James H. Craggs Construction Company v. Hugh G. King

274 F.2d 1, 1960 U.S. App. LEXIS 5516
CourtCourt of Appeals for the Fifth Circuit
DecidedJanuary 26, 1960
Docket17869_1
StatusPublished
Cited by4 cases

This text of 274 F.2d 1 (James H. Craggs Construction Company v. Hugh G. King) is published on Counsel Stack Legal Research, covering Court of Appeals for the Fifth Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
James H. Craggs Construction Company v. Hugh G. King, 274 F.2d 1, 1960 U.S. App. LEXIS 5516 (5th Cir. 1960).

Opinion

CAMERON, Circuit Judge.

The sole question presented by this appeal is whether there was sufficient evidence before the court below to support the verdict of the jury in favor of appellee King awarding damages for the breach by appellant Graggs of a hauling contract. King, plaintiff below, brought this action in a state court of Georgia for expenses and loss of profits resulting from an alleged breach of a subcontract entered into between him and appellant James H. Craggs Construction Company, *2 defendant below, the prime contractor under a government contract covering construction work at Turner Air Force Base, Georgia. Craggs removed the case to the District Court, filed an answer and counter claim against King and his surety, United States Fidelity and Guaranty Company, which Craggs brought in as an additional party. 1 This appeal is from a judgment rendered upon jury verdict in favor of King and against Craggs in the sum of $15,000, which judgment has che effect of denying recovery upon Craggs’ counter claims against King and the United States Fidelity and Guaranty Company. 2

Although the record contains some seven hundred printed pages and the exhibits are numerous and the briefs cover a wide range of arguments, the basic contentions of the parties are relatively simple. King contends that he had a contract, partly written and partly oral, to haul all of the concrete and the base aggregate with which Craggs would construct certain runways and taxi-ways for the government; that the agents of Craggs in charge of the work near Albany, Georgia refused to respect or perform plaintiff’s contract, but on the other hand set about to run him off of the job soon after he began work upon it, also refusing to pay him for the work he had done. Craggs claims that its contract with King was entirely in writing, that many of the provisions King contended for and now seeks to enforce were bottomed upon agreements King claimed to have made with defendant’s agents in charge of the work, who had no authority to amend or add to the contract; and it denied that it ran plaintiff off of the job, claiming, on the other hand, that plaintiff wrongfully quit his work and took his trucks away, causing defendant damages aggregating $27,954.39.

The case was submitted to the jury under the charge of the court below, which is not contained in the record, the jury returned a verdict in plaintiff’s favor, and defendant claims here that there was no evidence upon which the verdict could legally rest and that its motion for directed verdict made at the close of plaintiff’s evidence and repeated after all of the evidence was in, and its motion for judgment notwithstanding the verdict should have been granted.

Craggs, on April 29, 1958, entered into a written contract with the United States of America for the “Construction of Runway and Taxiway, FY-58.” Said government contract was referred to in a number of documents and in the testimony, but it was not offered in evidence.

About May, 1958, Craggs, a Florida corporation, through J. R. Fitzgerald, its vice president, and D. B. Murphree, its field engineer, conducted negotiations with King which culminated in a written contract dated August 21, 1958, the salient features of which are reproduced in the margin. 3 Plaintiff charged that *3 the written contract covered only a portion of the agreement between the parties and that other features were added or the initial ones explained by supplemental oral agreements and by dealings between the parties as the work progressed.

At the extended trial seventeen witnesses testified and more than a dozen exhibits were introduced in evidence, all without objection on either side. Craggs contends simply that there was not sufficient evidence to support a jury finding in favor of King. A careful reading of the record leads us to disagree with this position, and it is necessary to set out at some length the evidence favorable to King which the jury was justified in accepting. In sifting this evidence from the vast amount contained in the record it will be helpful to assemble it as it relates to the grounds King asserts as constituting the basis of his claim of a breach of his contract.

It should be kept in mind that negotiations between Craggs and King began in May, 1958, and that the parties all thought then that the work under discussion would be begun at a fairly early date. June 18th, Craggs submitted to King a writing purporting to set out the agreement between the parties, which brought on much more discussion and some changes in the written contract before it was executed August 21st. One of the main points discussed throughout the whole period of the dealing of the parties was the base rate of pay which King would receive for his hauling.

The written contract provided only that King should haul base aggregates “at a unit price of twenty-two cents ($0.22) per ton,” and “concrete batches (of coarse aggregate, fine aggregate and cement) at a unit price of twenty-five cents ($0.25) per ton.” King contended throughout that this price was based upon and was dependent upon the distance of the respective hauls, and he had David B. Murphree, Jr., engineer in charge of construction for Craggs, write him a letter dated July 4, 1958, 4 and introduced evidence of substantiating conversations, both before the contract was signed and during its abortive execution, between King on the one side, and Fitzgerald, Craggs’ vice president, Lavender, its superintendent in the field, and Murphree, its project engineer on the other.

“This will confirm our conversation regarding the hauling of base material aggregate and concrete material batches on the above captioned project.
“Our agreement was that the base material would be approximately a two mile haul and that the concrete material approximately a two and one half mile haul.
“The approximate tonnage on base material is 140,000 Ton. The approximate tonnage on the concrete aggregate is 110,000 Ton.”

*4 Murphree pointed out to King on the ground where the roads to be constructed by Craggs would run. Craggs did not build the roads along the routes so indicated, but so located them that the closest hauls, according to measurements made between Murphree and King in the latter days of their dealing, was 3.4 miles, and the longest was 4.10 miles. King complained constantly and fervently to Murphree and also to Lavender and Fitzgerald that he could not make any of the hauls over the longer routes at the price mentioned in the contract, and these representatives of Craggs merely temporized with him, telling him that due adjustment would be made to cover the added distances. As the product, in part, of these constant arguments, in which Fitzgerald at one time “raked Murphree over the coals” in a telephone conversation in King’s presence, Murphree developed and demonstrated a dislike for King which dominated his actions in his dealings with King.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

T-Peg v. Timber Works
2005 DNH 017 (D. New Hampshire, 2005)
State v. Dupard
609 P.2d 961 (Washington Supreme Court, 1980)
Massey-Ferguson, Inc. v. Bent Equipment Company
283 F.2d 12 (Fifth Circuit, 1960)
U. S. Industries, Inc. v. Camco, Incorporated
277 F.2d 292 (Fifth Circuit, 1960)

Cite This Page — Counsel Stack

Bluebook (online)
274 F.2d 1, 1960 U.S. App. LEXIS 5516, Counsel Stack Legal Research, https://law.counselstack.com/opinion/james-h-craggs-construction-company-v-hugh-g-king-ca5-1960.