
281 F. 699 (Fourth Circuit, 1922)
Bamberger Bros. v. Burrows
124 N.W. 333 (Supreme Court of Iowa, 1910)

Cite This Page — Counsel Stack

Bluebook (online)
93 F. 408, 1899 U.S. App. LEXIS 2880, Counsel Stack Legal Research, https://law.counselstack.com/opinion/jeffrey-mfg-co-v-central-coal-iron-co-circtdky-1899.