James Petrozello Co., Inc. v. Chatham Tp.
This text of 182 A.2d 572 (James Petrozello Co., Inc. v. Chatham Tp.) is published on Counsel Stack Legal Research, covering New Jersey Superior Court Appellate Division primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.
Opinion
JAMES PETROZELLO COMPANY, INC., ET AL., PLAINTIFFS-RESPONDENTS,
v.
TOWNSHIP OF CHATHAM, ETC., PETER ROSELLE & SONS CO., ET AL., DEFENDANTS-APPELLANTS.
Superior Court of New Jersey, Appellate Division.
*175 Before Judges CONFORD, GAULKIN and KILKENNY.
Mr. John R. Miller argued the cause for appellant Township of Chatham, etc.
Mr. Samuel A. Larner argued the cause for appellants Peter Roselle & Sons, et al. (Messrs. Budd, Larner & Kent, attorneys).
Mr. Merritt Lane, Jr., argued the cause for respondents (Messrs. McCarter & English, attorneys).
The opinion of the court was delivered by KILKENNY, J.A.D.
Plaintiffs' action in the Superior Court, Law Division, to set aside the township's award of a garbage contract for five years to the defendant contractors resulted in a judgment setting aside the award, and defendants appealed.
The facts are not in dispute. On November 9, 1961 the Township of Chatham advertised for bids for the collection of garbage and other refuse from properties within the municipality, and for the disposal thereof outside the limits of the township for alternate periods of three, four and five years. The "Information for Bidders" called for a lump sum bid for the collection and disposal of the garbage and refuse from all structures in existence upon the commencement of the term of the contract, and also for a unit bid per month charge for each of several categories of structures erected in the future during the term of the contract. Prospective bidders were directed to make a careful examination *176 of the properties in the township from which the garbage and refuse would be collected, as well as the municipal zoning ordinance. Information was given as to the present land uses and the approximate number of existing buildings in each classification. The bidders were referred to the land use provisions in the zoning ordinance and were told that "under present zoning no more than 200 individual apartments [units in apartment houses] could be constructed." There was also furnished a guide for the projection of growth in single-family residences in the form of statistics as to the number of building permits issued for single-family residences in each year from 1956 down through August of 1961. Building permits of single-family residences had varied from a high of 87 in 1956 to a low of 31 in 1958 and in 1960; and through August of 1961, 40 such permits had been issued.
The respective bids of the plaintiff contractors and defendant contractors were as follows:
Petrozello Roselle
For existing properties $240,000.00 $245,000.00
5 years
Each residence constructed
during term of contract $2.65 per mo. $2.25 per mo.
Each neighborhood business
constructed during term
of contract 5.00 per mo. 2.25 per mo.
Each group of six apartment
buildings constructed during
term of contract 9.00 per mo. 6.00 per mo.
Each office building constructed
during term of contract 150.00 per mo. 5.00 per mo.
Each municipal building
constructed during term
of contract 25.00 per mo. 5.00 per mo.
Each school constructed
during term of contract 50.00 per mo. 10.00 per mo.
*177 When the bids were received on December 7, 1961, they were referred to the committee dealing with the subject matter, for study and analysis. The committee reported thereafter that in its judgment new development in the municipality during the five-year term of the contract would result in 48 new residences per year (four per month); 60 apartments occupied in April 1964 (ten groups of six individual apartments); 140 apartments occupied in April 1965 (24 groups of six individual apartments); one office building or research laboratory occupied in April 1965; one municipal building occupied in April 1963; one high school opening in September 1962; and one elementary school opening in September 1965. Applying that prognosis against the unit bids received and adding thereto the lump sum base bids of the two lowest bidding contractors, the committee concluded in its report to the governing body that the total cost over the five-year period to the municipality would be:
Petrozello ................. $275,422.
Roselle ..................... $268,156
Accordingly, the township committee determined that Roselle was the lowest bidder and adopted a resolution on February 1, 1962 awarding the garbage contract to it for the period of five years.
The trial court found no fraud, chicanery or design on the part of the municipal officials to favor any bidder. It observed that the narrow question was whether the specifications were proper, "whether they afforded common standards for bidding which would produce sound competition." There was no denial that the committee to which the bids were referred for analysis, as the trial court observed, "made a serious and studious effort to work out probable quantities after the receipt of bids, but there is a serious question as to whether estimates of quantities should not have been submitted to the prospective bidders in the specifications." (Emphasis ours.) The trial court concluded that *178 "the committee in making its estimate used a reasonable and sound approach to the matter, but it erred in not doing so before the bidding for inclusion in the specifications. This is sufficient to vitiate the resolution awarding the contract."
It seems clear that the information upon which the municipal officials based their estimate of future development was available before the receipt of the bids and that the estimates as to structures in the several categories to be erected during the five-year term of the contract could have been made known to the several bidders in advance of the bidding. There is no contention made that the estimates adopted after the bids were received were unreasonable or excessive or made in bad faith. Rather, the position of the plaintiff taxpayer, Goodman, is that the township did not inform prospective bidders that the unit price quotations for future construction would be taken into consideration along with the lump sum base bid in determining who was the lowest bidder; and the failure to promulgate estimates before the reception of bids as to future development left the bidders without a common standard upon which to base their bids and created the possibility of an arbitrary computation of future growth by the municipal officials, so that one bidder rather than another could be favored by the capricious use of these variable factors.
To conform with statutory requirements, N.J.S.A. 40:50-1, specifications in an invitation to bid "must be as definite, precise and full as practicable in view of the character of the work, the quality and quantity of the materials to be furnished." Waszen v. Atlantic City, 137 N.J.L. 535, 537 (Sup. Ct. 1948), reversed on other grounds 1 N.J. 272 (1949). The specifications must "furnish the same information to all prospective bidders, so that there may be intelligent bidding." Phifer v. Bayonne, 105 N.J.L. 524, 525 (Sup. Ct. 1929). To invalidate an award for a deficiency in the specifications, "the irregularity *179
Free access — add to your briefcase to read the full text and ask questions with AI
Related
Cite This Page — Counsel Stack
182 A.2d 572, 75 N.J. Super. 173, Counsel Stack Legal Research, https://law.counselstack.com/opinion/james-petrozello-co-inc-v-chatham-tp-njsuperctappdiv-1962.