James G. Akers v. Sessions Paving Company

CourtCourt of Appeals of Tennessee
DecidedAugust 13, 2013
DocketM2012-02602-COA-R3-CV
StatusPublished

This text of James G. Akers v. Sessions Paving Company (James G. Akers v. Sessions Paving Company) is published on Counsel Stack Legal Research, covering Court of Appeals of Tennessee primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
James G. Akers v. Sessions Paving Company, (Tenn. Ct. App. 2013).

Opinion

IN THE COURT OF APPEALS OF TENNESSEE AT NASHVILLE July 11, 2013 Session

JAMES G. AKERS v. SESSIONS PAVING COMPANY ET AL.

Appeal from the Chancery Court for Hickman County No. 11-CV-4530 Robbie T. Beal, Chancellor

No. M2012-02602-COA-R3-CV - Filed August 13, 2013

This action arises out of the alleged breach of a construction subcontract due to the general contractor’s failure to pay for work performed by the subcontractor. At issue in this appeal are the plaintiff’s two claims against the general contractor and the insurer that provided the performance and payment bond. One claim is for breach of the subcontract; the other is for violation of the Prompt Pay Act, Tennessee Code Annotated §§ 66-34-101 through -703. The trial court granted the defendants’ motion for summary judgment finding that both claims were time-barred by Tennessee Code Annotated § 28-3-109(a)(3), the six-year statute of limitations for breach of contract. We affirm.

Tenn. R. App. P. 3 Appeal as of Right; Judgment of the Chancery Court Affirmed

F RANK G. C LEMENT, JR., J., delivered the opinion of the Court, in which A NDY D. B ENNETT and R ICHARD H. D INKINS, J.J., joined.

James G. Akers, Brentwood, Tennessee, Pro Se.

David K. Taylor and Max Smith, Nashville, Tennessee, for the appellees, Sessions Paving Company and Great American Insurance Co.

OPINION

In 2004, the Town of Centerville, Tennessee solicited bids for the expansion and improvement of its Municipal Airport. One of the defendants, Sessions Paving Company (“Sessions Paving”), was the successful bidder and was awarded the contract to manage and oversee the construction of the project in early September. The contract was for $523,841.60.

On September 15, 2004, Sessions Paving entered into a subcontract with Akers & Akers of Tennessee, Inc. (“Akers”) pursuant to which Akers would perform specific clearing and excavation activities on the construction site, and the company president, Mr. James G. Akers, would serve as Project Superintendent for Sessions Paving, in consideration for a total fee of $112,153.40.

Akers commenced work on September 21, 2004, and shortly thereafter encountered unexpected problems with the soil which Mr. Akers believed would require substantially more time, resources and costs than the parties had originally agreed upon. As a result, Mr. Akers requested that Sessions Paving amend the contract to provide for additional compensation to Akers. Over the next three months, Akers continued to work on the project while the parties attempted to re-negotiate the subcontract, but the negotiations were unsuccessful. During this period, Sessions Paving remitted progress payments to Akers that were substantially less than what Mr. Akers believed Akers was owed. Akers suspended work on December 13, 2004, when it became apparent that it was not going to be compensated for what it believed to be work in excess of that it contracted to do. Akers never worked on the project after December 13, 2004.

Over the next few months, Mr. Akers continued to ask Sessions for additional compensation for the work Akers performed on the airport project. On March 4, 2005, Akers, Sessions Paving, and the Town of Centerville entered into a settlement agreement, which provided that an independent third party would evaluate and determine a fair price for the work performed by Akers. Mr. Akers signed the agreement on behalf of Akers. One week later, on March 12, 2005, Mr. Akers, acting on behalf of Akers, filed a construction lien on the airport project in the Hickman County Register’s Office, stating Akers was owed $46,627.77.

On August 9, 2011, more than six years after entering into the settlement agreement and filing the construction lien, Mr. Akers notified Sessions Paving that he was the successor-in-interest to the corporation’s (Akers’) rights under the subcontract and the construction lien.1 He also informed Sessions Paving that if it did not pay him $765,058.71 by August 19 ($61,117.70 under the contract, plus statutory penalties and interest accruing since 2005), he would file a complaint for violation of the Tennessee Prompt Pay Act and for breach of contract.

Sessions Paving refused his demands; thus, on August 24, Mr. Akers (hereafter, “Plaintiff”) commenced this action against Sessions Paving and Great American Insurance

1 The defendants do not challenge Mr. Akers’ claim that he is the successor-in-interest to Akers & Akers.

-2- Company (collectively, “Defendants”).2 Defendants filed a joint Answer on November 22. After taking discovery, Defendants filed a joint motion for summary judgment, asserting that Plaintiff’s claims were time-barred. By Order entered October 16, 2012, the trial court granted Defendants’ motion for summary judgment. The court found that the six-year breach of contract statute of limitations applied to all of the claims. The court also found that Plaintiff was “clearly and fully aware that there was a potential claim for breach of contract under its subcontract with Sessions” on March 4, 2005, when Plaintiff entered into the settlement agreement with Sessions Paving and the Town of Centerville, or at the latest March 12, 2005, when Plaintiff filed a construction lien on the airport project with the Hickman County Register of Deeds. Based upon the above undisputed facts, the trial court concluded the August 9, 2011 complaint was untimely and, therefore, dismissed all claims against Defendants.3 Plaintiff filed a timely appeal and Statement of the Evidence.

A NALYSIS

Plaintiff raises two issues on appeal, both of which challenge the trial court’s determination that his claims are time barred by the six-year statute of limitations for breach of contract actions set forth in Tennessee Code Annotated § 28-3-109(a)(3). First, he contends that his Prompt Pay Act claims are not subject to the six-year statute of limitations. Second, he contends that the trial court erred in finding that his claims accrued more than six years prior to the commencement of this action.

I. Summary Judgment

This appeal arises from the grant of summary judgment, which is appropriate when a party establishes that there is no genuine issue as to any material fact and that a judgment may be rendered as a matter of law. Tenn. R. Civ. P. 56.04; Stovall v. Clarke, 113 S.W.3d 715, 721 (Tenn. 2003). It is appropriate in virtually all civil cases that can be resolved on the basis of legal issues alone. Byrd v. Hall, 847 S.W.2d 208, 210 (Tenn. 1993); Pendleton v. Mills, 73 S.W.3d 115, 121 (Tenn. Ct. App. 2001). Whether a claim should be dismissed based on the statute of limitations is a question of law, which we review de novo with no presumption of correctness. Redwing v. Catholic Bishop Diocese of Memphis, 363 S.W.3d 436, 456 (Tenn. 2012) (citing Fahrner v. SW Mfg., Inc., 48 S.W.3d 141, 144 (Tenn. 2001)).

2 Plaintiff also asserted claims against two other defendants, the Town of Centerville, and Meriweather Lewis Electric Company. The claims against those defendants are not at issue in this appeal. 3 Pursuant to Tennessee Rule of Civil Procedure 54.02, the trial court also found “there is no just reason for delay,” and directed that the Order be entered as a final judgment, notwithstanding Plaintiff's claims against the Town of Centerville and Meriweather Lewis Electric Company.

-3- II. The Prompt Pay Act

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Norman Redwing v. Catholic Bishop for the Diocese of Memphis
363 S.W.3d 436 (Tennessee Supreme Court, 2012)
Stovall v. Clarke
113 S.W.3d 715 (Tennessee Supreme Court, 2003)
Fahrner v. SW Manufacturing, Inc.
48 S.W.3d 141 (Tennessee Supreme Court, 2001)
Keller v. Colgems-EMI Music, Inc.
924 S.W.2d 357 (Court of Appeals of Tennessee, 1996)
Bland v. Smith
277 S.W.2d 377 (Tennessee Supreme Court, 1955)
Johnson v. Craycraft
914 S.W.2d 506 (Court of Appeals of Tennessee, 1995)
Pendleton v. Mills
73 S.W.3d 115 (Court of Appeals of Tennessee, 2001)
Foust v. Carney
329 S.W.2d 826 (Tennessee Supreme Court, 1959)
Wilkins v. Third National Bank in Nashville
884 S.W.2d 758 (Court of Appeals of Tennessee, 1994)
Byrd v. Hall
847 S.W.2d 208 (Tennessee Supreme Court, 1993)
Vance v. Schulder
547 S.W.2d 927 (Tennessee Supreme Court, 1977)
Greene v. THGC, Inc.
915 S.W.2d 809 (Court of Appeals of Tennessee, 1995)

Cite This Page — Counsel Stack

Bluebook (online)
James G. Akers v. Sessions Paving Company, Counsel Stack Legal Research, https://law.counselstack.com/opinion/james-g-akers-v-sessions-paving-company-tennctapp-2013.