James Cape & Sons Co. v. Bowles (In Re Bowles)

318 B.R. 129, 2004 Bankr. LEXIS 1999, 2004 WL 2979811
CourtUnited States Bankruptcy Court, E.D. Wisconsin
DecidedDecember 16, 2004
Docket18-31834
StatusPublished
Cited by10 cases

This text of 318 B.R. 129 (James Cape & Sons Co. v. Bowles (In Re Bowles)) is published on Counsel Stack Legal Research, covering United States Bankruptcy Court, E.D. Wisconsin primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
James Cape & Sons Co. v. Bowles (In Re Bowles), 318 B.R. 129, 2004 Bankr. LEXIS 1999, 2004 WL 2979811 (Wis. 2004).

Opinion

*133 MEMORANDUM DECISION

SUSAN y. KELLEY, Bankruptcy Judge.

James Cape & Sons Company (“Cape”), initiated this adversary proceeding against Joseph M. Bowles (the “Debtor”) contending that an arbitration award Cape received after a botched construction project is not dischargeable in the Debtor’s bankruptcy. The court has jurisdiction under 28 U.S.C. § 1334(b); this is a core proceeding as defined by 28 U.S.C. § 157(b)(2)(I); and venue is proper under 28 U.S.C. §§ 1408, 1409. This Memorandum Decision constitutes findings of fact and conclusions of law pursuant to Fed. R. Bankr.Proc. 7052.

FACTS

The background and many of the facts are not disputed. The parties have agreed that on July 22, 1999, the United States Army Corps of Engineers awarded an over $15 Million contract (the “Contract”) to Bowles Construction Services, Inc. (“Bowles Construction”), a Wisconsin corporation. The Debtor was the president and sole shareholder of Bowles Construction at the time the Contract was awarded, although he later resigned and sold his stock. The Contract involved the construction of a steel revetment barrier along Lake Michigan in Chicago, Illinois, part of a project known as the Chicago Shoreline Storm Damage Reduction Project (the “Project”). Neither party introduced the entire Contract into evidence, although various excerpts from the Contract are part of the record.

Bowles Construction qualified to act as the prime contractor under the Small Business Administration small business set aside program, but Bowles Construction had neither the resources nor the experience to perform the Contract on its own. Accordingly, as it had done in the past, Bowles Construction entered into a subcontract with Cape; Cape has over 1,000 employees and a history of successful large construction projects. Cape is also a Wisconsin corporation. Under their Subcontract dated August 25, 1999 (the “Subcontract”), Cape would perform approximately 80% of the work on the Project. The Subcontract does not contain a choice of law provision.

One of the most important documents in this transaction is also one of the least straightforward. Bowles Construction and the Debtor individually are parties to a $200,000 Supplemental Loan Agreement dated as of September 20, 1999 (the “Loan Agreement”), with Johnson Bank (the “Bank”). The copy of the Loan Agreement submitted into evidence at the trial did not contain the Bank’s signature, 1 although the Debtor did not vigorously dispute that he and Bowles Construction were parties to the Loan Agreement, under a format which Bowles Construction and Cape had used on other projects. Cape’s status vis-a-vis the Loan Agreement is curious: While the Loan Agreement is signed by Cape, and states in recitals that Cape’s guaranty of the loan and certain bonds is a pre-condition of the loan, Cape is not named as a party to the Loan Agreement in the preamble, Cape did not actually guaranty any obligations in the Loan Agreement itself (or make any agreements, for that matter), and Cape did not produce any written guaranty by Cape of the Loan Agreement or the bonds. 2

*134 The provisions of the Loan Agreement that are relevant to this dispute are similarly perplexing, especially those concerning the escrow account required to protect the collateral for the loan. Under Paragraph 1 of the Loan Agreement, Bowles Construction assigned payments received under the Contract to the Bank as security for the $200,000 loan. Bowles Construction then granted Cape a subordinate assignment of the Contract payments to secure all amounts guaranteed by Cape and all obligations incurred by Cape on behalf of Bowles Construction. As stated above, there is no written evidence of any amounts guaranteed or incurred by Cape on behalf of Bowles Construction. Notably, Bowles did not grant a security interest to Cape to secure Bowles Construction’s obligations to Cape under the Subcontract.

To facilitate the assignment, Paragraph 2 of the Loan Agreement calls for a lock box arrangement and escrow account “into which [Bowles Construction] and the Bank shall direct the payments or proceeds of payments received by the Bank pursuant to the Assignment of the [Contract].” Bowles Construction agreed to take all necessary or desirable steps required by the Bank to complete and perfect the assignment. The Debtor testified that he submitted a form to the Corps of Engineers to cause the electronic transfer payments under the Contract into the lock box account (the “Lock Box”) at the Bank, but the Corps did not comply with his instructions. 3 With one or two exceptions, the payments from the Corps were made by check to Bowles Construction and received by mail at the Chicago office of Bowles Construction. 4 No evidence was introduced that the Bank requested or required any other action with respect to the assignment of the Contract payments, although Cape made various demands (as evidenced by correspondence in August and October 2000) that Bowles Construction direct the Corps to make all future progress payments on the Project directly into the Lock Box at the Bank.

The Loan Agreement contemplated that the parties would agree to escrow instructions for the required “Escrow Account” consistent with the provisions of the Supplemental Loan Agreements for previous projects between Bowles Construction and Cape (none of which were introduced into evidence) and “executed in connection with the first extension of credit under the Credit Facility” (i.e. the $200,000 loan for the Project). Cape introduced the “Supplemental Escrow Instructions” for the Project as an exhibit. Presumably the Supplemental Escrow Instructions for the other projects are more illuminating than the Supplemental Escrow Instructions for this Project, because under the instant instructions, Bowles Construction directed the Escrow Agent to receive, and the Agent agreed to accept, funds from the Bank into the Escrow Account, “and to disburse amounts from the Escrow Account, from time to time as Bowles shall *135 determine to be necessary or appropriate, and all in accordance with the terms, provisions, conditions and instructions contained in the Escrow Instructions (Lafarge Dam Deauthorization), the Escrow Instructions (Sacramento Crushing Project), the Escrow Instructions (Handicap Entryway Project), the Escrow Instructions (Portage Project) and in the Escrow Instructions (Porch Wing Project).” In effect, the Loan Agreement requires Bowles Construction and the Bank to direct payments received by the Bank from the Project into the Escrow Account, then allows Bowles Construction to disburse those funds pursuant to the Supplemental Escrow Instructions. However, no specific instructions or provisions for the release of the funds for the Chicago Shoreline Project from the Escrow Account are contained in either the Loan Agreement or Supplemental Escrow Instructions for the Chicago Shoreline Project.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

State v. Paula L. Schwerdtfeger
Court of Appeals of Wisconsin, 2020
Ocean Innovations, Inc. v. Ahern (In re Ahern)
541 B.R. 438 (W.D. Wisconsin, 2015)
Vieth v. Williams (In re Williams)
478 B.R. 362 (E.D. Wisconsin, 2012)
Levine v. Ward (In Re Ward)
425 B.R. 507 (E.D. Wisconsin, 2010)
Ganther Construction, Inc. v. Ward (In Re Ward)
417 B.R. 582 (E.D. Wisconsin, 2009)
Fischer Construction, LLC v. Ecker (In Re Ecker)
400 B.R. 669 (E.D. Wisconsin, 2009)
Merritt v. Rizzo (In Re Rizzo)
337 B.R. 180 (N.D. Illinois, 2006)
Randle v. Highfill (In Re Highfill)
336 B.R. 701 (M.D. North Carolina, 2006)

Cite This Page — Counsel Stack

Bluebook (online)
318 B.R. 129, 2004 Bankr. LEXIS 1999, 2004 WL 2979811, Counsel Stack Legal Research, https://law.counselstack.com/opinion/james-cape-sons-co-v-bowles-in-re-bowles-wieb-2004.