JB Distribution Market of SLC, LLC v. City of Peoria

2025 IL App (4th) 241608-U
CourtAppellate Court of Illinois
DecidedSeptember 4, 2025
Docket4-24-1608
StatusUnpublished

This text of 2025 IL App (4th) 241608-U (JB Distribution Market of SLC, LLC v. City of Peoria) is published on Counsel Stack Legal Research, covering Appellate Court of Illinois primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
JB Distribution Market of SLC, LLC v. City of Peoria, 2025 IL App (4th) 241608-U (Ill. Ct. App. 2025).

Opinion

2025 IL App (4th) 241608-U NOTICE FILED This Order was filed under September 4, 2025 Supreme Court Rule 23 and is NO. 4-24-1608 Carla Bender not precedent except in the 4th District Appellate limited circumstances allowed IN THE APPELLATE COURT under Rule 23(e)(1). Court, IL

OF ILLINOIS

FOURTH DISTRICT

JB DISTRIBUTION MARKET OF SLC, LLC, ) Appeal from the Plaintiff-Appellant, ) Circuit Court of v. ) Peoria County THE CITY OF PEORIA, ) No. 24MR293 Defendant-Appellee. ) ) Honorable ) James A. Mack, ) Judge Presiding.

JUSTICE DOHERTY delivered the judgment of the court. Presiding Justice Harris and Justice Grischow concurred in the judgment.

ORDER

¶1 Held: The circuit court erred in dismissing, at the motion stage, plaintiff’s complaint on the basis that it was untimely.

¶2 Plaintiff JB Distribution Market of SLC, LLC, appeals the circuit court’s dismissal

of its complaint to enjoin defendant the City of Peoria (City) from utilizing section 11-31-1(e) of

the Illinois Municipal Code (65 ILCS 5/11-31-1(e) (West 2024)), which allows for accelerated

demolition of its property, or so called “fast-track demolition.” See City of Geneseo v. Pyrotem

Properties, LLC, 2022 IL App (4th) 220206, ¶ 18. The court found that, per the language of the

statute, plaintiff’s action was untimely because the City had already begun demolition before it

was filed. Plaintiff argues that the court erred in interpreting the statute. For the reasons that follow,

we reverse and remand.

¶3 I. BACKGROUND ¶4 On August 9, 2024, the City determined that plaintiff’s building at 4103 Southwest

Adams Street in Peoria, Illinois, qualified for fast-track demolition. The same day, the City posted

the statutorily required notices on the property. On August 21, a notice to remediate and a letter

explaining the City’s intention to demolish the building within 30 days were sent to plaintiff and

its registered agent.

¶5 The City issued a request for proposals to demolish the building and restore the site.

One of the requirements of the request for proposals that was ultimately incorporated into the

winning bidder’s contract was that “[g]enerally, 6ft. tall fencing shall be used during the active

debris removal and demolition activities.” The City entered a contract with a demolition company

on October 24, 2024, and the company began inspections and testing. It ultimately erected a fence

around the property on November 7, 2024.

¶6 On November 8, 2024, plaintiff filed a complaint seeking to enjoin the City from

demolishing the building. The complaint contained the following allegation: “The City has not

proceeded with demolition at the time of filing this Complaint.” Consequently, plaintiff argued, it

became necessary for the circuit court to determine, after a hearing, whether demolition was

necessary to remedy the hazard presented by the building.

¶7 The City filed a motion to dismiss, pursuant to section 2-619(a)(5) of the Code of

Civil Procedure (735 ILCS 5/2-619(a)(5) (West 2024)), arguing that the property qualified for

fast-track demolition and that the demolition contractor had taken substantial steps under the

contract to demolish the building, including asbestos testing and enclosing the property with

fencing. Because of these actions, the City argued, plaintiff’s request to enjoin demolition was

untimely. While there were affidavits attached to the motion, none of the affidavits stated that

demolition had in fact begun or touched on the subject of fencing or environmental testing.

-2- ¶8 At the hearing on the City’s section 2-619 motion, counsel exchanged arguments

on the meaning and application of the statutory provision authorizing the fast-track demolition.

Specifically, the parties disagreed on whether the complaint was timely if the City had proceeded

with any of the actions authorized by statute. The City argued that it had already proceeded with

demolition where its contractor had done asbestos testing and erected a fence that enclosed the

property. Plaintiff argued that since the City had not yet begun demolishing the building, the City

had not proceeded to demolition. Plaintiff’s counsel argued that the fencing and testing were

merely preparations to demolish that did not preclude plaintiff’s challenge. Plaintiff further argued

that the City’s interpretation of actions that constituted proceeding with demolition was so broad

that it would be impossible for an individual to ever challenge a fast-track demolition.

¶9 The circuit court looked to the demolition contract to find that during demolition,

the contractor was responsible for identifying hazardous materials, such as asbestos. Moreover,

fencing was required during active debris removal and demolition activities. The City’s contractor

had already completed asbestos testing and fenced the property prior to plaintiff’s complaint, in

accordance with a timeline identified in the contract, rendering the pleading untimely. Plaintiff’s

complaint was dismissed with prejudice. At a subsequent hearing, demolition of the building was

stayed pending appeal. At that hearing, evidence was introduced that showed substantial repairs to

the building had been made.

¶ 10 This appeal followed.

¶ 11 II. ANALYSIS

¶ 12 Plaintiff argues on appeal that the circuit court erred in its interpretation of the

statute where it diminished the requirement that the City proceed with demolition to the

requirement that the City take “some mere steps” toward demolition instead of proceeding with

-3- the demolition itself. “A motion to dismiss under section 2-619(a) admits the legal sufficiency of

the plaintiff’s claim but asserts certain defects or defenses outside the pleadings which defeat the

claim.” (Emphasis added.) Sandholm v. Kuecker, 2012 IL 111443, ¶ 55. All well-pleaded facts in

a plaintiff’s complaint and all reasonable inferences that may flow therefrom are to be accepted as

true by the court. Id. The pleadings and supporting documents are construed in the light most

favorable to the plaintiff. Id. The existence of a genuine issue of material fact precludes dismissal

as a matter of law. Id. Involuntary dismissal pursuant to section 2-619 is reviewed de novo, and,

to the extent we engage in statutory construction, our review remains de novo. Eads v. Heritage

Enterprises, Inc., 204 Ill. 2d 92, 96 (2003). Because the issues are all reviewed de novo, we

perform the same analysis the circuit court would perform anew and give no deference to the

court’s conclusions or specific rationale. Blagden v. McMillin, 2023 IL App (4th) 220238, ¶ 40.

¶ 13 We first examine the fast-track demolition statute to determine if it establishes the

City’s right to dismissal of plaintiff’s complaint as a matter of law. The cardinal rule of statutory

construction is to give effect to the intent of the legislature, as best demonstrated by the plain

language of the statute. Chapman v. Chicago Department of Finance, 2023 IL 128300, ¶ 28. When

engaging in statutory construction, we view the statute as a whole and “ ‘may consider the reason

for the law, the problems sought to be remedied, the purposes to be achieved, and the consequences

of construing the statute one way or another.’ ” Id. ¶¶ 28, 29 (quoting In re Appointment of Special

Prosecutor, 2019 IL 122949, ¶ 23).

Free access — add to your briefcase to read the full text and ask questions with AI

Related

City of Peru v. Bernardi
401 N.E.2d 1 (Appellate Court of Illinois, 1980)
Eads v. Heritage Enterprises, Inc.
787 N.E.2d 771 (Illinois Supreme Court, 2003)
Sandholm v. Kuecker
2012 IL 111443 (Illinois Supreme Court, 2012)
Reynolds v. Jimmy John's Enterprises, LLC
2013 IL App (4th) 120139 (Appellate Court of Illinois, 2013)
Village of West Dundee v. First United Methodist Church
2017 IL App (2d) 150278 (Appellate Court of Illinois, 2017)
In re Appointment of Special Prosecutor
2019 IL 122949 (Illinois Supreme Court, 2019)
City of Geneso v. Pyrotem Properties, LLC
2022 IL App (4th) 220206-U (Appellate Court of Illinois, 2022)
Blagden v. McMillin
2023 IL App (4th) 220238 (Appellate Court of Illinois, 2023)
Chapman v. Chicago Department of Finance
2023 IL 128300 (Illinois Supreme Court, 2023)
James v. Geneva Nursing & Rehabilitation Center, LLC
2023 IL App (2d) 220180 (Appellate Court of Illinois, 2023)

Cite This Page — Counsel Stack

Bluebook (online)
2025 IL App (4th) 241608-U, Counsel Stack Legal Research, https://law.counselstack.com/opinion/jb-distribution-market-of-slc-llc-v-city-of-peoria-illappct-2025.