JANEY CONSTRUCTION MANAGEMENT AND CONSULTING, INC. v. RANDI LOUISE WHITMORE GUSCOTT & Others.
Opinion
NOTICE: Summary decisions issued by the Appeals Court pursuant to M.A.C. Rule 23.0, as appearing in 97 Mass. App. Ct. 1017 (2020) (formerly known as rule 1:28, as amended by 73 Mass. App. Ct. 1001 [2009]), are primarily directed to the parties and, therefore, may not fully address the facts of the case or the panel's decisional rationale. Moreover, such decisions are not circulated to the entire court and, therefore, represent only the views of the panel that decided the case. A summary decision pursuant to rule 23.0 or rule 1:28 issued after February 25, 2008, may be cited for its persuasive value but, because of the limitations noted above, not as binding precedent. See Chace v. Curran, 71 Mass. App. Ct. 258, 260 n.4 (2008).
COMMONWEALTH OF MASSACHUSETTS
APPEALS COURT
25-P-466
JANEY CONSTRUCTION MANAGEMENT AND CONSULTING, INC.
vs.
RANDI LOUISE WHITMORE GUSCOTT 1 & others. 2
MEMORANDUM AND ORDER PURSUANT TO RULE 23.0
This case arises from a dispute between a construction
company and a deceased homeowner's heirs and estate over a
written construction contract (contract) to rebuild the
decedent's home (project) after it was destroyed by a tragic
fire. The plaintiff construction company, Janey Construction
Management and Consulting, Inc., commenced this action in
Superior Court seeking to enforce a mechanic's lien, and to
recover damages for breach of contract and quantum meruit. The personal representative of the estate of Valerie Whitmore Guscott filed a counterclaim for breach of contract, negligence, violation of G. L. c. 142A (Massachusetts Home Improvement Act), violation of G. L. c. 93A (Massachusetts Consumer Protection Act), and sought a declaratory judgment regarding the parties' rights and obligations in connection with the project. 3 A judge (motion judge) dismissed the plaintiff's claims for enforcement of a mechanic's lien and quantum meruit about eighteen months before trial. Following a six-day trial, a jury found both parties breached the contract but awarded no damages. The jury issued an advisory opinion that the plaintiff was liable for several G. L. c. 93A violations and recommended damages. After a hearing, careful consideration of the trial evidence, and review of the parties' post-trial written submissions, the trial judge issued detailed findings that adopted the jury's advisory verdict in part and ordered damages for the defendants totaling $103,250. 4
On appeal, the plaintiff claims that the motion judge erred in dismissing the quantum meruit claim, the trial judge abused her discretion by allowing an expert witness to testify on certain issues, and the final damages awarded were excessive. We affirm.
Background. In March 2017, a fire burned down Valerie Whitmore Guscott's home, killing her husband and father. The plaintiff's principal, Greg Janey, had known Whitmore Guscott's deceased husband for over forty years as a mentor in the construction business. In December 2017, Whitmore Guscott contracted with the plaintiff to rebuild her home. The scheduled completion date for the project was March 30, 2018. Payment for the project was to be in a lump sum funded by fire insurance proceeds (policy). The project faced substantial delays, which the plaintiff contends were due to a delay in receiving funds from insurance, and the defendants claim were due to poor project management. Whitmore Guscott lived in a rental property for about a year until the temporary living expense allowance under the policy was exhausted. 5 For over a year, beginning in May 2018, two months after the scheduled completion date, until a certificate of occupancy was issued for the project in June 2019, Whitmore Guscott and her children lived
at several hotels and stayed in relatives' homes. When the Whitmore Guscott family finally returned to their rebuilt home, they encountered a host of construction defects and property damage. Ultimately, the plaintiff did not complete all the repairs, and the defendants did not pay the full contract price.
Discussion. 1. The quantum meruit claim. Generally, "[a]
plaintiff is not entitled to recovery on a theory of quantum meruit where there is a valid contract that defines the obligations of the parties." Boston Med. Ctr. Corp. v. Secretary of the Executive Office of Human Servs., 443 Mass. 447, 467 (2012). There are two exceptions to this rule: (1) where the parties dispute whether there was a valid contract and the claims are brought in the alternative, see Chang v. Winklevoss, 95 Mass. App. Ct. 202, 211 (2019); and (2) where the plaintiff claims to have conferred additional value not covered by the contract. See Sugarman & Sugarman, P.C. v. Shapiro, 102 Mass. App. Ct. 816, 819-820 (2023). Here, the plaintiff does not dispute that there was a valid, fully integrated construction contract between the parties for the project. Nor does the plaintiff claim that any additional value was conferred beyond the scope of the contract. Instead, relying solely on the Supreme Judicial Court's holding in G4S Tech. LLC v. Massachusetts Tech. Park Corp., 479 Mass. 721 (2018) (G4S) that
a contractor may maintain a contract and quantum meruit claim despite the contractor's failure to comply strictly with contractual requirements unrelated to the design and construction itself, the plaintiff asserts that the motion judge erred by dismissing its quantum meruit claim. We disagree.
In G4S, a builder claimed to have completed around $10 million in services that were uncompensated and uncovered by the contract, because the other party did not complete necessary preparation work before construction. G4S at 727. The Supreme Judicial Court held that the builder was barred from contractual recovery because of material breaches of the contract's payment terms, unrelated to the construction itself, but potentially could recover under equitable theories for the $10 million extra value provided. Id. at 723, 735. Thus, G4S is an example of, not an exception to, the general requirement that a plaintiff must identify services not covered by a valid contract to proceed with a quantum meruit claim. G4S did not alter the requirement that a plaintiff must identify value conferred beyond the contract to sustain a quantum meruit claim. Here, the plaintiff did not show at the motion to dismiss stage that the exception contained in G4S applies.
2. Admission of expert testimony. The plaintiff also argues that the trial judge abused her discretion by allowing the defendants' expert witness to testify to the cost of repair,
the causes of the construction delay, and the causes of water damage in the home. We are not persuaded that any of the contested testimony was admitted erroneously.
Free access — add to your briefcase to read the full text and ask questions with AI
JANEY CONSTRUCTION MANAGEMENT AND CONSULTING, INC. v. RANDI LOUISE WHITMORE GUSCOTT & Others. (JANEY CONSTRUCTION MANAGEMENT AND CONSULTING, INC. v. RANDI LOUISE WHITMORE GUSCOTT & Others.) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.