Jeda Capital-56, LLC v. Village of Potsdam

661 F. App'x 20
CourtCourt of Appeals for the Second Circuit
DecidedSeptember 2, 2016
Docket14-4098-cv
StatusUnpublished
Cited by3 cases

This text of 661 F. App'x 20 (Jeda Capital-56, LLC v. Village of Potsdam) is published on Counsel Stack Legal Research, covering Court of Appeals for the Second Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Jeda Capital-56, LLC v. Village of Potsdam, 661 F. App'x 20 (2d Cir. 2016).

Opinion

SUMMARY ORDER

Plaintiff-appellant JEDA Capital-56, LLC (“JEDA”) appeals from the September 30, 2014 judgment of the District Court granting the motion for summary judgment by defendant-appellee the Village of Potsdam, New York (“the Village”). 1 We assume the parties’ familiarity with the underlying facts, the procedural *22 history of the case, and the issues on appeal.

BACKGROUND

JEDA and the Village entered into a lease, under the terms of which JEDA, a developer, would build a water storage facility that it would lease to the Village in exchange for monthly rent payments. JEDA was to deliver the facility to the Village by December 1, 2008. Delivery still had not occurred, however, as of August 18, 2009, when the parties executed a “Project Completion Agreement” (“PCA”), which identified various items that needed to be completed before the Village would accept delivery. The PCA also contained a release provision, which is the principal subject of this appeal. 2

JEDA never completed the facility to the Village’s satisfaction, and the Village never accepted delivery or made any rent payments. In January 2010, Community Bank, which had financed JEDA’s project, commenced a foreclosure action on the water storage facility property, purchased it,' and sold it to the Village pursuant to a preexisting agreement.

JEDA commenced this action on May-27, 2011, alleging pursuant to state contract law that the Village breached its contract with JEDA and pursuant to 42 U.S.C. § 1983 that the Village deprived JEDA of property without due process of law. JEDA also sought rescission of the PCA based on claims that it was obtained by duress, that it was obtained -without consideration, and that it contained contradictory terms. The District Court dismissed JEDA’s rescission claims on their merits. Having found that the PCA was enforceable, the District Court went on to hold that the PCA barred JEDA’s claim for nonpayment of rent and its § 1983 claims for deprivation of property. Finally, the District Court declined to exercise supplemental jurisdiction over JEDA’s state-law claims for unjust enrichment and for breach of contract based on alleged alterations to the lease agreement.

On appeal, JEDA argues that the District Court erred in granting summary judgment because (1) the release in the PCA is unenforceable because it was obtained by economic duress, (2) the release is unenforceable because JEDA received .no consideration for signing it, and (3) the release is unenforceable because it contains contradictory terms. In addition, JEDA argues that (4) even if the release is enforceable, it does not cover all of JEDA’s claims. We consider each of these arguments in turn.

DISCUSSION

JEDA first argues that the release was obtained by economic duress. We need *23 not decide whether duress was present, however, because JEDA ratified the release and therefore waived the right to claim duress. Under New York law, “[a] party may ratify a contract or release entered into under duress by intentionally accepting benefits under the contract, by remaining silent or acquiescing in the contract for a period of time after [the party] has the opportunity to avoid it, or by acting upon it, performing under it, or affirmatively acknowledging it.” VKK Corp. v. Nat’l Football League, 244 F.3d 114, 123 (2d Cir. 2001) (internal quotation marks omitted). Here, JEDA signed the PCA on August 18, 2009, but did not attempt to repudiate it until commencing this suit on May 27, 2011. To the contrary, JEDA affirmatively sought to perform under the PCA and to hold the Village to its alleged obligations under that agreement. This delay of more than 21 months is “simply too long” to permit JEDA to assert duress in this litigation. See id. at 124 (finding that a party ratified a contract by acquiescing for one year); see also United States v. Twenty Miljam-350 IED Jammers, 669 F.3d 78, 91 (2d Cir. 2011) (finding ratification under New York law after a four-month period of acquiescence).

Second, JEDA argues that “[t]he PCA is invalid for lack of consideration.” JEDA Br. 18. Assuming without deciding that consideration is even necessary under these circumstances, see N.Y. Gen. Oblig. Law § 15-303, we reject this argument as meritless. As the District Court rightly observed, JEDA, in exchange for signing the PCA, gained the resolution of a number of disputed items to which it was not clearly entitled at the time. These included, for example, the resolution of concerns stemming from a possible discrepancy in elevation between two towers in the water storage facility. Resolution of a disputed claim is sufficient consideration to support a contract. See, e.g., Apfel v. Prudential-Bache Sec. Inc., 81 N.Y.2d 470, 600 N.Y.S.2d 433, 616 N.E.2d 1095, 1097 (1993); Wahl v. Barnum, 116 N.Y. 87, 22 N.E. 280, 282 (1889) (holding that settlement of a disputed claim is legal consideration, even if the claim lacked merit).

Third, JEDA argues that the District Court improperly granted the Village summary judgment on JEDA’s fifth cause of action—which sought rescission of the PCA based on its allegedly contradictory terms—because the Village did not specifically move for summary judgment on that claim. Even if we assume arguendo that JEDA has correctly characterized the Village’s motion, this argument is nonetheless meritless. 3 Although we have discouraged district courts from granting summary judgment sua sponte, it is permissible to do so as long as the party against whom summary judgment is granted is not “procedurally prejudiced” as a result. Bridgeway Corp. v. Citibank, 201 F.3d 134, 139 (2d Cir. 2000). “A party is procedurally prejudiced if it is surprised by the district court’s action and that surprise results in the party’s failure to present evidence in support of its position.” Id. Here, JEDA has not pointed to any additional evidence it could have brought to oppose summary judgment on its fifth cause of action. Indeed, JEDA presented to the District Court precisely the same argument against summary judgment that it now rehearses in its principal brief. We therefore have no reason to conclude that JEDA was procedurally prejudiced by the District Court’s grant of summary judgment on that claim.

Furthermore, we agree with the District Court that JEDA’s fifth cause of *24 action fails on its merits.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Jeda Capital-56, LLC v. Potsdam Assoc., LLC
2024 NY Slip Op 01231 (Appellate Division of the Supreme Court of New York, 2024)
(PC) Craver v. Ables
E.D. California, 2023
Jeda Capital-56, LLC v. Village of Potsdam
2021 NY Slip Op 05902 (Appellate Division of the Supreme Court of New York, 2021)

Cite This Page — Counsel Stack

Bluebook (online)
661 F. App'x 20, Counsel Stack Legal Research, https://law.counselstack.com/opinion/jeda-capital-56-llc-v-village-of-potsdam-ca2-2016.