JE Dunn Construction Co.

CourtArmed Services Board of Contract Appeals
DecidedApril 25, 2022
DocketASBCA No. 62936
StatusPublished

This text of JE Dunn Construction Co. (JE Dunn Construction Co.) is published on Counsel Stack Legal Research, covering Armed Services Board of Contract Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
JE Dunn Construction Co., (asbca 2022).

Opinion

ARMED SERVICES BOARD OF CONTRACT APPEALS Appeal of - ) ) JE Dunn Construction Co. ) ASBCA No. 62936 ) Under Contract No. W9127S-17-D-6003 )

APPEARANCES FOR THE APPELLANT: Reginald M. Jones, Esq. David Timm, Esq. Nicholas T. Solosky, Esq. Fox Rothschild LLP Washington, DC

APPEARANCES FOR THE GOVERNMENT: Michael P. Goodman, Esq. Engineer Chief Trial Attorney Michael T. Geiselhart, Esq. Liz K. Harris, Esq. Engineer Trial Attorneys U.S. Army Engineer District, Little Rock

OPINION BY ADMINISTRATIVE JUDGE SHACKLEFORD PURSUANT TO RULE 12.3

This appeal involves a contract for JE Dunn Construction Company (JE Dunn) to perform design-build construction work for the United States Army Corps of Engineers (USACE or government) at Fort Drum, New York. JE Dunn alleges that USACE changed the contract by implementing COVID-19-related restrictions requiring all personnel arriving at Fort Drum from more than 350 miles away to quarantine for 14 days prior to performing work on-site. USACE argues that the sovereign acts doctrine bars JE Dunn’s claim, that JE Dunn would still have been required to quarantine under New York’s COVID-19 protocols and therefore would have suffered the same damages notwithstanding Fort Drum’s quarantine requirement, and that the risk of costs relating to a pandemic or quarantine under a fixed-price contract rest with the contractor. The Board has jurisdiction over this appeal pursuant to the Contract Disputes Act of 1978, 41 U.S.C. §§ 7101-7109. JE Dunn elected Rule 12.3 disposition, and both parties elected to submit this appeal on the record pursuant to Board Rule 11. We deny the appeal.

FINDINGS OF FACT

1. On July 14, 2017, USACE awarded Contract No. W9127S-17-D-6003 (the contract) to JE Dunn for design-build construction work (R4, tab 1 at 1 1).

1 Page number citations refer to the PDF page number, unless otherwise stated. 2. On September 25, 2018, USACE awarded Task Order No. W9127S-18-F-0155 to JE Dunn under the contract. This task order was for heating, ventilation, and air conditioning (HVAC) replacement services at the Guthrie Health Care Clinic at Fort Drum at a total price of $30,428,439. (R4, tab 2 at 46-51)

3. The contract incorporated by reference Federal Acquisition Regulation (FAR) 52.249-10, DEFAULT (FIXED-PRICE CONSTRUCTION) (APR 1984) (Default Clause) (R4, tab 1 at 9). This clause provides, in part:

(b) The Contractor's right to proceed shall not be terminated nor the Contractor charged with damages under this clause, if—

(1) The delay in completing the work arises from unforeseeable causes beyond the control and without the fault or negligence of the Contractor. Examples of such causes include . . .

(vi) epidemics

(vii) quarantine restrictions . . . .

(2) The Contractor, within 10 days from the beginning of any delay (unless extended by the Contracting Officer), notifies the Contracting Officer in writing of the causes of delay. The Contracting Officer shall ascertain the facts and the extent of delay. If, in the judgment of the Contracting Officer, the findings of fact warrant such action, the time for completing the work shall be extended.

FAR 52.249-10(b)(1-2)

4. On April 22, 2020, Major General Brian Mennes, the Fort Drum Commander, imposed General Order No. 1B. This order—which applied to service members, their dependents, and civilian personnel—outlined prevention and mitigation procedures aimed at slowing the spread of COVID-19. (R4, tab 3 at 102-09)

5. By letter dated May 4, 2020, JE Dunn notified USACE of pandemic-related on- site health and cleaning changes that would increase the cost of performance and cause delays. These changes included conditional or limited jobsite access. (R4, tab 4 at 110)

6. On June 25, 2020, New York Executive Order 205 (EO 205) went into effect. This executive order imposed a 14-day quarantine requirement on all persons traveling to

2 New York “from a state with a positive test rate higher than 10 per 100,000 residents, or higher than a 10% test positivity rate, over a seven day rolling average.” (R4, tab 5 at 111-12)

7. On July 16, 2020, USACE informed JE Dunn that anyone arriving at Fort Drum from outside a 350-mile radius would be required to quarantine for 14 days before being permitted to enter the base (R4, tab 6 at 113).

8. By letter dated October 22, 2020, JE Dunn submitted a request for equitable adjustment (REA) pursuant to FAR 52.243-7, NOTIFICATION OF CHANGES (APR 1984). JE Dunn sought an equitable increase of $47,737 to the contract price to compensate for projected hotel, food, rental car, labor, profit, and overhead expenses associated with the 14-day quarantine of two of JE Dunn’s subcontractor’s employees. This REA requested a monetary adjustment to the contract price only. (R4, tab 7 at 114-22)

9. By letter dated November 3, 2020, USACE denied JE Dunn’s October 22, 2020 REA. USACE stated that the Default Clause governed JE Dunn’s request and only allowed for additional time to complete performance in response to the quarantine restriction and not monetary compensation. (R4, tab 8 at 123)

10. On November 4, 2020, New York Executive Order 205.2 (EO 205.2) went into effect. This order permitted travelers from states affected by EO 205 to bypass the 14-day quarantine requirement by providing proof of a negative test administered within 72 hours of entering New York, quarantining for a minimum of three days, and testing negative again on the fourth day. NY Exec. Order No. 205.2 (Oct. 31, 2020) 2

11. The subcontractor’s two employees—Stephania Walker and Nancy Moore— travelled to Fort Drum from Pensacola, Florida and quarantined in Watertown, New York from November 26 to December 10, 2020 (R4, tab 7 at 119).

12. JE Dunn’s two employees—Mr. Daniel Lacy and Mr. Mike Schmidt— travelled to Fort Drum from Kansas City, Missouri and quarantined in Watertown, New York (R4, tab 9 at 136-37; app. supp.R4, tabs 16-23).

13. Mr. Lacy quarantined from October 30 to November 12, 2020 (app. R4 supp., tabs 17-19). Mr. Schmidt quarantined from January 4 to January 17, 2021 (app. supp. R4, tabs 22-23).

2 This executive order is available at https://www.governor.ny.gov/sites/default/files/ atoms/files/EO205.2.pdf.

3 14. By letter dated January 29, 2021, JE Dunn submitted a claim requesting a contracting officer’s final decision (COFD). JE Dunn sought $67,626 for expenses associated with the quarantine of all four employees. (R4, tab 9 at 124-25) These expenses included additional per diem, labor, profit, and overhead expenses stemming from the quarantines of Mr. Lacy and Mr. Schmidt (id. at 126-48).

15. By letter dated March 9, 2021, USACE’s contracting officer (CO) denied JE Dunn’s claim, stating that § 3610 of the Coronavirus Aid, Relief, and Economic Security (CARES) Act does not permit the government to reimburse contractors for expenses incurred due to the pandemic for employees who are not in a leave or vacation status (R4, tab 11 at 150-52). The CO also denied that any contract changes were made that would allow for reimbursement because New York also imposed mandatory quarantine protocols for out-of-state travelers, which were requirements not directly related to JE Dunn and the contract (id. at 152).

16. On March 17, 2021, all travel restrictions at Fort Drum were lifted (R4, tab 13 at 154). Effective June 25, 2021, New York rescinded EO 205 (R4, tab 14 at 155).

17. On June 1, 2021, JE Dunn appealed the COFD to the Board.

DECISION

The Parties’ Contentions

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Horowitz v. United States
267 U.S. 458 (Supreme Court, 1925)
CONNER BROS. CONST. CO., INC. v. Geren
550 F.3d 1368 (Federal Circuit, 2008)

Cite This Page — Counsel Stack

Bluebook (online)
JE Dunn Construction Co., Counsel Stack Legal Research, https://law.counselstack.com/opinion/je-dunn-construction-co-asbca-2022.