James Const. v. State Ex Rel. Dotd

977 So. 2d 989
CourtLouisiana Court of Appeal
DecidedNovember 2, 2007
Docket2007 CA 0225
StatusPublished

This text of 977 So. 2d 989 (James Const. v. State Ex Rel. Dotd) is published on Counsel Stack Legal Research, covering Louisiana Court of Appeal primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
James Const. v. State Ex Rel. Dotd, 977 So. 2d 989 (La. Ct. App. 2007).

Opinion

977 So.2d 989 (2007)

JAMES CONSTRUCTION GROUP, L.L.C. F/K/A Angelo Iafrate Construction, L.L.C.
v.
STATE of Louisiana, Through the DEPARTMENT OF TRANSPORTATION AND DEVELOPMENT.

No. 2007 CA 0225.

Court of Appeal of Louisiana, First Circuit.

November 2, 2007.

*991 Eric A. Kracht, George P. Vourvoulias, Baton Rouge, LA, for Plaintiff/Appellant, James Construction Group, L.L.C. F/K/A Infrate Construction, L.L.C.

Timothy Strohschein, Baton Rouge, LA, for Defendant/Appellee, State of Louisiana, through the Department of Transportation and Development.

Before WHIPPLE, GUIDRY, and HUGHES, JJ.

GUIDRY, J.

In this suit to recover $420,000 withheld as stipulated damages for untimely completion of a highway construction project, plaintiff appeals a partial summary judgment granted in favor of the defendant. For the following reasons, we affirm.

FACTS AND PROCEDURAL HISTORY

The State of Louisiana, through the Department of Transportation and Development (DOTD), awarded a construction contract to JCG Construction Group, L.L.C. (JCG) for a road project involving Interstate 10 (1-10) and known as the Louisiana Avenue Interchange. The contract provided the project was to be completed within four hundred and forty days for a price of $18,900,905.75. As a result of multiple plan changes amending the contract, forty days were added to the original completion date of the contract. According to DOTD's calculations, the deadline for completion of the contract was June 22, 2003. However, the work within the scope of the original contract was not accepted as complete until August 3, 2003. Therefore, DOTD assessed stipulated damages against JCG for a total of forty-two days, at the contractually provided rate of $10,000 per day, and withheld payment of that amount from the contract price earned by JCG. DOTD accepted all work, including work added by plan changes, as being complete on August 28, 2003.

After DOTD refused JCG's demands, JCG filed the instant suit to recover $420,000 as the amount withheld for stipulated damages. JCG alleged DOTD was not entitled to any stipulated damages because the actual deadline for completion of *992 the project was August 31, 2003. This contention was based on the claims that: (1) DOTD agreed in Plan Change 22 to grant JCG fifty-six additional days for completion of the contract; and (2) JCG was entitled to twelve additional days because of a delay that was attributable to DOTD in relocating a fiber-optic cable. In addition to recovery of the sum withheld as stipulated damages, JCG also requested an award of $206,706.51 as damages for additional costs and lost revenues it allegedly suffered as a result of the excessive number of change orders made by DOTD during the construction project.

DOTD filed an answer and reconventional demand seeking to recover $55,779.43, which it alleged JCG was overpaid under the contract as a result of the stipulated damages it incurred. Subsequently, DOTD filed a motion for partial summary judgment holding that: (1) it had properly implemented Plan Change 22; (2) JCG was not entitled to a fifty-six-day extension of the completion date under Plan Change 22; (3) JCG was not entitled to a twelve-day extension of the completion date for additional work related to the relocation of a fiber-optic cable; (4) DOTD properly assessed stipulated damages against JCG; and (5) JCG was liable to DOTD for an overpayment of $55,779.43. Following a hearing, the district court granted a partial summary judgment in favor of DOTD and against JCG for $55,779.43. After making an express determination that there was no just cause for delay, the district court designated the judgment as a final judgment pursuant to La. C.C.P. art. 1915 B. JCG has now appealed, designating five assignments of error.

ASSIGNMENTS OF ERROR

1. The district court erred in its conclusion that DOTD properly implemented Plan Change No. 22 in view of uncontroverted evidence that DOTD breached its written promise to extend the contract time fifty-six days.
2. The district court misconstrued the contract, as well as the substantive law regarding prevention of performance and concurrent delays, and disregarded evidence that DOTD caused and/or otherwise contributed to the delays for which it assessed stipulated damages against JCG.
3. The district court erred in its conclusions that JCG was not entitled to time extensions beyond June 22, 2003, for Plan Changes 22 and 29, as well as for the delays caused by the fiber-optic cable relocation.
4. The district court erred in failing to make the required inquiry as to the reasonableness of the stipulated damages and whether they approximated DOTD's actual damages, disregarding the undisputed evidence that the stipulated damages bore no relationship to DOTD's actual damages.
5. The district court improperly admitted into evidence and relied upon affidavits from DOTD representatives that were not served upon opposing counsel more than fifteen days before the motion hearing, as required by La. C.C.P. art. 966 B.

STANDARD OF REVIEW

On appeal, summary judgments are reviewed de novo under the same criteria that govern the district court's consideration of whether summary judgment is appropriate. An appellate court thus asks the same questions as does the trial court in determining whether summary judgment is appropriate: whether there is any genuine issue of material fact, and whether *993 the mover is entitled to judgment as a matter of law. La. C.C.P. art. 966 B; Love v. AAA Temporaries, Inc., XXXX-XXXX, p. 3 (La.App. 1st Cir.5/4/07), 961 So.2d 480, 483.

A motion for summary judgment is a procedural device used to avoid a full-scale trial when there is no genuine factual dispute. The motion should be granted only if the pleadings, depositions, answers to interrogatories, and admissions on file, together with any affidavits, show that there is no genuine issue as to material fact and that the mover is entitled to judgment as a matter of law. The summary judgment procedure is favored and is designed to secure the just, speedy, and inexpensive determination of every action. La. C.C.P. art. 966 A(2); Love, XXXX-XXXX at p. 4, 961 So.2d at 483.

The burden of proof is on the movant. However, if the movant will not bear the burden of proof at trial on the matter that is before the court on the motion for summary judgment, the movant's burden on the motion does not require him to negate all essential elements of the adverse party's claim, action, or defense, but rather to point out to the court that there is an absence of factual support for one or more elements essential to the adverse party's Claim, action, or defense. Thereafter, if the adverse party fails to provide factual evidence sufficient to establish that he will be able to satisfy his evidentiary burden of proof at trial, there is no genuine issue of material fact. La. C.C.P. art. 966 C(2); Love, XXXX-XXXX at p. 4, 961 So.2d at 483.

ASSIGNMENT OF ERROR NUMBER ONE

In its first assignment of error, JCG asserts the district court committed clear error in construing Plan Change 22 as not requiring a fifty-six day extension for completion of the contract. It argues that, at the very least, the court should have found that a genuine issue of material fact precluded summary judgment on the issue of DOTD's implementation of Plan Change 22.

The interpretation of a contract is the determination of the common intent of the parties. La. C.C. art.2045.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Lombardo v. Deshotel
647 So. 2d 1086 (Supreme Court of Louisiana, 1994)
MOBILE EXPLORATION v. Certain Underwriters
837 So. 2d 11 (Louisiana Court of Appeal, 2002)
Utley-James of La., Inc. v. State, Div. of Admin.
671 So. 2d 473 (Louisiana Court of Appeal, 1995)
White v. Gulf States Utilities
465 So. 2d 287 (Louisiana Court of Appeal, 1985)
La. Smoked Products v. Savoie's Sausage
696 So. 2d 1373 (Supreme Court of Louisiana, 1997)
Kops v. Lee
871 So. 2d 1187 (Louisiana Court of Appeal, 2004)
Buggage v. Volks Constructors
928 So. 2d 536 (Supreme Court of Louisiana, 2006)
Savoie v. Savoie
864 So. 2d 742 (Louisiana Court of Appeal, 2003)
Jones v. State
956 So. 2d 103 (Louisiana Court of Appeal, 2007)
Love v. AAA Temporaries, Inc.
961 So. 2d 480 (Louisiana Court of Appeal, 2007)

Cite This Page — Counsel Stack

Bluebook (online)
977 So. 2d 989, Counsel Stack Legal Research, https://law.counselstack.com/opinion/james-const-v-state-ex-rel-dotd-lactapp-2007.