JANEY CONSTRUCTION MANAGEMENT AND CONSULTING, INC. v. RANDI LOUISE WHITMORE GUSCOTT & Others.

CourtMassachusetts Appeals Court
DecidedApril 27, 2026
Docket25-P-0466
StatusUnpublished

This text of JANEY CONSTRUCTION MANAGEMENT AND CONSULTING, INC. v. RANDI LOUISE WHITMORE GUSCOTT & Others. (JANEY CONSTRUCTION MANAGEMENT AND CONSULTING, INC. v. RANDI LOUISE WHITMORE GUSCOTT & Others.) is published on Counsel Stack Legal Research, covering Massachusetts Appeals Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
JANEY CONSTRUCTION MANAGEMENT AND CONSULTING, INC. v. RANDI LOUISE WHITMORE GUSCOTT & Others., (Mass. Ct. App. 2026).

Opinion

NOTICE: Summary decisions issued by the Appeals Court pursuant to M.A.C. Rule 23.0, as appearing in 97 Mass. App. Ct. 1017 (2020) (formerly known as rule 1:28, as amended by 73 Mass. App. Ct. 1001 [2009]), are primarily directed to the parties and, therefore, may not fully address the facts of the case or the panel's decisional rationale. Moreover, such decisions are not circulated to the entire court and, therefore, represent only the views of the panel that decided the case. A summary decision pursuant to rule 23.0 or rule 1:28 issued after February 25, 2008, may be cited for its persuasive value but, because of the limitations noted above, not as binding precedent. See Chace v. Curran, 71 Mass. App. Ct. 258, 260 n.4 (2008).

COMMONWEALTH OF MASSACHUSETTS

APPEALS COURT

25-P-466

JANEY CONSTRUCTION MANAGEMENT AND CONSULTING, INC.

vs.

RANDI LOUISE WHITMORE GUSCOTT 1 & others. 2

MEMORANDUM AND ORDER PURSUANT TO RULE 23.0

This case arises from a dispute between a construction

company and a deceased homeowner's heirs and estate over a

written construction contract (contract) to rebuild the

decedent's home (project) after it was destroyed by a tragic

fire. The plaintiff construction company, Janey Construction

Management and Consulting, Inc., commenced this action in

Superior Court seeking to enforce a mechanic's lien, and to

1As an heir of Valerie Whitmore Guscott, also known as Valerie Faye Whitmore Guscott.

2Charlie Rose Whitmore Guscott and Kennet Bartley Whitmore Guscott, as heirs of Valerie Whitmore Guscott, and Wanda Whitmore, as the personal representative of the estate of Valerie Whitmore Guscott. recover damages for breach of contract and quantum meruit. The

personal representative of the estate of Valerie Whitmore

Guscott filed a counterclaim for breach of contract, negligence,

violation of G. L. c. 142A (Massachusetts Home Improvement Act),

violation of G. L. c. 93A (Massachusetts Consumer Protection

Act), and sought a declaratory judgment regarding the parties'

rights and obligations in connection with the project. 3 A judge

(motion judge) dismissed the plaintiff's claims for enforcement

of a mechanic's lien and quantum meruit about eighteen months

before trial. Following a six-day trial, a jury found both

parties breached the contract but awarded no damages. The jury

issued an advisory opinion that the plaintiff was liable for

several G. L. c. 93A violations and recommended damages. After

a hearing, careful consideration of the trial evidence, and

review of the parties' post-trial written submissions, the trial

judge issued detailed findings that adopted the jury's advisory

verdict in part and ordered damages for the defendants totaling

$103,250. 4

3 The negligence claim was dismissed by agreement before it reached the jury. The Massachusetts Home Improvement Act claim was merged with the G. L. c. 93A claim.

4 The jury's advisory award included an additional $200,000 for the plaintiff charging a different interest rate from that provided in the contract, which the judge rejected.

2 On appeal, the plaintiff claims that the motion judge erred

in dismissing the quantum meruit claim, the trial judge abused

her discretion by allowing an expert witness to testify on

certain issues, and the final damages awarded were excessive.

We affirm.

Background. In March 2017, a fire burned down Valerie

Whitmore Guscott's home, killing her husband and father. The

plaintiff's principal, Greg Janey, had known Whitmore Guscott's

deceased husband for over forty years as a mentor in the

construction business. In December 2017, Whitmore Guscott

contracted with the plaintiff to rebuild her home. The

scheduled completion date for the project was March 30, 2018.

Payment for the project was to be in a lump sum funded by fire

insurance proceeds (policy). The project faced substantial

delays, which the plaintiff contends were due to a delay in

receiving funds from insurance, and the defendants claim were

due to poor project management. Whitmore Guscott lived in a

rental property for about a year until the temporary living

expense allowance under the policy was exhausted. 5 For over a

year, beginning in May 2018, two months after the scheduled

completion date, until a certificate of occupancy was issued for

the project in June 2019, Whitmore Guscott and her children

5 Her three children attended college and resided with her when not at school.

3 lived at several hotels and stayed in relatives' homes. When

the Whitmore Guscott family finally returned to their rebuilt

home, they encountered a host of construction defects and

property damage. Ultimately, the plaintiff did not complete all

the repairs, and the defendants did not pay the full contract

price.

Discussion. 1. The quantum meruit claim. Generally, "[a]

plaintiff is not entitled to recovery on a theory of quantum

meruit where there is a valid contract that defines the

obligations of the parties." Boston Med. Ctr. Corp. v.

Secretary of the Executive Office of Human Servs., 443 Mass.

447, 467 (2012). There are two exceptions to this rule: (1)

where the parties dispute whether there was a valid contract and

the claims are brought in the alternative, see Chang v.

Winklevoss, 95 Mass. App. Ct. 202, 211 (2019); and (2) where the

plaintiff claims to have conferred additional value not covered

by the contract. See Sugarman & Sugarman, P.C. v. Shapiro, 102

Mass. App. Ct. 816, 819-820 (2023). Here, the plaintiff does

not dispute that there was a valid, fully integrated

construction contract between the parties for the project. Nor

does the plaintiff claim that any additional value was conferred

beyond the scope of the contract. Instead, relying solely on

the Supreme Judicial Court's holding in G4S Tech. LLC v.

Massachusetts Tech. Park Corp., 479 Mass. 721 (2018) (G4S) that

4 a contractor may maintain a contract and quantum meruit claim

despite the contractor's failure to comply strictly with

contractual requirements unrelated to the design and

construction itself, the plaintiff asserts that the motion judge

erred by dismissing its quantum meruit claim. We disagree.

In G4S, a builder claimed to have completed around $10

million in services that were uncompensated and uncovered by the

contract, because the other party did not complete necessary

preparation work before construction. G4S at 727. The Supreme

Judicial Court held that the builder was barred from contractual

recovery because of material breaches of the contract's payment

terms, unrelated to the construction itself, but potentially

could recover under equitable theories for the $10 million extra

value provided. Id. at 723, 735. Thus, G4S is an example of,

not an exception to, the general requirement that a plaintiff

must identify services not covered by a valid contract to

proceed with a quantum meruit claim. G4S did not alter the

requirement that a plaintiff must identify value conferred

beyond the contract to sustain a quantum meruit claim. Here,

the plaintiff did not show at the motion to dismiss stage that

the exception contained in G4S applies.

2. Admission of expert testimony. The plaintiff also

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Ficara v. Belleau
117 N.E.2d 287 (Massachusetts Supreme Judicial Court, 1954)
Department of Youth Services v. a Juvenile
499 N.E.2d 812 (Massachusetts Supreme Judicial Court, 1986)
G4S Technology LLC v. Massachusetts Technology Park Corp.
99 N.E.3d 728 (Massachusetts Supreme Judicial Court, 2018)
The Exhibit Source, Inc. v. Wells Avenue Business Center, LLC
114 N.E.3d 993 (Massachusetts Appeals Court, 2018)
Chang v. Winklevoss
123 N.E.3d 204 (Massachusetts Appeals Court, 2019)
Kattar v. Demoulas
433 Mass. 1 (Massachusetts Supreme Judicial Court, 2000)
Fabre v. Walton
802 N.E.2d 1030 (Massachusetts Supreme Judicial Court, 2004)
Hancock v. Commissioner of Education
443 Mass. 428 (Massachusetts Supreme Judicial Court, 2005)
Chace v. Curran
881 N.E.2d 792 (Massachusetts Appeals Court, 2008)

Cite This Page — Counsel Stack

Bluebook (online)
JANEY CONSTRUCTION MANAGEMENT AND CONSULTING, INC. v. RANDI LOUISE WHITMORE GUSCOTT & Others., Counsel Stack Legal Research, https://law.counselstack.com/opinion/janey-construction-management-and-consulting-inc-v-randi-louise-whitmore-massappct-2026.