Jauch v. Powertown Tire Corp.

212 A.D. 326, 209 N.Y.S. 16, 1925 N.Y. App. Div. LEXIS 9463
CourtAppellate Division of the Supreme Court of the State of New York
DecidedMarch 11, 1925
StatusPublished
Cited by2 cases

This text of 212 A.D. 326 (Jauch v. Powertown Tire Corp.) is published on Counsel Stack Legal Research, covering Appellate Division of the Supreme Court of the State of New York primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Jauch v. Powertown Tire Corp., 212 A.D. 326, 209 N.Y.S. 16, 1925 N.Y. App. Div. LEXIS 9463 (N.Y. Ct. App. 1925).

Opinion

Hubbs, P. J.:

The complaint, as amended, alleges that on June 1, 1920, a contract of sale was entered into between the plaintiff’s assignor and the defendant for 40,000 pounds of cotton fabric, at two dollars and forty-five cents per pound, F. O. B. mills, to be paid for upon presentation of sight draft with bill of lading attached, delivery to be made at the rate of about 10,000 pounds monthly in July, August, September and October; that the plaintiff’s assignor duly complied with the terms of the contract and in July shipped 6,680 pounds and was at all times able and willing to deliver the balance of said 40,000 pounds according to the terms of the contract; that delivery of 6,680 pounds in July did not amount to a material breach of the contract which entitled the defendant to cancel the entire contract; that the defendant notified the plaintiff that it would not accept the 6,680 pounds shipped or any subsequent installment.

Upon the trial the defendant contended that the shipment of [328]*3286,680 pounds instead of 10,000 pounds constituted a breach of the contract which gave it the right to rescind the whole contract as a matter of law.

The evidence discloses that the plaintiff’s assignor did not manufacture the product in question, but purchased it of the mills, and the contract so states. The plaintiff’s assignor, prior to making the contract with the defendant, had entered into valid contracts with mills to furnish it with 50,000 pounds of the cotton product in question, to be delivered in quantities which would enable it to fill the contract with the defendant as written. The mills were unable to furnish the plaintiff’s assignor the amount contracted to be delivered in July, but did furnish 6,680 pounds. That quantity the plaintiff’s assignor shipped to the defendant.

On July thirtieth, before the arrival of the shipment and before the defendant knew that the shipment would not amount to 10.000 pounds, it wrote the brokers of whom it made the purchase to cancel the contract, as we have been compelled to purchase 10.000 pounds spot shipment during the month of July and have already loaded up for August and September deliveries.” Later it took the position that it ordered the contract canceled because the goods were not received in July, and not because the shipment made did not contain 10,000 pounds. The defendant refused to accept the shipment of 6,680 pounds.

The learned trial court permitted the jury to determine whether the failure of the plaintiff’s assignor to ship the full 10,000 pounds instead of 6,680 pounds in July was such a material breach as to justify the defendant in repudiating the whole contract. The jury decided that issue in favor of the plaintiff. The trial court set aside the verdict and ordered a new trial upon the ground that it was error to permit the jury to find damages against the defendant for failure to accept the 6,680 pounds shipped on the July installment.

Counsel for the plaintiff now concedes that the plaintiff is not entitled to recover damages because of the defendant’s failure to accept 6,680 pounds shipped on the July installment. It is urged, however, that the verdict should be reduced in the sum of $7,000, the amount of damage allowed for failure to accept the July installment, and that the verdict as so reduced be reinstated.

As heretofore stated, the defendant placed its refusal to go on with the contract jipon the ground that the first installment did not arrive during July. That ground was clearly untenable, as the plaintiff’s assignor was bound by the terms of the contract to ship only the first installment during the month of July.

It is a general principle that where a party to a contract refuses to fulfill and bases the refusal upon a particular ground clearly [329]*329and deliberately stated, all other objections are deemed waived. (Littlejohn v. Shaw, 159 N. Y. 188.)

Passing that objection, however, we are of the opinion that the verdict of the jury was justified, except as to the damage allowed on the July installment, which we do not pass upon as it is conceded by the plaintiff that no recovery should be had on accouni of the defendant’s failure to accept that installment. No exceptions were taken by the defendant to the manner in which the case was submitted to the jury and the charge, as a whole, fairly stated to the jury that the question for it to determine was whether, under all the circumstances the shipment of 6,680 pounds instead of 10,000 pounds was such a material difference as to justify the defendant in refusing to accept the further installments. Accepting, for the purpose of this decision, the concession now made by the plaintiff, that the difference between the amount shipped and the amount called for by the contract was so great that it did not constitute a substantial compliance with the contract, and that the defendant buyer was, therefore, justified in refusing to accept the shipment, what is the effect? It appears that the price had declined from $2.45, the contract price per pound, to $1.75, in July. By rejecting the shipment the defendant saved $7,000. The failure to ship 10,000 pounds in July, instead of resulting in a damage to the defendant, resulted in a substantial gain. It appears that it was not in immediate need of the goods and that it was not damaged in any other way by failure to receive the full 10,000 pounds in the first installment. The plaintiff’s assignor was not careless, negligent or willful; it did everything that a prudent business man could have done to secure the 10,000 pounds with which to fill the defendant’s contract. It had protected itself by valid contracts with the mills and it continuously and persistently urged upon the mills the necessity of shipping 10,000 pounds during the month of July. The mills were unable to do so because of car shortage and traffic congestion. Under such circumstances the defendant buyer could not, as a matter of law, arbitrarily and apparently because the price of the goods had gone down, cancel the contract and refuse to accept future installments.

Prior to the enactment of article 5 of the Personal Property Law (as added by Laws of 1911, chap. 571), known as the Sales of Goods Act, the law of this State was settled that under an executory contract for the sale of goods to be delivered in installments a failure of the seller to deliver an installment constituted a breach of the contract which justified the buyer, who was not in default, in rescinding the whole contract. (Wolfert v. Caledonia Springs Ice Co., 195 N. Y. 118.)

[330]*330Section 126, subdivision 2, of the Personal Property Law (as added by Laws of 1911, chap. 571) has established a new standard. (Miller & Sons Co. v. Sergeant Co., 191 App. Div. 814.) Section 126 of said statute provides:

§ 126. Delivery in installments.
“1. Unless otherwise agreed, the buyer of goods is not bound to accept delivery thereof by installments.
" 2.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Albert J. Schiff Associates, Inc. v. Flack
73 A.D.2d 329 (Appellate Division of the Supreme Court of New York, 1980)
Johnson v. National Life Insurance
150 Misc. 118 (New York Supreme Court, 1934)

Cite This Page — Counsel Stack

Bluebook (online)
212 A.D. 326, 209 N.Y.S. 16, 1925 N.Y. App. Div. LEXIS 9463, Counsel Stack Legal Research, https://law.counselstack.com/opinion/jauch-v-powertown-tire-corp-nyappdiv-1925.