Jardine Mining Co. v. United States

115 F. Supp. 174, 126 Ct. Cl. 263, 1953 U.S. Ct. Cl. LEXIS 40
CourtUnited States Court of Claims
DecidedSeptember 30, 1953
DocketNo. 48890
StatusPublished

This text of 115 F. Supp. 174 (Jardine Mining Co. v. United States) is published on Counsel Stack Legal Research, covering United States Court of Claims primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Jardine Mining Co. v. United States, 115 F. Supp. 174, 126 Ct. Cl. 263, 1953 U.S. Ct. Cl. LEXIS 40 (cc 1953).

Opinion

Howell, Judge,

delivered the opinion of the court:

This suit1 was brought under the War Contract Hardship Claims Act, known as the Lucas Act, 60 Stat. 902, as amended by 62 Stat. 869, 992, 41 U. S. C. (Supp. Y) § 106 note, to recover the net loss alleged to have been sustained by plaintiff in the performance of Government contracts between September 16,1940, and August 14,1945.

By order of the court dated 'March 6, 1950, the case was referred to a Commissioner for the limited purpose of taking evidence and making findings on the question of the plaintiff’s request for relief. The issue now before the court for decision is whether or not the record establishes that plaintiff had on file with the department or agency concerned a request for relief within the meaning of the Act.

It is defendant’s position that the documents relied on by plaintiff were not sufficient to apprise the contracting agency that it was being asked to grant plaintiff relief as a matter of grace. Fogarty v. United States, 340 U. S. 8.

Plaintiff is a mining corporation doing business in the State of Montana. In April 1942, the Bureau of Mines of the Department of the Interior wrote to plaintiff concerning the availability and cost of white arsenic ore in the vicinity of plaintiff’s mines at Jardine, Montana. Plaintiff replied that all of its ore contained a concentration of from one to two percent arsenic; that it could probably produce about two million pounds of white arsenic, 99.9 percent pure, per annum, at an estimated cost of 5 cents per pound. Plaintiff stated that it had not treated its ore to recover arsenic since 1936 because of the low market price for arsenic and that it would cost approximately $15,000 to repair its equipment in order to resume arsenic production.

[265]*265In May 1942, the War Production Board wrote to plaintiff and asked if plaintiff would proceed with the rehabilitation of its plant if a satisfactory arrangement could be made for the purchase of its arsenic output. In June 1943, the War Production Board wrote to the Secretary of Commerce requesting that Metals Reserve Company be authorized to negotiate with plaintiff for arsenic production for resale in accordance with allocation directives from the Chemicals Division of the War Production Board.

On June 17, 1943, plaintiff entered into a contract with Metals Reserve Company for sale and delivery to Metals Reserve of 10,000,000 pounds (5,000 tons) of refined white arsenic for a total price of $600,000. The contract provided in a clause entitled “Delivery Schedule” (Finding 6) for two separate and distinct delivery periods. One-half of the contract quantity of arsenic was to be delivered within 18 months from the date of the execution of the contract, or by December 17, 1944, and the balance to be delivered within the next ensuing 12 months, or by December 17, 1945.

The contract provided that shipments were to commence on or about January 1, 1944, after completion of the mill construction and the installation of the necessary facilities, and were to be at the rate of approximately 400,000 pounds per month. It also provided :

However, it is hereby understood and agreed that the quantities, as set forth in the above entitled paragraph “Delivery Schedule” shall be shipped within the periods of time, as therein specified. * * *

A “Force Majeure” clause provided that where there was a prevention of or delay in the performance of the contract for some disabling reason beyond the control of either party, the party affected would be entitled to a suspension of the agreement. This clause also provided:

Nothing contained in this paragraph shall be construed to permit Seller to make up any deficiencies in the delivery schedule, contrary to the paragraph entitled “Special Conditions.”

The above-mentioned “Special Conditions” clause provided that time was of the essence in the contract and that- any [266]*266deficiencies resulting from failure by seller to deliver the arsenic called for in the first or 18-month delivery period, could not be made up by deliveries in the succeeding second or 12-month delivery period.

The contract also contained the following cancellation provision:

Notwithstanding any other provision hereof, Buyer may cancel this Contract, without payment of any damages or penalties for such cancellation, with respect to any material remaining undelivered after January 1, 1946.

Plaintiff borrowed $500,000 from the Smaller War Plants Corporation, the loan being secured by a mortgage upon the real and personal property of plaintiff. Metals Reserve Company consented to an assignment by plaintiff to Smaller War Plants Corporation of the proceeds to become due plaintiff under the contract.

On March 15,1944, plaintiff wrote to Metals Reserve Company and advised that office that because of difficulties encountered in securing the necessary materials to rebuild the refined arsenic furnace, and the fact that the frozen condition of the ground made it impossible to lay the foundation, shipments of arsenic under the contract could not begin before July 1944. Pointing out that the causes of the delay were beyond the seller’s control within the meaning of the contract’s “Force Majeure” clause, plaintiff stated that it would require an extension of time to perform under the provisions of the contract. This letter was acknowledged by Metals Reserve on March 31, 1944, in a letter which said nothing about whether or not the extension of time would be granted, but which did state as follows:

You understand, of course, that these delays do not operate to alter the terms of the provisions “Delivery Schedule” and “Special Conditions’’ of the contract nor to extend the final termination date thereof.

On December 14,1944, three days before the end of the first delivery period, plaintiff wrote to Metals Reserve Company stating that serious delays beyond the control of plaintiff had prevented delivery of all the arsenic called for in the first contract period and that all the funds borrowed from [267]*267Smaller War Plants bad been expended plus about $156,000 of private capital. The letter concluded with the following:

In view of all the circumstances involved, we respectfully request that a bi’oad and liberal interpretation be made of the provisions of the contract and that the time of delivery of the balance of the 5,000 tons of refined arsenic be extended to enable Jardine Mining Company to deliver all of the arsenic contracted for, regardless of the time involved, and without loss.

On the same day, Smaller War Plants also wrote to Metals Eeserve. In that letter Smaller War Plants pointed out that under the terms of the contract, Jardine was obligated to deliver 2,500 tons of arsenic by December 17, 1944, and another 2,500 tons by December 17,1945, “these two provisions being separate.” The letter also contained the following statement:

We are writing you this letter ahead of the expiration date for delivery of the first 2,500 tons with the hope that you will consider favorably the request of the Jardine Mining Company for a suspension of the contract for the period of time which they have lost through circumstances beyond their control.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Fogarty v. United States
340 U.S. 8 (Supreme Court, 1950)
Jardine Mining Co. v. United States
88 F. Supp. 265 (Court of Claims, 1950)
Owens v. United States
104 F. Supp. 1015 (Court of Claims, 1952)

Cite This Page — Counsel Stack

Bluebook (online)
115 F. Supp. 174, 126 Ct. Cl. 263, 1953 U.S. Ct. Cl. LEXIS 40, Counsel Stack Legal Research, https://law.counselstack.com/opinion/jardine-mining-co-v-united-states-cc-1953.