Janice Suzanne Allen v. Hutchison Construction, Inc.

CourtCourt of Appeals of Texas
DecidedFebruary 28, 2002
Docket03-00-00743-CV
StatusPublished

This text of Janice Suzanne Allen v. Hutchison Construction, Inc. (Janice Suzanne Allen v. Hutchison Construction, Inc.) is published on Counsel Stack Legal Research, covering Court of Appeals of Texas primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Janice Suzanne Allen v. Hutchison Construction, Inc., (Tex. Ct. App. 2002).

Opinion

TEXAS COURT OF APPEALS, THIRD DISTRICT, AT AUSTIN

444444444444444 NO. 03-00-00743-CV 444444444444444

Janice Suzanne Allen, Appellant

v.

Hutchison Construction, Inc., Appellee

44444444444444444444444444444444444444444444444444444444444444444 FROM THE COUNTY COURT AT LAW NO. 1 OF TRAVIS COUNTY NO. 241,970, HONORABLE J. DAVID PHILLIPS, JUDGE PRESIDING 44444444444444444444444444444444444444444444444444444444444444444

Appellant Janice Suzanne Allen (Allen) and appellee Hutchison Construction, Inc.

(Hutchison) entered into a contract for the construction of a wall surrounding Allen’s property. After

the wall was substantially completed, the City of Austin “red-tagged” the structure for failure to

adhere to the City’s building codes and ordered any further construction to cease. As a result of the

City’s actions, a dispute ensued between the two parties over who had been responsible for obtaining

the relevant permit or variance to construct the wall. Ultimately, Allen sued Hutchison for

negligence, negligent misrepresentation, breach of contract, and violation of the Deceptive Trade

Practices Act. Hutchison counterclaimed, alleging breach of contract. The case was tried to the

bench, and the trial court found in favor of Hutchison, awarding $10,815 in actual damages, plus pre-

and post-judgment interest and attorney’s fees. We find the evidence legally and factually sufficient

to support the trial court’s judgment and affirm. BACKGROUND

Allen is an artist who lives on property located on Two Coves Road. Allen and her

neighbors had been engaged in an unrelated dispute. In an effort to shield her artwork from her

neighbors’ view, Allen sought to have a wall constructed along her property line. Allen also

interviewed contractors to construct an art studio on her property.

On November 17, 1997, after meeting with representatives from Hutchison, Allen

engaged Hutchison to construct the wall, but not the studio. Before entering into the contract, Allen

met with Hutchison representatives on several occasions to discuss the height of the proposed wall.

Hutchison agreed to construct a ten-foot wall, and Allen indicated that she would provide topsoil so

that Hutchison could landscape the wall. During these meetings, Hutchison also inquired as to

whether Allen’s property was located within the city limits of Austin. The parties dispute the specific

inquiries made by Hutchison and the response provided by Allen. Hutchison maintains that Allen was

specifically asked whether her property was located within the city limits and that Allen replied that

she recently had her house built on the same property and “had no inspections or anything,”

suggesting to Hutchison that the property was not within the city’s jurisdiction and that no permit was

necessary for the construction of the wall. Allen, on the other hand, testified during the trial that

Hutchison only inquired as to who had inspected her home when it was built, and she informed

Hutchison that the City had inspected it. In any event, no permit was sought or obtained by either

party. Following the meetings, Hutchison drafted the plans and began construction soon after the

contract was signed.

2 Construction of the wall initially progressed as planned, and Hutchison intermittently

submitted invoices to Allen for work performed, which Allen paid. During the course of the project,

Hutchison submitted two change orders to modify the project. The first change order extended the

length of the wall and deleted the rip-rap work. The second change order deleted the landscaping

work and reduced the price accordingly because Allen had not supplied the topsoil by the time the

wall was completed. Allen never signed this second change order.

On January 21, 1998, shortly after Hutchison left the second change order at Allen’s

house for her signature, a City of Austin building inspector “red-tagged” the wall for failure to comply

with the City’s building codes, requiring all remaining work to cease. Hutchison sent a final invoice

for the balance due for the work actually completed, but Allen refused to pay. According to her

testimony at trial, Allen unsuccessfully attempted to obtain a variance and a permit from the City.

Allen ultimately hired other contractors to reduce the height of the wall in order to comply with the

City’s building codes.

Allen then sued Hutchison, asserting damages in an amount equal to the expenses

incurred in attempting to obtain a variance or a permit from the City and the cost of reducing the

height of the wall. Hutchison counterclaimed, alleging breach of contract. Hutchison argued that by

the time the wall was red-tagged, the project was substantially completed, and Allen breached the

contract by failing to pay Hutchison for that work. The trial court found in favor of Hutchison and

awarded damages in the amount of the value of the work performed minus the amount that Allen had

already paid. Allen requested findings of fact and conclusions of law, which the trial court filed. In

those findings and conclusions, the trial court concluded that although ordinarily the contractor bears

3 the burden of obtaining a permit for residential construction, in this case, Hutchison was justified in

relying on Allen’s representation that the property was not within the city’s jurisdiction and was

therefore excused from its duty to obtain a permit. The court further concluded that Hutchison acted

as a reasonably prudent contractor in investigating whether a building permit was necessary and in

determining that the project did not require a City building permit. By five issues, Allen appeals the

judgment of the trial court.

DISCUSSION

Standard of Review

Allen generally challenges the legal and factual sufficiency of the evidence to support

the trial court’s findings of fact and conclusions of law and the judgment. Findings of fact in a case

tried to the court have the same force and effect as a jury verdict. Anderson v. City of Seven Points,

806 S.W.2d 791, 794 (Tex. 1991); Westech Eng’g, Inc. v. Clearwater Constructors, Inc., 835

S.W.2d 190, 195 (Tex. App.—Austin 1992, no writ). Findings of fact are reviewed for factual and

legal sufficiency under the same standards applied in reviewing evidence supporting a jury’s finding.

Anderson, 806 S.W.2d at 794; Stable Energy, L.P. v. Newberry, 999 S.W.2d 538, 546 (Tex.

App.—Austin 1999, pet. denied). However, a court’s conclusions of law are accorded de novo

review. Asai v. Vanco Insulation Abatement, Inc., 932 S.W.2d 118, 121 (Tex. App.—El Paso 1996,

no writ).

In considering a legal sufficiency point, we consider only the evidence or inferences

from the evidence favorable to the decision of the trier of fact and disregard all evidence and

inferences to the contrary. Garza v. Alviar, 395 S.W.2d 821, 823 (Tex. 1965). If the appellant did

4 not have the burden of proof on the challenged finding, the appellant must show that no evidence

supports the adverse finding; the challenge fails if more than a scintilla of evidence supports the

finding. Burroughs Wellcome Co. v.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Superior Ironworks, Inc. v. Roll Form Products, Inc.
789 S.W.2d 430 (Court of Appeals of Texas, 1990)
Stafford v. Stafford
726 S.W.2d 14 (Texas Supreme Court, 1987)
Anderson v. City of Seven Points
806 S.W.2d 791 (Texas Supreme Court, 1991)
Pool v. Ford Motor Co.
715 S.W.2d 629 (Texas Supreme Court, 1986)
Westech Engineering, Inc. v. Clearwater Constructors, Inc.
835 S.W.2d 190 (Court of Appeals of Texas, 1992)
Burroughs Wellcome Co. v. Crye
907 S.W.2d 497 (Texas Supreme Court, 1995)
Stable Energy, L.P. v. Kachina Oil & Gas, Inc.
52 S.W.3d 327 (Court of Appeals of Texas, 2001)
Stable Energy, L.P. v. Newberry
999 S.W.2d 538 (Court of Appeals of Texas, 1999)
Ames v. Ames
776 S.W.2d 154 (Texas Supreme Court, 1989)
Cropper v. Caterpillar Tractor Co.
754 S.W.2d 646 (Texas Supreme Court, 1988)
McGalliard v. Kuhlmann
722 S.W.2d 694 (Texas Supreme Court, 1986)
Asai v. Vanco Insulation Abatement, Inc.
932 S.W.2d 118 (Court of Appeals of Texas, 1996)
Garza v. Alviar
395 S.W.2d 821 (Texas Supreme Court, 1965)
Smith v. Central Freight Lines, Inc.
774 S.W.2d 411 (Court of Appeals of Texas, 1989)
Gill Savings Ass'n v. Chair King, Inc.
797 S.W.2d 31 (Texas Supreme Court, 1990)
Praesel v. Johnson
967 S.W.2d 391 (Texas Supreme Court, 1998)
Sterner v. Marathon Oil Co.
767 S.W.2d 686 (Texas Supreme Court, 1989)
Cain v. Bain
709 S.W.2d 175 (Texas Supreme Court, 1986)

Cite This Page — Counsel Stack

Bluebook (online)
Janice Suzanne Allen v. Hutchison Construction, Inc., Counsel Stack Legal Research, https://law.counselstack.com/opinion/janice-suzanne-allen-v-hutchison-construction-inc-texapp-2002.