James M. Johnson v. Princeton Public Utilities Commission, and third party v. Hydrocon, Inc., Third Party

CourtCourt of Appeals of Minnesota
DecidedJanuary 4, 2016
DocketA15-38
StatusUnpublished

This text of James M. Johnson v. Princeton Public Utilities Commission, and third party v. Hydrocon, Inc., Third Party (James M. Johnson v. Princeton Public Utilities Commission, and third party v. Hydrocon, Inc., Third Party) is published on Counsel Stack Legal Research, covering Court of Appeals of Minnesota primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
James M. Johnson v. Princeton Public Utilities Commission, and third party v. Hydrocon, Inc., Third Party, (Mich. Ct. App. 2016).

Opinion

This opinion will be unpublished and may not be cited except as provided by Minn. Stat. § 480A.08, subd. 3 (2014).

STATE OF MINNESOTA IN COURT OF APPEALS A15-0038

James M. Johnson, et al., Appellants,

vs.

Princeton Public Utilities Commission, defendant and third party plaintiff, Respondent,

Hydrocon, Inc., Third Party Defendant.

Filed January 4, 2016 Affirmed in part, reversed in part, and remanded Cleary, Chief Judge

Mille Lacs County District Court File No. 48-CV-11-2174

James E. Lindell, Grim Daniel Howland, Lindell & Lavoie, LLP, Minneapolis, Minnesota (for appellants)

Larry D. Espel, Kathryn N. Hibbard, Katherine M. Swenson, Greene Espel PLLP, Minneapolis, Minnesota (for respondent) Considered and decided by Schellhas, Presiding Judge; Cleary, Chief Judge; and

Randall, Judge.

UNPUBLISHED OPINION

CLEARY, Chief Judge

In this appeal from a judgment entered following a jury trial of appellants James

Johnson (Johnson) and Sherri Johnson’s negligence claims arising out of an accident at a

construction site, appellants assert that the district court erred by (1) denying their motion

for judgment as a matter of law on liability; (2) denying their motion for a new trial on

damages; (3) granting remittitur of the jury award; and (4) granting respondent Princeton

Public Utilities Commission’s (the PUC) motion for a collateral-source offset. The PUC

cross-appeals, asserting that the district court erred by ruling that appellants’ negligence

claims were not barred by workers’ compensation election of remedies. We affirm in

part, reverse in part, and remand for entry of judgment for appellants in the amount of

$240,000.

FACTS

Appellant James Johnson was employed as a construction worker by third-party

defendant Hydrocon Inc. during the time relevant to this litigation. Hydrocon is a sewer

and water contractor. On August 26, 2009, the PUC and Hydrocon entered a contract

under which Hydrocon was to perform construction work on the water main serving an

ice arena in Princeton, Minnesota. The PUC agreed to secure an electric utility pole so

 Retired judge of the Minnesota Court of Appeals, serving by appointment pursuant to Minn. Const. art. VI, § 10.

2 that it would not fall while Hydrocon dug a ditch nearby. On the morning of August 31,

2009, employees of the PUC arrived at the construction site in order to secure the pole.

The PUC employees used a digger truck to secure the utility pole and

disconnected the utility wires from the pole so it would be out of service during the water

main work. Hydrocon was not involved in securing the pole. After multiple employees

of the PUC secured the pole, one employee, Thomas Otto, remained at the site all day to

supervise the pole.

Johnson operated the compacting machine, a ride-on vehicle that packs loose soil.

When the work near the pole was complete, Johnson informed Otto that Hydrocon

employees were done working near the pole, at which time Otto released the pole from

the digger truck that was securing it. Shortly after Otto drove the digger truck away from

the pole, it fell onto the roof of the compacting machine that Johnson was driving.

On February 15, 2011, Johnson reached a settlement regarding this incident with

Hydrocon’s workers’ compensation insurance providers. On September 30, 2011,

Johnson and his wife, appellant Sherri Johnson, filed a complaint against the PUC. The

PUC filed a third-party complaint against Hydrocon. After a settlement between the PUC

and Hydrocon, the Johnsons and PUC went to trial.

After trial, the jury returned a special-verdict form that contained three sets of two

questions regarding the parties’ negligence. These questions asked (1) if the PUC was

negligent and (2) whether the PUC’s negligence was a direct cause of Johnson’s injuries,

(3) if Johnson was negligent and (4) whether Johnson’s negligence was a direct cause of

his injuries, (5) if Hydrocon was negligent and (6) whether Hydrocon’s negligence was a

3 direct cause of Johnson’s injuries. The instructions stated that if the jury answered “yes”

to two or more of questions two, four, or six, meaning that more than one of the PUC,

Johnson, or Hydrocon had been negligent in a way that directly caused Johnson’s

injuries, only then should they answer question seven regarding apportionment of fault.

As to the PUC, the jury found it had been negligent and the negligence was a direct cause

of the injury. As to Johnson, the jury found he had been negligent but the negligence was

not a direct cause of the injury. As to Hydrocon, the jury found it was not negligent.

Despite finding only the PUC’s negligence directly caused the injury, the jury went on to

answer question seven, apportioning 70% of fault to the PUC and 30% to Johnson. The

jury valued damages at $240,000. Despite the inconsistent verdict, the judge dismissed

the jury.

On January 17, 2014, the district court ordered a new trial based on the jury’s

inconsistent special-verdict answers. Appellants objected to this decision. On May 13,

the district court offered appellants a remittitur, allowing them “to choose between entry

of judgment for seventy percent of the original jury verdict . . . or a new trial.”

Appellants did not reject remittitur. On July 14, the court entered a judgment for

appellants in the amount of $134,085.

Appellants and respondent both made post-trial motions. Appellants argued for

judgment as a matter of law (JMOL) that the PUC was the only party causally negligent

in the accident for JMOL with respect to damages and, in the alternative, for a new trial

on damages. Appellants also moved to vacate the district court’s ruling on collateral-

4 source offsets. Respondent sought JMOL as to its liability and filed a motion for fees and

costs. All motions were denied. This appeal followed.

DECISION

Common enterprise

We review a district court’s denial of a motion for JMOL de novo. Bahr v. Boise

Cascade Corp., 766 N.W.2d 910, 919 (Minn. 2009). However, “we view the evidence in

the light most favorable to the prevailing party.” Id.

[JMOL] should be granted: only in those unequivocal cases where (1) in the light of the evidence as a whole, it would clearly be the duty of the [district] court to set aside a contrary verdict as being manifestly against the entire evidence, or where (2) it would be contrary to the law applicable to the case.

Jerry’s Enters., Inc. v. Larkin, Hoffman, Daly & Lindgren, Ltd., 711 N.W.2d 811, 816

(Minn. 2006) (quotation omitted).

Respondent appeals the district court’s denial of its motion for JMOL. It argues

that the PUC and Hydrocon were engaged in a common enterprise and therefore,

appellants’ negligence claims fail as a matter of law. When an employer and a third party

are working in “furtherance of a common enterprise,” an injured employee must choose

between receiving workers’ compensation benefits through the employer or pursuing a

common-law negligence action against the third party. Minn. Stat. § 176.061, subds. 1, 4

(2014). A common enterprise exists between the employer and the third party where “the

masters have joined forces and in effect have put the servants into a common pool.”

Gleason v.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Braginsky v. State Farm Mutual Automobile Insurance Co.
624 N.W.2d 789 (Court of Appeals of Minnesota, 2001)
Navarre v. South Washington County Schools
652 N.W.2d 9 (Supreme Court of Minnesota, 2002)
Bogut v. Jannetta
410 N.W.2d 451 (Court of Appeals of Minnesota, 1987)
Graff v. ROBERT M. SWENDRA AGENCY, INC.
776 N.W.2d 744 (Court of Appeals of Minnesota, 2009)
Kroning v. State Farm Automobile Insurance Co.
567 N.W.2d 42 (Supreme Court of Minnesota, 1997)
Rush v. Jostock
710 N.W.2d 570 (Court of Appeals of Minnesota, 2006)
Pulkrabek v. Johnson
418 N.W.2d 514 (Court of Appeals of Minnesota, 1988)
Bahr v. Boise Cascade Corp.
766 N.W.2d 910 (Supreme Court of Minnesota, 2009)
Jerry's Enterprises, Inc. v. Larkin, Hoffman, Daly & Lindgren, Ltd.
711 N.W.2d 811 (Supreme Court of Minnesota, 2006)
Olson v. Lyrek
582 N.W.2d 582 (Court of Appeals of Minnesota, 1998)
Hampton Bank v. River City Yachts, Inc.
528 N.W.2d 880 (Court of Appeals of Minnesota, 1995)
O'MALLEY v. Ulland Bros.
549 N.W.2d 889 (Supreme Court of Minnesota, 1996)
McCourtie v. United States Steel Corp.
93 N.W.2d 552 (Supreme Court of Minnesota, 1958)
Schleicher v. Lunda Construction Co.
406 N.W.2d 311 (Supreme Court of Minnesota, 1987)
Heine v. Simon
702 N.W.2d 752 (Supreme Court of Minnesota, 2005)
Gleason v. Geary
8 N.W.2d 808 (Supreme Court of Minnesota, 1943)
Moorhead Economic Development Authority v. Anda
789 N.W.2d 860 (Supreme Court of Minnesota, 2010)
Graff v. Robert M. Swendra Agency, Inc.
800 N.W.2d 112 (Supreme Court of Minnesota, 2011)
Daly v. McFarland
812 N.W.2d 113 (Supreme Court of Minnesota, 2012)

Cite This Page — Counsel Stack

Bluebook (online)
James M. Johnson v. Princeton Public Utilities Commission, and third party v. Hydrocon, Inc., Third Party, Counsel Stack Legal Research, https://law.counselstack.com/opinion/james-m-johnson-v-princeton-public-utilities-commission-and-third-party-minnctapp-2016.