James McHugh Sons, Inc. v. United States

99 Ct. Cl. 414, 1943 U.S. Ct. Cl. LEXIS 66, 1943 WL 4228
CourtUnited States Court of Claims
DecidedMay 3, 1943
DocketNo. 43154
StatusPublished
Cited by11 cases

This text of 99 Ct. Cl. 414 (James McHugh Sons, Inc. v. United States) is published on Counsel Stack Legal Research, covering United States Court of Claims primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
James McHugh Sons, Inc. v. United States, 99 Ct. Cl. 414, 1943 U.S. Ct. Cl. LEXIS 66, 1943 WL 4228 (cc 1943).

Opinion

Whitaker, Judge,

delivered the opinion of the court:

On December 1,1933, plaintiff entered into a contract with the defendant for the construction of 18 four-family apartments at Fort Sill, Oklahoma. It sues to recover on five items of work it was required to do which it alleges were not called for by the contract. Its first claim is for additional back-filling in the amount of $195.24; the second, for additional cost of constructing fireplaces $393.00; third, for the cost of placing mortar between tiles, $4,298.13; fourth, for the cost of louvers, $40.52; and fifth, for the cost of grinding and rubbing concrete surfaces, $3,174.15.

To all of these-claims the defendant first interposes the defense that the decision of the contracting officer on these items was adverse to plaintiff and that plaintiff took no appeal to the head of the department.

Instead of issuing change orders covering the various items uf work not called for by the original contract before the work was done, the Constructing Quartermaster directed [429]*429plaintiff to do the work first and to submit a claim for it upon its completion. Accordingly, plaintiff on July 7, 1934 submitted a claim for 18 items of extra work. The Constructing Quartermaster prepared a propo'sed change order covering these various items and forwarded it to the Quartermaster General for approval. Most of the items were approved, and a change order apparently was issued covering them. The items on which this suit is based were disapproved and, hence, no change order was issued with respect to them.

No appeal was taken from this action of the Quartermaster General, who was the contracting officer. However, paragraph 3 of the letter from the Quartermaster General to the Constructing Quartermaster, quoted in the letter of the Constructing Quartermaster to the plaintiff dated October 22, 1934, reads as follows:

Regarding such items included in your draft of the proposed change order as have been disallowed by this office, the contractor is at liberty, if he so desires, to file a claim therefor after the completion of the contract.

Upon receipt of this letter plaintiff wrote the Constructing Quartermaster on October 25,1934, requesting reconsideration of the items disapproved, its letter concluding:

We do not desire to present a claim against the Government after the completion of our contract, and we feel that after the facts [we] have recited are realized by the Office of' the Quartermaster General, that our request for a change order to cover the above items will be approved. We have faith in your fairness and judgment.
As we expect to complete and turn over to the Constructing Quartermaster the last of the 18 four-family apartments by October 31, 1934, we request immediate action on the reconsideration of these items, in order that when our contract is completed, they [sic] will be no delay in our final payment.

No answer was made to this letter; the matter lay dormant until after the completion of the entire work. The action taken as outlined in the Constructing Quartermaster’s letter of October 22, 1934, therefore, was not final and no appeal was necessary at the time.

[430]*430After the work had been completed the plaintiff executed a release excepting therefrom the claims in suit. Thereafter it wrote the Quartermaster General a series of letters with reference to them. In reply thereto the Quartermaster General wrote the plaintiff on February 16, 1935, stating that he would prepare an administrative report to be submitted to the Comptroller General with the claims, and that plaintiff might file any additional documentary evidence it desired. The Quartermaster General, however, said:

As this office is without authority to render any decisions on the claims and can only present the facts for consideration by The Comptroller General, it is considered advisable that your firm submit all of the facts in writing rather than verbally, * * *

but it was stated that an interview would be granted if desired. The interview was granted and plaintiff presented additional evidence and argument to a committee appointed by the Quartermaster General to consider the claims. The plaintiff, however, was never advised of the decision of the Quartermaster General, although it requested advice thereon under date of April 17,1935, saying that unless it was advised of his decision it “would have nothing from which to take our appeal, and, therefore, [we] request that prior to forwarding the matter to the General Accounting Office that you render a decision on the matter and advise us so that if not satisfied we may take an appeal therefrom.” In reply thereto on April 20,1935 the Quartermaster General wrote plaintiff in part as follows:

You are apparently not aware of the procedure to be followed in forwarding claims to the General Accounting Office, which is under the jurisdiction of The Comptroller General of the United States for final settlement. The function of this office and of other Governmental Departments in forwarding claims to the General Accounting Office is to assemble all pertinent data and make a definite determination of fact. Any recommendation this office may make in transmitting these claims is confidential and the law prohibits the divulging of the nature thereof.
After your claim has been passed upon by the General Accounting Office it will advise you what disposition has been made thereof and will definitely outline the reasons for allowing or disallowing the various items [431]*431your If you are of the opinion that the findings of the General Accounting Office are based upon an erroneous statement of fact or additional evidence has arisen which might cause it to reverse its decision, you are at liberty to present your case to that office for reconsideration.

The Quartermaster General had an entirely erroneous conception of his duties under the contract. The contract called for decisions by him, and not by the Comptroller General, and the plaintiff, of course, was entitled to be advised of his decision. Since the Quartermaster General misconceived his function, he did not follow the provisions of the contract, and his failure to do so made it impossible for the plaintiff to avail itself of its contractual right to appeal to the head of the department. It follows, therefore, that its failure to appeal is no bar to its prosecution of its case in this court. We proceed, therefore, to consider the merits of the several items of plaintiff’s claim.

Claim for additional backfilling

The contracting officer disallowed this claim in his letter of October 22, 1934, on the ground that the unit price of $1.00 per cubic yard for earth excavation included backfill-ing. Apparently this is true. Plaintiff’s president admitted on cross-examination that in figuring on the original contract his estimate for excavation included the cost of back-filling. It would appear, therefore, that when the plaintiff bid $1.00 a cubic yard for additional earth excavation it meant that to include the cost of backfilling.

Defendant’s inspector had directed plaintiff to move all surplus earth to a place about 200 yards away, except so much of it as was needed for backfilling. The plaintiff did not leave sufficient earth near the foundation walls to do all the backfilling required and had to bring back some that had been removed.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

WRB Corp. v. United States
183 Ct. Cl. 409 (Court of Claims, 1968)
New York Shipbuilding Corporation v. The United States
385 F.2d 427 (Court of Claims, 1967)
C. J. Langenfelder & Son, Inc. v. The United States
341 F.2d 600 (Court of Claims, 1965)
C. J. Langenfelder & Son, Inc. v. United States
341 F.2d 600 (Court of Claims, 1965)
Stein Bros. Mfg. Co. v. The United States
337 F.2d 861 (Court of Claims, 1963)
Stein Bros. Mfg. Co. v. United States
337 F.2d 861 (Court of Claims, 1963)
Jefferson Construction Co. v. United States
151 Ct. Cl. 75 (Court of Claims, 1960)
Maxan Dress Corp. v. United States
115 F. Supp. 439 (Court of Claims, 1953)
Brister & Koester Lumber Corp. v. United States
188 F.2d 986 (D.C. Circuit, 1951)
Ross Engineering Co. v. Pace
153 F.2d 35 (Fourth Circuit, 1946)
Cape Ann Granite Co. v. United States
100 Ct. Cl. 53 (Court of Claims, 1943)

Cite This Page — Counsel Stack

Bluebook (online)
99 Ct. Cl. 414, 1943 U.S. Ct. Cl. LEXIS 66, 1943 WL 4228, Counsel Stack Legal Research, https://law.counselstack.com/opinion/james-mchugh-sons-inc-v-united-states-cc-1943.