Jacksonville & Atlantic Railroad v. Woodworth

26 Fla. 368
CourtSupreme Court of Florida
DecidedJune 15, 1890
StatusPublished
Cited by5 cases

This text of 26 Fla. 368 (Jacksonville & Atlantic Railroad v. Woodworth) is published on Counsel Stack Legal Research, covering Supreme Court of Florida primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Jacksonville & Atlantic Railroad v. Woodworth, 26 Fla. 368 (Fla. 1890).

Opinion

Raney, C. J.

I. The first assignment of error in this case is, that the praecipe for the summons ad respondendum was not recorded as required by law. The statute, section 4, page 811, McClellan’s Digest, makes it the duty of the clerks of the Circuit Court to transcribe “ into their memorandum books ” each praecipe before issuing the original writ of summons. If any advantage can be taken by a defendant of the failure of the Clerk to perform this duty, it must be done in the Circuit Court, and at least before a general appearance to the writ. Certainly the objection cannot be raised primarily in the Appellate Court. With these observations, we pass to the question whether or not the verdict is contrary to the evidence,

II. By the terms of the contract the Pavilion at Pablo Beach was to have been completed on the first day of October. The plaintiff, Woodworth, continued subsequently to prosecute the work. From his doing so, and the mere assent thereto (whether express or implied,) by the railroad company, no modification, waiver or abandonment of the [380]*380contract as to any other of its features than that of the time for completing the building, was to be inferred. Benjamin’s Principles of Contract, 139; Phillips vs. Seymour, 91 U. S., 646; Stewart vs. Keteltas, 36 N. Y., 388; Cooke vs. Murphy, 70 Ill., 96. The fact that the plaintiff may have had a right to recover damages of the defendant on account of delays to which it put the plaintiff by not delivering materials promptly in accordance with the contract, did not entitle him to any more or different pay for building the Pavilion, than the sum specified in the contract.

The parties had the right to alter the contract as to any of its terms, if they saw fit to do so; (Munroe vs. Perkins, 9 Pick., 298; Rogers vs. Rogers & Brother, 139 Mass, 440, and authorities supra), but whoever asserts that there has been any material alteration in, or abandonment of, a contract, pending its execution, is under burden to prove the allegation.

From the time of the execution of the contract to the ninth of October, there was nothing to indicate an abandonment of it. On that day the president of the railroad company wrote the letter to be found in the statement of the case, upon which letter the plaintiff, as shown by his testimony, relies as evidence that the contract had been abandoned. There is.in this letter an admission of detention caused by bad weather, and an expression of willingness to make due allowance for it; but the inference to be drawn from the letter as a whole is that he expected the plaintiff to complete the building, and there is in it nothing indicating an abandonment of the contract except as to the time for completion' of the work. ITe complains that the building is progressing very slowly, and insists that the plaintiff shall put on additional force and complete it without further delay; all of which must, in the absence of proof of a new [381]*381contract, be considered as an insistance by the company of a prompt performance by the plaintiff of the September contract in all its features except that of time for the completion of the work. .

The plaintiff states that on or about the 24th of November he demanded a settlement, and that “ they ” (meaning, it is to be assumed, some representative of the defendant,) showed him an account which was more than the contract. He gives no further explanation, or description of this account. The testimony of Ely, the treasurer of the company, shows that the plaintiff rendered the company an account, consisting of a statement, the commencement of which is as follows:

“Jacksonville, Fla., Nov. —, 1885.

“Am’t due for labor and material for build’g at Pablo B’ch.”

' This heading is followed by the names of persons and firms, and opposite each name is the amount due them for labor or materials. Below this is a certificate of William C. West, a notary public, bearing date November 24th, 1885, to the effect that the plaintiff had personallyappeared before him, and being duly sworn, “affirms that the within statement of amount due for labor and material is correct.” Then follows the following account:

“Jacksonville, Fla., Nov. 18, 1885.

“ J. & A. R. R. Co. To Jas. F. Woodworth, 3Dr.

To building Pavilion at Pablo B’ch, as per contrac t$3,980.00

For casing 17 windows, at $1.50 per window . . 25.50

1 sliding door lock.......... 2.50

3 doz. barrel bolts on sliding doors...... 7.20

Fabor for same.............. 3.00

1 extra column in building......... 5.00

$4,023.20

Rec’d by cash............ 1,100.00

2.923.20

[382]*382The item: “To building Pavilion at Pablo Beach, as per contract, $3,980,” is an assertion by the plaintiff that he had earned, and was entitled to debit the company the sum stated for building the Pavilion, and this sum being the same as that mentioned in the written contract of September, it, in the absence of proof of another and substituted contract, is to be taken as an identification of the September contract, and an admission of it as being the one under whose terms he had constructed the building, and was claiming a credit of the stated amount. The other items of this account, one of which is expressly stated to be “extra,” must, in the absence of 'any explanation to the contrary, be regarded as additional to the contract, but not as neutralizing the admission made by the first item. Their presence in the account is not inconsistent with the idea of the existence of the contract as indicated by the first item. The credit item of $1,100 corresponds in amount witli the aggregate of the five cash payments which Ely, the treasurer of the company, says he made to plaintiff as follows : September 1 ith,$25o, September 19th, $250, October 1st, $300, October 17th, $200, November 10th, $100. The first four of these payments correspond in their aggregate sum with that of the four weekly installments of $250 each, “ with which to pay for labor,” which the contract provided should be paid to plaintiff while the work was in progress, and it is to them that the president of the company refers in speaking of one thousand dollars as having been paid “ almost literally ” as provided by the contract. Considering the credit of $1,100 in connection with the testimony of Ely, all of which payments had been made prior to the making or rendering of the account of November 18th, the only reasonable construction to be placed on such credit is, that it is an acknowledgment by the plaintiff of so much as having [383]*383been paid on the September contract. Even if we assume that $43.20 of it, which amount is sufficient to satisfy the additional items, was intended by the plaintiff in rendering his account, to be applied to those items, he must still be understood as applying $1,056.80, the balance of the credit, to the $3,980 debit for building the Pavilion under the September contract.

The aggregate of the items in the sworn statement of the amount due for labor and material for building the Pavilion, is as it was rendered, $3,340.01. In so far as the evidence shows, these payments appear to have been made to the persons named in it. On the eleventh of November, the plaintiff accepted an order drawn on him by J. L. Bettes and W. E. Gruber, in favor of First National Bank, for “fifty dollars on account of painting Pablo Beach Pavilion,” and it was accepted by plaintiff

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Indian River Construction Co. v. City of Jacksonville
350 So. 2d 1139 (District Court of Appeal of Florida, 1977)
Bailey v. Martin
112 S.E.2d 807 (Court of Appeals of Georgia, 1960)
Wiggin v. Marsh Lumber Co.
87 S.E. 194 (West Virginia Supreme Court, 1915)
Duval County v. Charleston Lumber & Manufacturing Co.
45 Fla. 256 (Supreme Court of Florida, 1903)
Redmond v. W. M. Donaldson & Co.
35 Fla. 167 (Supreme Court of Florida, 1895)

Cite This Page — Counsel Stack

Bluebook (online)
26 Fla. 368, Counsel Stack Legal Research, https://law.counselstack.com/opinion/jacksonville-atlantic-railroad-v-woodworth-fla-1890.