James McHugh Sons, Inc. v. United States

89 Ct. Cl. 94, 1939 U.S. Ct. Cl. LEXIS 190, 1939 WL 4209
CourtUnited States Court of Claims
DecidedMay 29, 1939
DocketNo. 43155
StatusPublished

This text of 89 Ct. Cl. 94 (James McHugh Sons, Inc. v. United States) is published on Counsel Stack Legal Research, covering United States Court of Claims primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
James McHugh Sons, Inc. v. United States, 89 Ct. Cl. 94, 1939 U.S. Ct. Cl. LEXIS 190, 1939 WL 4209 (cc 1939).

Opinion

LittletoN, Judge,

delivered the opinion of the court:

The extra work and extra costs which plaintiff contends it was required by defendant to perform and incur outside the requirements of its contract dated May 29, 1980, are as follows:

Installing ventilating system-$2, 887.00

Installing plumbing fixtures_ 4, 599. 62

Reconstruction of ceilings_ 7,717. 70

Construction of porches- 8, 617.14

Extra plaster work around door frames and borrowed lights- 1, 525. 00

The defendant contends that all the items upon which plaintiff bases its claim were specified as a part of the work required by plaintiff’s contract with the Government and were shown by the drawings and specifications. We think the defendant’s position is correct. The drawings and specifications which are in evidence adequately disclose and refer to all the work upon which plaintiff bases its claim for extra compensation.

An invitation for bids for remodeling certain portions of the United States Veterans’ Hospital at Hines, Illinois, was issued on February 27,1930. The form of contract, the draw[111]*111ings, and the specifications, under which the work specified in the invitation for bids was to be performed, were available to plaintiff at that time. On March 22, 1930, plaintiff, after an inspection of the premises, submitted its bid for $133,288, which was accepted by the defendant, and a contract was entered into May 29,1930. Plaintiff commenced work thereunder June 28, 1930, and completed the same within the time allowed. The invitation for bids, after specifying certain alterations, also included in the work to be done “changes in and additions to existing construction as shown on the drawings.” Plaintiff proposed to furnish all labor and material and perform all work in strict accordance with the specifications and drawings mentioned therein, and the contract contained similar provisions. In the specifications plaintiff was invited to visit the portion of the buildings covered by the specifications and drawings, to make thorough examinations of the present arrangements and conditions, and to compare same carefully with the new plan. Under the terms of the specifications all such comparative conditions were to be considered by the contractor as a part of his bid on the material to be furnished and labor to be performed, and also for the furnishing of all new materials and labor for the full and satisfactory completion of the work according to the specifications and drawings. Plaintiff visited the site of the work before submitting its bid and was given full opportunity to make a thorough inspection. The specifications provided, among other things, that “Anything mentioned in the specifications and not shown on the drawings or shown on the drawings and not mentioned in the specifications shall be of like effect as if shown or mentioned in both.”

The evidence shows, and we have found as facts, that the specifications and the accompanying drawings, together with a proper inspection of the premises, were sufficient to advise one familiar with building remodeling work of all the work required to be performed upon which plaintiff bases its claim for extra compensation.

1. Ventilating System. — The specifications definitely required work in connection with the ventilating system as a part of the plaintiff’s contract. . On page 43, under the head[112]*112ing of “Mechanical Equipment,” the specifications stated as follows :

The general conditions set forth at the beginning of the specifications shall govern when practicable for all work in connection with plumbing, heating, ventilating, and electrical work shown on the drawings or specified herein.
Work Included. — This section of the specifications includes the finishing and installation in complete working order of plumbing, sanitary, and storm-sewer connections, hot and cold water with the building, roughing in for cooking equipment, and certain plumbing and other fixtures furnished by the Government, refrigerating units for drinking water, changes in and additions to heating and ventilating system, changes in and extension of conduit and electrical service, light, cooking and power, pipe covering, etc.

Paragraph M, page 7a, of the specifications provided that new materials, for construction not otherwise clearly specified should be of the same character, grade, and finish as that used in similar locations in other parts of the building, and that this included plumbing, heating, ventilating, and electrical equipment. A ventilating system was clearly disclosed and shown by the drawings. Ventilating ducts and registers already in the building were shown on the drawings on the floors of the building on which they were located and the drawings further showed the new work to be performed and the new ventilating ducts and registers, with the sizes thereof and the places where they were to be installed, which ducts and registers were not in the building at the time the contract was made.- The drawings specified the size of the sheet-metal ventilating' ducts and the registers, and there is no evidence that the defendant required plaintiff to install ventilating ducts and registers other than those shown on the drawings or to furnish material therefor different or more expensive than the material of which the ventilating system already in the building was constructed.

2. Plumbing Fixtures. — The material facts with reference to this item of plaintiff’s claim are set forth in findings 6 to 9, inclusive. This item of the claim relates to furnishing and installing thermostatic control valves, recording thermom[113]*113eters, and continuous-flow bathtubs. The contract is definite and specific in its requirement that the contractor shall furnish this equipment, although defendant furnished tubs then on hand. The specifications on page 43 provided “Special attention is called to the fact that within 30 days after the date of acceptance of bid the contractor must submit to the Director a complete list of the following material * * * giving the name and address of manufacturer and also, when so required for proper identification, the trade name and catalogue number of the following material proposed to be used in the work.”

The items listed thereafter on page 44 of the specifications included “Plumbing fixtures. Thermostatic Regulators for hot water with Recording Thermometer,” and on page 45 of the specifications the term “Plumbing Fixtures as indicated on drawings of new arrangements” is broken down and shown in separate items, among which is listed nine continuous-flow bath tubs to be installed in Unit G, 1st, 2nd, 3rd, and 4th floors, and one continuous-flow bath tub in Unit F of the building. Paragraph IP-35, page 59 of the specifications required the contractor to “furnish and install in connection with each continuous-flow tub an approved thermostatic control valve, etc.” Paragraph IP-35, page 60 of the specifications, provided that the contractor should “furnish and install, where shown on the plans, continuous-flow tubs. * * * Each continuous-flow tub shall be equipped with a recording thermometer * * *.” These provisions are clear and unambiguous, and show positively that plaintiff was required to perform the work and furnish the materials upon which this item of the claim is based. Included in this item of the claim is the claim of plaintiff for compensation for the cost of certain tub fittings for the continuous-flow bath tubs installed.

Free access — add to your briefcase to read the full text and ask questions with AI

Cite This Page — Counsel Stack

Bluebook (online)
89 Ct. Cl. 94, 1939 U.S. Ct. Cl. LEXIS 190, 1939 WL 4209, Counsel Stack Legal Research, https://law.counselstack.com/opinion/james-mchugh-sons-inc-v-united-states-cc-1939.