This text of 615 F. Supp. 29 (Jahanger v. Purolator Sky Courier) is published on Counsel Stack Legal Research, covering District Court, E.D. Pennsylvania primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Jahanger v. Purolator Sky Courier, 615 F. Supp. 29, 1985 U.S. Dist. LEXIS 18411 (E.D. Pa. 1985).

Opinion

MEMORANDUM

RAYMOND J. BRODERICK, District Judge.

Plaintiff Mohammed Jahanger seeks to recover damages he suffered when his shipment of legal documents in support of his claim against the Iranian government arrived at its destination at the Peace Palace, The Hague, one day late for consideration by that body. Plaintiff contends that agents of the defendant, Purolator Sky Courier, made oral representations constituting an oral contract that the shipment would be delivered in four days, and claims that the fact that the delivery actually took five days to reach its destination constitutes a breach of that agreement. Defendant contends that its standard airbill is the express contract governing this shipment. The airbill provides that Purolator does not specifically guarantee a delivery date. The defendant moves for summary judgment on the basis of the terms of the airbill.

In deciding defendant’s motion for summary judgment, the Court must determine whether it has carried its burden of showing that there are no genuine issues of material fact which would preclude judgment in its favor as a matter of law. See Hollinger v. Wagner Mining Equipment Co., 667 F.2d 402, 405 (3d Cir.1981). As to issues of fact, all reasonable inferences from the evidentiary material of record must be drawn in favor of the plaintiff. Small v. Seldows Stationary, 617 F.2d *31 992, 994 (3d Cir.1980). A response to a properly supported summary judgment motion may not rest on allegations in the pleadings, but must present significant probative evidence in the form of affidavits, depositions, or answers to interrogatories sufficient to create a genuine issue of material fact. Fed.R.Civ.P. 56(e); Sunshine Books Ltd. v. Temple University, 697 F.2d 90, 96 (3d Cir.1982).

The material facts as to which there is no genuine issue establish that plaintiff believed he had a property claim against the Iranian government. In order for that claim to receive consideration, it was essential that certain legal documents be received at the Peace Palace in The Hague by January 19, 1982. On January 12, 1982, a secretary in the office of plaintiff’s former attorney in Woodbury, New Jersey called defendant Purolator to inquire about the travel time required to send a package from New Jersey to The Netherlands, and was told that delivery took four days. On January 14, 1982, the same secretary called defendant and asked that the shipment be picked up the following day. Upon pickup on January 15, 1982, plaintiff’s lawyer told defendant’s courier that someone in defendant’s office said delivery would take four days. Defendant’s courier responded, “... if that’s what they said ... then it must be true.”

Defendant’s courier filled out a Purolator airbill and left a copy with plaintiff’s attorney. Plaintiff’s attorney did not read or sign the airbill presented to him. The air-bill provides that no specific delivery date is guaranteed. Plaintiff’s package did not arrive at its destination until January 20, 1982, precluding plaintiff’s opportunity to present his claim against the Iranian government.

Defendant maintains that the five-day delivery in this case was one day longer than the normal delivery time. Defendant’s affidavit states that this delivery took an extra day because the Laker Airlines flight used by defendant was diverted by fog to London Stonstead Airport and was not able to land at Gatwick Airport, its scheduled destination. At Stonstead, plaintiff’s package was impounded by Customs with all other baggage on the airline. Despite attempts by defendant’s agent to expedite the Customs process, plaintiff’s package was returned to Gatwick too late to connect with the flight defendant used to transport shipments to Continental Europe [see Affidavit of Laurie Watkins]. These allegations by defendant are uncontroverted by plaintiff.

Plaintiff contends that defendant’s courier should have advised plaintiff’s attorney of the airbill terms inconsistent with plaintiff’s expectation that delivery would take four days. It is defendant’s position that there is no genuine issue as to any material fact, and that summary judgment should be granted defendant on the ground that the airbill is an express contract between the parties, and that based on the uncontroverted facts of this case parol evidence may not be used to vary the terms of the airbill.

Summary judgment will be granted to defendant. No material factual dispute exists in this case. The only dispute is whether defendant’s airbill or the conversations between the agents of the plaintiff and agents of the defendant constitute the contract in this case.

Plaintiff contends that New Jersey law governs the controversy. The Court is of the opinion, however, that the Warsaw Convention, as modified by the Montreal Treaty, governs this case. Title 49 U.S.C. § 1502. The Warsaw Convention applies to “all international transportation of persons, baggage, or goods performed by aircraft for hire” between signatory nations. Chapter I, Article (1), Title 49 U.S.C. § 1502. The United States and The Netherlands are signatory nations of the Convention. The airbill in this case states that in the event of international carriage, the liability provisions of the Warsaw Convention shall apply to the carriage. It is well-settled that where the contract of the parties provides for international carriage between designated termini, the provisions of the Convention govern the carriage. Butz *32 v. British Airways, 421 F.Supp. 127 (E.D. Pa.1976), aff’d 566 F.2d 1168 (3d Cir.1977). Where the Warsaw Convention applies, its limitations and theories of liability are exclusive. Abramson v. Japan Airlines Co., Ltd., 739 F.2d 130, 134 (3d Cir.1984); Boehringer-Mannhein Diagnostics v. Pan Am World Airways, Inc., 737 F.2d 456 (5th Cir.1984).

Article 19 of the Warsaw Convention provides that carriers “shall be liable for damage occasioned by delay in transportation of ... goods.” In this case the plaintiff contends that an oral agreement explicitly fixed the time for arrival of the plaintiffs goods on January 19, 1982. However, the airbill does not show that any specific time for delivery was stipulated, and in fact the printed provisions on the airbill state that “Due to the nature of the business, Purolator cannot guarantee delivery by a stipulated date or by a stipulated time, nor shall Purolator be liable for the consequences of delay ...”

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Romano v. British Airways
943 F. Supp. 623 (N.D. West Virginia, 1996)
Tokio Marine & Fire Insurance v. United Air Lines, Inc.
933 F. Supp. 1527 (C.D. California, 1996)
Onyebuchim Onyeanusi v. Pan American World Airways, Inc.
767 F. Supp. 654 (E.D. Pennsylvania, 1990)
Floyd v. Eastern Airlines, Inc.
872 F.2d 1462 (Eleventh Circuit, 1989)

Cite This Page — Counsel Stack

Bluebook (online)
615 F. Supp. 29, 1985 U.S. Dist. LEXIS 18411, Counsel Stack Legal Research, https://law.counselstack.com/opinion/jahanger-v-purolator-sky-courier-paed-1985.