James E. Koch v. J&J Ranch, LLC, a Wyoming Limited Liability Company

2013 WY 51, 299 P.3d 689, 2013 WL 1800241, 2013 Wyo. LEXIS 54
CourtWyoming Supreme Court
DecidedApril 30, 2013
DocketS-12-0179
StatusPublished
Cited by5 cases

This text of 2013 WY 51 (James E. Koch v. J&J Ranch, LLC, a Wyoming Limited Liability Company) is published on Counsel Stack Legal Research, covering Wyoming Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
James E. Koch v. J&J Ranch, LLC, a Wyoming Limited Liability Company, 2013 WY 51, 299 P.3d 689, 2013 WL 1800241, 2013 Wyo. LEXIS 54 (Wyo. 2013).

Opinion

DAVIS, Justice.

[T1] The parties are two rural landowners who own easements crossing a parcel of ranchland in Laramie County, Wyoming. When Appellant James Koch improved the common roadway and asked his neighbor to contribute to the cost of those improvements, Appellee J & J Ranch, LLC brought suit against Koch in the District Court for the First Judicial District. J & J sought a declaratory judgment as to the parties' respective rights and duties relating to maintenance and repair of the road, as well as injunctive relief and damages for Koch's alleged interference with J & J's use of the easement.

[12] Koch responded with similar counterclaims, but also claimed the right to equitable contribution from J & J for the costs he incurred in improving the road. We will affirm the district court's denial of Koch's request for equitable contribution, but reverse its declaration of the parties' rights regarding any future maintenance work and as to the rights of the parties to recover for repair and maintenance they perform. 1

ISSUES

[T3] We restate the questions raised by this appeal as follows:

1. Was the district court's denial of Koch's equitable contribution claim consistent with the principles set out in Rageth v. Sidon Irrigation District, 2011 WY 121, 258 P.3d 712 (Wyo.2011), and otherwise not clearly erroneous or an abuse of dis-eretion?
2. Did the court err as a matter of law when it declared that:
a. Appellant had no right to repair or maintain the easement?
b. Appellant had no right to recover a portion of the costs of repair or maintenance from Appellee?
c. Appellant's use of the easement could not exceed the boundaries of his grant?

FACTS

[14] Dean Fogg was the original owner of the servient estate involved in this case. In July of 1979, Fogg granted a road easement to Jerry Palen, who sold his property (including the appurtenant easement) to Morris and Judy Perkins in 1991. Appellant Koch purchased that property in March 2006. After Fogg died in 2004, the servient property passed through a trust he had created to his daughter, Janet Shatto. J & J purchased an easement over the roadway used by Palen *692 and his successors from Shatto in October of 2007.

[15] Koch's road easement describes its width as "a minimum of thirty (80) feet," and it contains no provisions regarding maintenance of the road. J & J's casement limits the width of its road to thirty feet, but it also provides that J & J "agrees to maintain the road easement."

[T6] The road used by Koch and J & J begins at Campstool Road east of Cheyenne, and then proceeds south for approximately one mile. The road then reaches a Y, from which Koch has to travel a short distance to the southwest to reach his property. To reach the J & J property from that point one has to drive another mile, first bearing to the southeast, then directly to the east, and then due south. Approximately two-thirds of this second mile lie on a separate easement granted to J & J by Arp & Hammond Hardware Company in May of 2008.

[17] For most of its history, the common portion of Koch's and J & J's easements "was just a two-rutted road through the pasture" that received little or no maintenance. Although Mr. Perkins occasionally dumped some gravel in the deepest ruts and mud puddles on the road while he owned the property, and although others occasionally dragged old tires down the road in an effort to smooth it, the more common practice was to simply drive around those obstructions, thereby widening the road. The topography of the land through which the road runs allowed snow to drift on it, at times preventing its use for up to a week.

[18] By the time Koch acquired his property in 2006, years of use and the cumulative effect of weather had lowered the roadbed nearly three feet below the adjacent pastureland. As a result, snowmelt and rain filled the road, washed downhill, and created large waterholes and puddles in most low-lying areas. In the one-mile course of the easement there were approximately twenty such holes which, when full, were three feet deep and impassable by ordinary passenger vehicles. When Koch moved onto his newly-acquired property in 2006, he could not pull his horse trailer down the road with his dual-wheel, four-wheel-drive Dodge pickup truck and had to wait nearly three weeks for the road to dry out.

[19] Koch is an excavating contractor, and he therefore owns heavy equipment suitable for road maintenance. After Koch moved in, he obtained permission from Dean Fogg's son Dennis to fill the mudholes and level the road with a front-end loader in 2006 and 2007.

[110] Some time in 2006, Koch met James Johnson, J & J's owner and manager. The two talked about the poor condition of the road, and Johnson proposed that they work together to fix it. He asked Koch about gravelling it. Koch believed gravelling would be too expensive, and the two orally agreed that Koch would instead use his loader to cut a small ditch along the road in the areas which filled with water, and that he would push the soil excavated from the ditches to the center of the road, thus elevating it. They hoped those measures would drain water in problem areas and allow the road to dry more quickly. Koch performed the agreed work in 2006 and 2007, and he also periodically smoothed the road and plowed snow from it. Johnson paid Koch for a portion of the cost of the work, which came to approximately $800 in each year.

[111] In 2008, Koch decided to improve the road by transforming the small ditches he had made into true borrow ditches and by using the soil he would remove when he deepened and widened the ditches to increase the height of the road, which would in turn hopefully provide still better drainage and reduce snow drifts. In March of that year he billed Johnson $700 for what he claimed was Johnson's share of the cost of the ditching and elevation work he had done that January and February. When Koch informed Johnson that $350 per month was going to be his share of the costs "from here on out," Johnson refused to pay the bill. After that, the two had no further discussions about snow removal, road maintenance, or improvement of the road. Koch never again billed Johnson for any work except for $200 for road grading in June of 2008, which Johnson paid.

*693 [412] Unfortunately, the work Koch did in 2008 did not result in improvement to the road. The material he removed from the ditches was mainly sand, which did not compact well when placed on the road. Consequently, it absorbed and held water rather than allowing it to drain as Koch originally intended. The relatively soft and unstable sand surface also made the road more difficult for cars to travel, because it developed deep ruts in which they could become stuck.

[113] Koch improved the road dramatically in 2009. He obtained permission from the owner of the servient estate to dig into adjacent hills for rock, which he then placed on top of the sand roadway, which made it much more stable and also increased drainage.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
2013 WY 51, 299 P.3d 689, 2013 WL 1800241, 2013 Wyo. LEXIS 54, Counsel Stack Legal Research, https://law.counselstack.com/opinion/james-e-koch-v-jj-ranch-llc-a-wyoming-limited-liability-company-wyo-2013.