James City County v. United States Environmental Protection Agency

758 F. Supp. 348
District Court, E.D. Virginia·Decided November 8, 1990·No. Civ. A. 89-156-NN·Published·Cited by 4 cases

Opinion

MEMORANDUM OPINION AND ORDER

MacKENZIE, District Judge.

Plaintiff James City County (“County”) brought suit against defendants, United States Environmental Protection Agency (“EPA”) and United States Army Corps of Engineers (“Corps”) after the EPA, acting under Section 404(c) of the Federal Water Pollution Control Act of 1972, vetoed the Corps’ decision to permit the placement of dirt fill to construct a dam for the proposed Ware Creek Reservoir. Both plaintiff and defendants moved for summary judgment. Thereafter, the entire administrative record was submitted to this Court. The Southern Environmental Law Center, the National Wildlife Federation, the Virginia Wildlife Federation and the Chesapeake Bay Foundation participated in this action as amici curiae.

I.

James City County, adjacent to Williams-burg, Virginia, located on the York-James Peninsula, is the second fastest-growing county in Virginia. Currently, it receives its supply of water from two separate water systems. The James City County System provides the County with 1.9 million gallons of water per day, predominantly derived from groundwater. The City of Newport News System supplies the County with 5.4 million gallons of water per day. At its peak, the Newport News System could supply James City County with 7.7 million gallons of water per day.

Beginning in 1979, consultants alerted James City County that severe water shortages were inevitable if the County did not take action to meet its growing water supply needs. Numerous water studies were conducted, and, as a result, a figure of 18.2 million gallons per day was determined to be necessary to fulfill the County’s water needs through the year 2030. Thus, James City County found itself faced with the unenviable task of finding a reliable, practical way to meet a 10.5 million gallon per day water deficit.

Further water studies ensued — at least sixteen water supply studies were conducted by federal, state and private authorities over a ten year period. Based on the aforementioned studies, James City County and the Corps concluded that constructing a reservoir on Ware Creek was the only practical long term solution. The proposed reservoir would be situated along the border of James City and New Kent Counties, approximately one thousand feet downstream from the confluence of Ware Creek and France Swamp. Capacity of the reservoir would be over six thousand million gallons at a normal pool elevation of thirty-five feet. Most importantly, the project would provide a safe yield of 9.4 million gallons of water per day.

Between 1982 and 1984, James City County laid the groundwork for obtaining a permit to place fill for the Ware Creek Reservoir. Under the Federal Water Pollu *350 tion Control Act of 1972, such a permit is required from the Corps before any fill material is discharged into navigable waters. 1 In preparation for its permit, the County purchased land in the area to forestall residual development and created a Reservoir Protection Overlay District to restrict incompatible land uses in the watershed. In addition, James City County obtained the consent of neighboring New Kent County to use a portion of New Kent County’s property for the reservoir.

In 1984, the groundwork set, James City County formally filed an application with the Corps for a fill permit. Pursuant to the National Environmental Policy Act, the Corps directed an extensive review of the Ware Creek Reservoir project. 2 The Corps then solicited EPA’s assistance as a “cooperating agency” in preparing a Final Environmental Impact Statement for the project. In the meantime, James City County hired numerous experts at considerable county expense to ensure that any issues raised by EPA could be addressed.

The Corps published its Final Environmental Impact Statement in October of 1987. The Corps’ statement had taken an additional two years on account of EPA’s exhortations that further investigations be done. EPA’s contribution to the statement, nonetheless, was a scant two and a half pages of commentary, the crux of which was EPA’s contention that the Commonwealth of Virginia was not doing enough to encourage regional as opposed to local water supply development. 3

Representatives from James City County, sensing a growing rift between the Corps and EPA over the project, approached the EPA with several mitigation plans. The County representatives hoped that a suitable plan would perhaps lead to a compromise upon which both EPA and the Corps could agree. EPA’s response to James City County’s overtures was that the proposed placement of fill was simply “unmitigatable”. 4

On July 11, 1988 the Corps announced its decision that James City County should be granted a permit to place fill in Ware Creek. In its Record of Decision, the Corps found that no agency, including EPA, had identified any practicable, environmentally preferable alternatives for meeting James City County’s desperate need for water. 5 Moreover, the Corps found that James City County had taken all the appropriate steps to minimize any adverse effects of the project. 6

Notwithstanding the Corps favorable findings, James City County, with the assistance of such agencies as the Fish and Wildlife Service, continued to work on a new, more extensive mitigation plan. In August of 1988, the County formally submitted a plan which included a 1.15 million dollar fund to preserve thousands of acres of top priority wetlands. James City County asked the Corps to integrate this plan into any final permit.

Nevertheless, after ten years of supposed cooperation, dozens of experts, countless water studies and a bevy of mitigation proposals, the EPA, on November 18, 1988, vetoed the Corps’ overwhelming ratification of the proposed placement of fill. As a result, the Corps was estopped from granting James City County the permit to which the Corps held the County was entitled.

II.

A. EPA Incorrectly Presumed That James City County Had Alternatives Available To The Ware Creek Reservoir.

Under Section 404(a) of the Clean Water Act (the “Act”), 33 U.S.C. § 1344 (1982), the Secretary of the Army, acting through the Corps, is authorized to issue permits for the discharge of dredged or fill *351 material into navigable waters at specified disposal sites. In determining whether to issue permits, the Corps is directed in Section 404(b) of the Act to apply the guidelines developed by the EPA. 33 U.S.C. § 1344(b) (Supp. III, 1985). These guidelines appear as 40 C.F.R. Part 230 (1987).

Free access — add to your briefcase to read the full text and ask questions with AI

James City County v. United States Environmental Protection Agency, 758 F. Supp. 348 (E.D. Va. 1990).

758 F. Supp. 348 (James City County v. United States Environmental Protection Agency) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related