James Wiley d/b/a Wiley's Construction v. Christopher Haynes

CourtIntermediate Court of Appeals of West Virginia
DecidedMay 23, 2024
Docket23-ica-143
StatusPublished

This text of James Wiley d/b/a Wiley's Construction v. Christopher Haynes (James Wiley d/b/a Wiley's Construction v. Christopher Haynes) is published on Counsel Stack Legal Research, covering Intermediate Court of Appeals of West Virginia primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
James Wiley d/b/a Wiley's Construction v. Christopher Haynes, (W. Va. Ct. App. 2024).

Opinion

IN THE INTERMEDIATE COURT OF APPEALS OF WEST VIRGINIA FILED May 23, 2024 JAMES WILEY D/B/A WILEY’S CONSTRUCTION, ASHLEY N. DEEM, DEPUTY CLERK Defendant Below, Petitioner INTERMEDIATE COURT OF APPEALS OF WEST VIRGINIA

v.) No. 23-ICA-143 (Cir. Ct. Mercer Cnty. No. CC-28-2018-C-309-WS)

CHRISTOPHER HAYNES, Plaintiff Below, Respondent

MEMORANDUM DECISION

Petitioner James Wiley d/b/a Wiley’s Construction (“Wiley”) appeals the Circuit Court of Mercer County’s order denying his Rule 59 motion for a new trial dated March 9, 2023. Respondent Christopher Haynes (“Haynes”) filed a timely response.1 The issue on appeal is whether the circuit court erred in concluding that a “finished basement” was included in the terms of the contract between the parties and awarding damages based on that conclusion.

This Court has jurisdiction over this appeal pursuant to West Virginia Code § 51- 11-4 (2022). After considering the parties’ arguments, the record on appeal, and the applicable law, this Court finds no substantial question of law and no prejudicial error. For these reasons, a memorandum decision affirming the circuit court’s order is appropriate under Rule 21 of the Rules of Appellate Procedure.

This case involves a contract dispute, specifically whether the terms of the contract included a finished basement. In 2014, Haynes purchased a piece of real estate in Mercer County. In 2016, Haynes, with the assistance of his parents, purchased a “log kit” for $16,500, which included house plans and instructions on how to construct the residence.

It is undisputed that at some point in April or early May of 2017, Haynes, his father, and Wiley met at the site where the residence was to be built to discuss the nature and cost of construction. At that time, Haynes gave Wiley the house plans (i.e., log kit). The

1 Mr. Wiley is represented by Tracey A. Rohrbaugh, Esq. Mr. Haynes is represented by Anthony R. Veneri, Esq.

1 conversation moved to a nearby store, and there Wiley drew a diagram of the basement that would be finished.2

On May 24, 2017, Haynes and Wiley entered into the initial contract, which included partial construction of the dwelling. This initial contract only required Wiley to construct the exterior of the log structure on a basement foundation for a price of $33,000. Further, the contract provided that Wiley would secure the costs of constructing the foundation (footers and floors) from Reynolds Construction, obtain the costs for the electrical work from Vest Electric, provide a bid for the plumbing of the residence, and obtain a bid from Compton Construction for the sheetrock work in the residence.

At some point after entering the contract, Haynes took the contract to MCNB Bank seeking a construction loan. However, the bank would not accept a contract for partial construction. The bank required a complete, “turn-key” contract, so that upon completion of the contract, the residence would be a full and complete structure. On August 10, 2017, Wiley drafted an “Addendum” to the original contract. With the Addendum the contract provided for a complete, “turn-key” construction of the residence for a price of $195,000.3 Notably the August 10, 2017, contract stated:

This Addendum of existing contract dated May 24, 2017. This Addendum while consist of Exterior and Interior of Total of $195,000 with see draw schedule dated May 24, 2017.4

With the turn-key contract in hand, and MCNB’s pre-construction appraisal of the completed structure which came in at $275,000, Haynes was able to secure a construction loan for $202,500. After the deduction of loan costs, Haynes was left with $196,898.69 to spend on the construction of the residence.

In August 2017, once Reynolds Construction laid the foundation, Wiley began construction on the property. The first disbursement by MCNB occurred on August 21, 2017, when $10,506.54 was paid to Lowe’s for the roof trusses. However, in March 2018,

2 Wiley admits to drawing the diagram, however, at trial neither party entered the drawing into evidence. 3 Attached to the August 10, 2017, contract was a “Schedule of Disbursements” pursuant to the percentages of completion that was generated by Wiley, which also included a specific draw schedule for the completion of the residence. The disbursement schedule and draw schedule were back dated by Wiley to the May 24, 2017, contract. 4 Under both the May 24, 2017, and August 10, 2017, contracts Wiley was to complete all work in a “workmanlike manner according to standard practices.”

2 after about seven months of working on the residence, Haynes relayed to Wiley that he had run out of money and could no longer pay him. The last disbursement by MCNB occurred on March 22, 2018, for $3,291.30 to Lowe’s for fans and other items.

On November 8, 2018, Haynes filed suit against Wiley in Mercer County Circuit Court alleging that Wiley breached the contract between the parties because Wiley failed to provide him with a complete log home for the total contract price of $195,000. On November 20, 2018, Wiley answered and denied the complaint and filed a counterclaim for breach of contract and unjust enrichment. A bench trial was conducted on the three nonconsecutive days in 2022: January 14, January 28, and February 15.

On June 7, 2022, following the bench trial, the circuit court entered its judgment order, concluding that by a preponderance of the evidence, the written contract between Wiley and Haynes included Wiley building the full interior and exterior of the residence including a finished basement for the sum of $195,000. The court found that the written contract incorporated not only all the work included on the May 24, 2017, contract, but also the two-page disbursement schedule that included the foundation, framing, plumbing, wiring, sheetrock, roof, floors, painting, electrical fixtures, appliances, plumbing fixtures, lot preparation, decks, windows and doors, gutters, septic system, grading and landscaping, and other construction.

The circuit court concluded that by a preponderance of the evidence, Haynes proved that Wiley breached the contract by (1) not completing the work to be performed,5 and (2) completing some work in a defective manner that was not “workmanlike” as required by the written contract. The construction which was not workmanlike as required by the contract included, but was not limited to: the deck, the band boards, the lack of the appropriate gap above the windows and doors, both sets of stairs, the floors, the island, the garage ceiling, the roof, and the failure to properly miter joints and line up boards.

In regard to contract damages, the circuit court concluded that by a preponderance of the evidence, Ricky Duncan’s $151,973.30 estimate was reasonable, and the appropriate amount required to complete the residence in a workmanlike manner as required by the contract.6 By a preponderance of the evidence, the court found that Mr. Duncan’s estimate, if perfected, would correct the defects itemized, as well as complete the work not completed as reflected. The contract between the parties not only contemplated all work to be completed in a workmanlike manner, but that the contract would result in a completed residence. Further, the court found Wiley’s expert, Derrick Whitt, was not credible, and his

5 The circuit court listed each item not completed in its judgment order. Judgment Order 7-9. 6 Mr. Duncan was Haynes’ construction expert.

3 estimate did not incorporate all the work that was performed in a non-workmanlike manner. The court stated that although the estimate of $151,973.30 may seem high in light of the original contract price, the court did not have any other comparable estimates with which to calculate damages in this case.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Trenton Const. Co., Inc. v. Straub
310 S.E.2d 496 (West Virginia Supreme Court, 1983)
Tennant v. Marion Health Care Foundation, Inc.
459 S.E.2d 374 (West Virginia Supreme Court, 1995)
Realmark Developments, Inc. v. Ranson
542 S.E.2d 880 (West Virginia Supreme Court, 2000)

Cite This Page — Counsel Stack

Bluebook (online)
James Wiley d/b/a Wiley's Construction v. Christopher Haynes, Counsel Stack Legal Research, https://law.counselstack.com/opinion/james-wiley-dba-wileys-construction-v-christopher-haynes-wvactapp-2024.