Jacobs Engineering Group v. United States

CourtCourt of Appeals for the Federal Circuit
DecidedJanuary 19, 2006
Docket2005-5052
StatusPublished

This text of Jacobs Engineering Group v. United States (Jacobs Engineering Group v. United States) is published on Counsel Stack Legal Research, covering Court of Appeals for the Federal Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Jacobs Engineering Group v. United States, (Fed. Cir. 2006).

Opinion

United States Court of Appeals for the Federal Circuit

05-5052

JACOBS ENGINEERING GROUP, INC.,

Plaintiff-Appellant, v.

UNITED STATES,

Defendant-Appellee.

Robert J. Symon, Spriggs & Hollingsworth, of Washington, DC, argued for plaintiff-appellant.

James W. Poirier, Trial Attorney, Commercial Litigation Branch, Civil Division, United States Department of Justice, of Washington, DC, argued for defendant- appellee. With him on the brief were Peter D. Keisler, Assistant Attorney General and David M. Cohen, Director.

Appealed from: United States Court of Federal Claims

Judge George W. Miller United States Court of Appeals for the Federal Circuit 05-5052

Plaintiff-Appellant,

v.

______________________________

DECIDED: January 19, 2006 ______________________________

Before MAYER, Circuit Judge, FRIEDMAN, Senior Circuit Judge, and BRYSON, Circuit Judge.

FRIEDMAN, Senior Circuit Judge.

A development and construction contract required the government to reimburse

the contractor for 80 percent of its cost of performing the contract. The contract’s

termination-for-the-convenience-of-the-government clause (“termination clause”)

required the government upon such termination to pay the contractor “[a]ll costs

reimbursable” under the contract. See 48 C.F.R. § 52.249-6(g); Jacobs Eng’g Group,

Inc. v. United States, 63 Fed. Cl. 451, 455 (2005) (trial court decision). The question is

whether, when the government so terminated the contract, it was required to reimburse

the contractor for all of the costs the contractor incurred up to that point or only for 80

percent of them. Reversing the United States Court of Federal Claims, we hold that the

contractor may recover all of its cost, rather than 80 percent. I

The government entered into a contract with Jacobs Engineering Group, Inc.

(“Jacobs”)’ predecessor (whose contract Jacobs took over when it acquired the

predecessor) to develop, design, fabricate, construct, and install a gasification

improvement facility. No fee was payable to the contractor, but the contract contained

the following cost sharing provision covering the “total estimated cost for the work” of

$28,750,375:

Cost Sharing. The Contractor and the Government agree to share the cost of the effort for Phase I and Phase II as follows:

Government Contractor Total (80%) (20%) (100%) Phase I $19,850,784 $4,962,696 $24,813,480 Phase II 3,149,515 787,379 3,936,894 Total $23,000,299 $5,750,075* $28,750,374

*Includes foregone fee in the amount of $1,181,594 for Phase I and $169,531 for Phase II.

The contract further provided that if the contracting officer approved a cost

overrun, the contractor’s share would be 20 percent.

The contract also contained a standard termination for convenience clause,

Federal Acquisition Regulation (“FAR”) § 52.249-6 (May 1986), which authorized the

government to “terminate performance of work [if] [t]he Contracting Officer determines

that a termination is in the Government’s interest.” If that occurred, the government was

required to pay the contractor “[a]ll costs reimbursable under this contract, not

previously paid, for the performance of this contract before the effective date of the

termination, and part of those costs that may continue for a reasonable time with the

05-5052 2 approval of or as directed by the Contracting Officer.” FAR § 52.249-6(g)(1) (May

1986).

The contract also authorized the contractor to discontinue the project after Phase

I was completed unless it received what it deemed “adequate cost sharing and . . . an

advanced patent waiver.” If the contractor did so, it would “be liable for 20% of the

costs incurred during the performance period.”

During performance, the government terminated the contract for its convenience

(because it did not have funds to complete performance). Jacobs submitted a

termination settlement proposal which sought reimbursement of 100 percent of its costs,

which the government rejected. The contracting officer then rejected Jacobs’ claim for

recovery of all of its costs, limiting recovery to 80 percent. Jacobs challenged that

decision in the United States Court of Federal Claims.

On cross-motion for summary judgment, the court granted the government’s

motion and entered a judgment on its behalf. 63 Fed. Cl. at 459. The court stated:

The termination clause does not invalidate the cost-sharing provision of the Contract. Rather, it clearly seeks to fashion a remedy for the contractor in conjunction with the cost- sharing provisions. Thus, only those costs that would be reimbursed under the Contract will be paid to the contractor in the event of a termination for convenience. Here 80 percent of Jacobs’s costs were reimbursable under the cost- sharing provision and therefore, under the termination for convenience clause, Jacobs is entitled to only 80 percent of its costs not previously paid.

Id. At 457 (emphasis in original) (citations omitted).

II

The termination clause required the government, upon terminating the contract,

to pay the contractor “[a]ll costs reimbursable under this contract.” The government

05-5052 3 contends, as the Court of Federal Claims held, that since the contract required it to

reimburse the contractor for only 80 percent of the costs, its payment under the

termination clause is limited to 80 percent of the costs. We conclude, however, that the

term “all costs reimbursable” defines the type or kind of costs for which the contract

provides reimbursement and not the amount of such costs.

The contract specifies a substantial number of costs that are reimbursable and

some that are not. Reimbursable costs include “fabricated or unfabricated, parts, work

in process, completed work, supplies, and other materials procured or acquired for the

work terminated, . . . completed or partially completed plans, drawings, information, and

other property that . . . would be required to be furnished to the Government, . . . and

the jigs, dies, fixtures, and other special tools and tooling acquired or manufactured for

this contract.” FAR § 52.249-6(c)(6) (May 1986). They also include costs allowable

under FAR § 31.2 (see FAR § 52.249-6(h) (May 2004)), such as labor relations costs

(FAR § 31.205-21), plant protection costs (FAR § 31.205-29), and help-wanted

advertising costs for jobs specific to the project (FAR § 31.205-34(a)(1)). On the other

hand, entertainment costs (FAR § 31.205-14), fines and penalties (FAR § 31.205-15),

and general help-wanted advertisement costs (FAR § 31.205-34(b)) are not

reimbursable. The termination clause’s reference to “all costs reimbursable” under the

contract appears designed to incorporate the contract’s division between reimbursable

and non-reimbursable costs.

Throughout the contract, when the parties intended the 80 percent – 20 percent

division of costs to cover particular situations, they explicitly so provided. The table

shown above specified the amount of the costs for each phase of the contract that each

05-5052 4 party would bear. If the contractor terminated performance after Phase I was

completed, it would “be liable for 20% of the costs incurred during the performance

period.” If there was an approved cost overrun, the contractor was required to absorb

20 percent of it.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Jacobs Engineering Group, Inc. v. United States
63 Fed. Cl. 451 (Federal Claims, 2005)

Cite This Page — Counsel Stack

Bluebook (online)
Jacobs Engineering Group v. United States, Counsel Stack Legal Research, https://law.counselstack.com/opinion/jacobs-engineering-group-v-united-states-cafc-2006.