JE Sinn Consulting, LLC

CourtArmed Services Board of Contract Appeals
DecidedMay 5, 2023
Docket63353, 63383
StatusPublished

This text of JE Sinn Consulting, LLC (JE Sinn Consulting, LLC) is published on Counsel Stack Legal Research, covering Armed Services Board of Contract Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
JE Sinn Consulting, LLC, (asbca 2023).

Opinion

ARMED SERVICES BOARD OF CONTRACT APPEALS Appeals of - ) ) JE Sinn Consulting, LLC ) ASBCA Nos. 63353, 63383 ) Under Contract No. FA3016-20-C-0102 )

APPEARANCE FOR THE APPELLANT: Mr. Joel E. Sinn President

APPEARANCES FOR THE GOVERNMENT: Caryl A. Potter III, Esq. Air Force Deputy Chief Trial Attorney Michael J. Farr, Esq. Trial Attorney

OPINION BY ADMINISTRATIVE JUDGE WOODROW

Appellant, JE Sinn Consulting, LLC (JE Sinn or appellant), elected to pursue these appeals under the Board’s Rule 12.2, Small Claims (Expedited) procedure. Accordingly, this decision shall have no precedential value, and in the absence of fraud shall be final and conclusive and may not be appealed or set aside. See 41 U.S.C. § 7106(b)(4)-(5). Mr. Joel Sinn, President of JE Sinn, is representing appellant pro se.

On September 18, 2020, the Air Force awarded Contract No. FA3016-20-C-0102 to JE Sinn in the total amount of $291,688 (R4, tab 6 at 1-2). The contract was a firm-fixed-price (FFP) design-build construction contract for the replacement of a culvert bridge on Cowgill Road at Joint Base San Antonio (JBSA)-Camp Bullis, Texas (id. at 1, 4, 34). The contract included Contract Line Item Number (CLIN) 0001 for the design work, which required submission of 65%, 95%, and 100% design packages, and CLIN 0002 for the construction work with an overall performance period of 222 days (R4, tab 6 at 1, 4).

The Air Force issued the Notice to Proceed (NTP) for the design work on September 28, 2020, with a scheduled completion date of February 8, 2021 (R4, tab 7). On January 26, 2021, the parties executed a bilateral modification (Modification No. P0001) to extend the design period to April 1, 2021. This modification included a standard release of any monetary claims associated with the facts and circumstances of the modification. (R4, tab 8 at 2) The pertinent language releases “all liabilities, obligations, claims, and demands whatsoever under or arising from the said contract for further equitable adjustments attributed to such facts or circumstances giving rise to this modification. This release of claims for this modification is agreed to be full and complete without any exceptions.” The extension of the design period was necessary due to delays in processing base passes for appellant’s personnel and for the Air Force’s review of the appellant’s design submittals (tr. 29-34). JE Sinn submitted the final 100% design package on March 26, 2021, and the Air Force approved the final design on April 7, 2021 (R4, tab 50 at 5).

On April 28, 2021, the parties bilaterally modified (Modification No. P00002) the contract to address the discovery of lead-based paint on the bridge structure, adding an additional amount of $5,999.41 for lead paint abatement work. This amount included only JE Sinn’s direct costs, but not extended overhead (tr. 43). The modification included a standard release of any additional monetary claims associated with the facts and circumstances of the modification. The release language is virtually identical to the release in Modification No. P00001 (R4, tab 9 at 4). On June 24, 2021, the Navy issued a NTP for the construction work (including lead-based paint abatement) and subsequently issued unilateral modification (Modification No. P00003) to establish the contract completion date of October 12, 2021 (R4, tabs 12 at 2, 13).

On August 26, 2021, JE Sinn poured the concrete for the bridge deck. The last concrete truck arrived three hours late. (R4, tabs 14 at 2, 44 at 3) During the delay, part of the unfilled area concrete started to set, creating a “cold joint” in what was intended to be a monolithic concrete structure (R4, tab 44 at 3-4; tr. 45-46). As a result, JE Sinn’s Designer of Record (DOR), Munoz Engineering, recommended that tensile strength tests be performed on the bridge deck concrete (R4, tabs 16 at 4, 18). On September 23, 2021, JE Sinn notified the Air Force that the tensile strength test failed, and, on October 4, 2021, the DOR recommended removing and replacing the concrete placed after the three-hour delay in pouring (R4, tab 21 at 2, 9). On October 6, 2021, the Air Force civil engineer office provided comments regarding the DOR’s recommended course of action, including stating the need to include an additional tensile strength test, including citing the applicable American Society for Testing and Materials (ASTM) number, the PSI or MPa rating needed for a passing test result, and the timing of the test, i.e., how many days after the concrete pour (R4, tab 22 at 3). That same day, the Air Force civil engineer office held a conference call with the DOR and JE Sinn, during which the Air Force agreed with the proposed repair, but requested that a new tensile strength test be accomplished as a means to inspect whether the repair was successful (R4, tab 44 at 4; tr. 49, 124-25). JE Sinn’s DOR, however, stated that a second tensile strength was unnecessary (tr. 50-51, 55), and, at that time, the CO did not expressly direct JE Sinn to perform the second tensile strength test (tr. 55-56).

On October 13, 2021, a heavy storm passed through the San Antonio area, causing the dry creek bed under the project bridge to overflow the top of the bridge

2 deck and the road on either side of the bridge (R4, tab 25 at 2). The high water washed away a significant amount of road and shoulder base material and dislodged the bracing holding the bridge forms for the concrete railing (id.). According to JE Sinn, repairing the damage required it to remove all of the loose rocks from the new road base, scarify the remaining base, add and compact new base material, and then repair 300 feet of shoulders (R4, tabs 24 at 6-10, 25 at 8; tr. 62-63).

On October 13, 2021, JE Sinn advised the Air Force that the DOR did not specify a requirement for another tensile strength test as part of the remedial work, that the method used in the repairs is standard for this type of repair, and that a tensile strength test is not listed as a requirement following such repairs (R4, tab 44 at 4; tr. 50-51, 54-55). On November 15, 2021, JE Sinn notified the government that it had completed the concrete repairs and asked for a final inspection, stating that it was not necessary to retest the tensile strength of the repaired bridge deck because the DOR had been present throughout the repairs. If the Air Force insisted upon retesting, JE Sinn said it would seek reimbursement for the costs of the retest. (R4, tabs 39 at 9-10, 44 at 4)

On December 2, 2021, the Air Force conducted the final inspection (R4, tab 44 at 4). When the Air Force civil engineering project manager, Mr. Dwight Wellons, asked appellant for the results of the second tensile strength test and stated that without such results, the Air Force could not accept the project, appellant again asserted that since the DOR did not require the test as part of the proposed remedial work, the test was neither necessary nor required. (id. at 4-5; tr. 55-56).

On January 12, 2022, the CO directed JE Sinn to perform a second tensile strength test on the repaired concrete (R4, tab 39 at 1). JE Sinn performed the test and provided the Air Force with the test results on January 20, 2022, which showed that the repairs and rework performed were successful. (R4, tab 42 at 5-8). Subsequently, on January 13, 2022, the CO issued appellant a final acceptance letter (R4, tab 41).

Requests for Equitable Adjustment

On September 14, 2021, appellant submitted its first request for equitable adjustment (REA) for additional compensation and a nine-day time extension due to heavy rainfalls that allegedly delayed the project for seven days, plus a weekend, and resulted in additional expenses to pump water out of the creek bed and lost time on the contract work (R4, tab 17 at 2).

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Bell Bci Co. v. United States
570 F.3d 1337 (Federal Circuit, 2009)
Lakeshore Engineering Services, Inc. v. United States
748 F.3d 1341 (Federal Circuit, 2014)

Cite This Page — Counsel Stack

Bluebook (online)
JE Sinn Consulting, LLC, Counsel Stack Legal Research, https://law.counselstack.com/opinion/je-sinn-consulting-llc-asbca-2023.