James B. Lambie Co. v. Bigelow

34 App. D.C. 49, 1909 U.S. App. LEXIS 5996
CourtCourt of Appeals for the D.C. Circuit
DecidedNovember 15, 1909
DocketNo. 1993
StatusPublished
Cited by3 cases

This text of 34 App. D.C. 49 (James B. Lambie Co. v. Bigelow) is published on Counsel Stack Legal Research, covering Court of Appeals for the D.C. Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
James B. Lambie Co. v. Bigelow, 34 App. D.C. 49, 1909 U.S. App. LEXIS 5996 (D.C. Cir. 1909).

Opinion

Mr. Justice Robb

delivered the opinion of the Court:

In the first assignment of error appellants object to the consideration by the trial court of the testimony “of Stephen A. Galloway and of Albert S. Bigelow, because their testimony was given ex parte without notice,—save to counsel for C. A. Schneider’s Sons, who was unavoidably absent,—and without opportunity to cross-examine, and further because it was irregularly and improperly taken under the guise of surrebuttal testimony, when in reality it was nothing short of a continuation of appellees’ direct defense evidence.”

The record shows that due notice was given to counsel then representing appellants, who in a letter to the examiner asked that his right to cross-examine be reserved. It does not appear that he subsequently asserted such right, or that he brought the matter to the attention of the trial court in any way. Having then offered no objection to the consideration of this testimony, it is too late for him to raise the question here. He should have raised the question below by motion to suppress.

The second and remaining assignment of error challenges the action of the court in refusing relief and dismissing the bill. This assignment brings into review the provisions of the Code respecting mechanics’ liens, and particularly the provisions entitling subcontractors, materialmen and laborers, upon performance of certain conditions, to such liens.

Sec. 1237 of the Code [31 Stat. at L. 1384, chap. 854] specifies that a contractor shall be entitled to a mechanics’ lien upon the building and lot of ground upon which the same is erected for the reasonable value of the work, and materials furnished by him for and about the erection, improvement, repair, or addition to such building, etc., “provided that the person claiming the lien shall file the notice” herein prescribed. Tn the following section it is provided that any such contractor “wishing to avail himself of the provision aforesaid, whether his claim be due or not, shall file in the office of the clerk of [54]*54the supreme court of the’District, during the construction or within three months after the completion of such building * * * a notice of his intention to hold a lien on the property hereby declared liable to such lien for the amount due or to become due to him,” etc.

Sec. 1239 provides that “any person directly employed by the original contractor, whether as subcontractor, materialman, or laborer, to furnish work or materials for the completion of the work contracted for as aforesaid, shall be entitled to a similar lien to that of 'the original contractor upon his filing a similar notice * * * subject, however, to the conditions set forth in the following sections:”

Sec. 1240 ordains that all liens in favor of parties employed by the contractor shall he subject to the terms and conditions of the original contract, except, such as shall relate to the waiver-of liens, and that if “said original contractor, hy reason .of any breach of the contract on his part, shall be entitled to recover less than the amount agreed upon in his contract, the liens of said parties so employed by him shall be enforceable only for said reduced amount, and if said original contractor shall be entitled to recover nothing said liens shall -not be enforceable at all.”

Sec. -1241 imposes upon the subcontractors, and other persons employed by the contractor, as aforesaid, the additional duty of serving notice upon the owner of the property upon which the lien is claimed, and provides that a failure to serve the additional notice will entitle the owner to make payments according to the terms-of his .contract.

Sec. 1242 imposes upon the owner the duty, “after notice shall he filed hy said party employed under the original contractor, and a copy thereof served upon the owner or his agent, as aforesaid,” of retaining, out of any subsequent payments be-, coming due to the contractor, a sufficient amount to satisfy any indebtedness due from said contractor to the said subcontractor.

Sec. 1243 entitles the subcontractor to know the terms of the contract between the owner and the contractor.

[55]*55Sec. 1244 is as follows: “Advance Payments. If the owner, for the purpose of avoiding the provisions hereof, and defeating the lien of the subcontractor, or other person employed by the contractor, as aforesaid, shall make payments to the contractor in advance of the time agreed upon therefor in the contract, and the amount still due or to become due to the contractor shall be insufficient to satisfy the liens of the subcontractors, or others so employed by the contractor, the property shall remain subject to said liens in the same manner as if such payments had not been made.”

A mechanics’ lien has no existence outside the statute creating it. It was not recognized at common law, nor was it allowed in equity. It is founded upon the just and natural consideration that a party who has enhanced the value of property by contributing thereto labor and materials shall be entitled to a preferred claim on such property, to the extent of his contribution. While the statute creating such a lien is to be reasonably construed so as to effectuate, if possible, the legislative intent, we are not at liberty to excuse those who would claim its protection from the performance of precedent conditions. As was said by Mr. Justice Field in Davis v. Alvord, 94 U. S. 549, 24 L. ed. 285: “Whilst the statute giving liens to mechanics and laborers for their work and labor is to be liberally construed, so as to afford the security intended, it cannot be too strongly impressed upon them, that they must not only bring themselves by their notices, as was done in this case, clearly within- the provisions of the statute, but they must be prepared, if the priority of their lien be disputed, to- show a compliance with those provisions, and to fix with certainty the commencement and completion of their work.”

The provisions of the Code above set forth , are free from ambiguity. The conditions imposed are just and reasonable. The contractor is required only to file his notice with the clerk of the supreme court of the District. The reason why he is not required to give notice to the owner is obvious. Being a party to the contract the owner is presumed to be familiar with its terms, and the claims of the contractor thereunder. Sub[56]*56contractors, in these days of industrial development, are so numerous that to charge the owner with notice of each would impose an unreasonable burden upon him. The law therefore declares that in addition to filing the notice required of contractors the subcontractor shall notify the owner of his intention to hold a lien, and the nature and extent of the claim. Prior to the filing of such notice the subcontractor has only an inchoate right,—an unperfected lien. Until such notice is filed the owner has absolute authority to make payments to his contractor according to the terms of his contract. A fair inference to be deduced from the statute is that the owner, upon the failure of the subcontractor to file the required notice, may make advance payments, providing that such payments are made in good faith and not for the purpose of defeating the lien of the subcontractor. In this case the owner, when he made the advance payments, had no notice that the subcontractors intend7 ed to claim liens, and there is absolutely nothing in the. record showing bad faith on his part.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

McNair Builders, Inc. v. 1629 16th Street, L.L.C.
968 A.2d 505 (District of Columbia Court of Appeals, 2009)
Moore v. Axelrod
443 A.2d 40 (District of Columbia Court of Appeals, 1982)
F. T. Merrill v. B. R. Acker Co.
142 F.2d 102 (D.C. Circuit, 1944)

Cite This Page — Counsel Stack

Bluebook (online)
34 App. D.C. 49, 1909 U.S. App. LEXIS 5996, Counsel Stack Legal Research, https://law.counselstack.com/opinion/james-b-lambie-co-v-bigelow-cadc-1909.