Jackson v. Porter Land and Water Co.

90 P. 122, 151 Cal. 32, 1907 Cal. LEXIS 389
CourtCalifornia Supreme Court
DecidedApril 4, 1907
DocketL.A. No. 1761.
StatusPublished
Cited by15 cases

This text of 90 P. 122 (Jackson v. Porter Land and Water Co.) is published on Counsel Stack Legal Research, covering California Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Jackson v. Porter Land and Water Co., 90 P. 122, 151 Cal. 32, 1907 Cal. LEXIS 389 (Cal. 1907).

Opinion

*33 LORIGAN, J.

This action was brought to recover the •contract price for furnishing and erecting pumping machinery.

The trial court found that the parties entered into a contract on June 2, 1902, whereby plaintiff was to erect on the premises of defendant a pumping plant consisting of a thirty-five actual horsepower Olds distillate engine with a 110-gallon oil tank, together with a horizontal centrifugal pump of a capacity to elevate three hundred and fifty inches of water twenty-four feet high; said plant and all connections to be first-class and connected with defendant’s fifteen wells; the plant to be completed within thirty days and ..guaranteed to perform the work as specified, the purchase price being $3,250; the time provided in the agreement for installing the pumping plant was waived by the defendant; that plaintiff performed all the conditions of the agreement •except' that he did not erect or furnish a thirty-five actual .horsepower engine as provided in the contract, but, on the ■contrary, the engine erected by plaintiff on said premises .and as part of said pumping plant was materially less than thirty-five horsepower; that said engine was not capable of providing the necessary power to raise the amount of water in said contract required; that on the twelfth day of August, 1902, the pumping plant, including the engine, was received "by defendant, but was not to be considered accepted till •examined by an expert to be called by defendant; that .said pumping plant was operated by defendant continuously from the twelfth day of August, 1902, to the seventh day •of September, 1902, when an expert called by defendant ■examined the same and found only a trivial defect in the .governor attached to the engine, which was promptly remedied, and thereafter defendant continued to operate said pumping plant in pumping water for its irrigating system until about the fifth day of November, 1902, at which last date defendant discontinued the use of the engine and pump, constituting part of said pumping plant, but did not notify plaintiff that it had done so until somewhere between the fifteenth and thirtieth days of that month; that some time during the latter half of the month of November, 1902, • defendant notified plaintiff that the said engine was not of rthe horsepower provided for in the contract; that during *34 the entire time defendant was using said pumping plant it knew the engine was not of the horsepower provided in the contract; that after November 5, 1902, when defendant ceased operating said engine and pump, it detached from nearly all of its fifteen wells the horizontal pipe furnished by plaintiff as part of the pumping plant, and which" was about sixteen hundred feet in length, and had been laid in an open trench with suction-pipes, on each side of said fifteen wells from which the said pumping plant was designed and intended to draw water, but left said sixteen hundred feet of pipe in the trench with openings made by detaching the suction-pipe leading down into the wells, through which openings water from defendant’s flowing wells and seepage waters coming into said trench were allowed to enter said pipe, and defendant removed the plug from the lower end of said pipe, so as to permit water to flow through the same into defendant’s irrigating system, and thereby continuously-supplied water to the customers of defendant from the time when it ceased to operate said engine and pump; that without the knowledge or consent of plaintiff, in October, 1903, defendant caused said engine to be operated by an hydraulic engineer for the portions of two days for the purpose of testing and ascertaining the horsepower of said engine.

In addition the court found that by taking the pumping plant, including the said engine, into its possession on the twelfth day of August, 1902, and by operating the same for a period of nearly three months,—to wit, until the fifth day of November, 1902,—without any notice to the plaintiff of the inefficiency of said machinery, or that the same was not-satisfactory, the defendant accepted the said plant, notwithstanding it was not in accordance with the contract.

Upon these findings judgment was rendered in favor of plaintiff for the full amount of the purchase price. This, appeal is taken by the defendant from the judgment and. the order of the court denying its motion for a new trial.

It is insisted by appellant that the evidence is insufficient, to justify the finding that defendant accepted the plant as. furnished by the plaintiff, and that the judgment was not-warranted by the findings.

The point that the findings were not justified by the evidence is, we think, untenable. The evidence on the question! *35 of acceptance, as upon all the other facts in issue, except the terms of the contract and the incapacity of the engine to raise the amount of water required by the agreement, is conflicting; but there was certainly sufficient evidence to be gathered from the conflict supporting all the findings made by the court. It is true that the court was in error as to some dates mentioned in the findings and in some minor particulars, but we do not consider that these substantially affect the sufficiency of the findings.

There was evidence in the case showing that under the contract between them the plaintiff set up on the premises of defendant in connection with its irrigating system, a pumping plant claimed by plaintiff to be of the character called for in the agreement. The defendant had fifteen wells to be operated by this plant, and the machinery having been installed, pipes laid, and connections made with all of these wells, a test operation of the plant was commenced by the plaintiff on August 1, 1902. It was provided in the contract that the plant should be installed by plaintiff in complete running order, and that he should leave his expert with it for six days to instruct the engineer of defendant how to operate the plant, and it was in harmony with this provision of the agreement and to test the plant that a six days’ run by the expert of plaintiff was commenced on August 1, 1902. The evidence of plaintiff shows that at the end of that time the engine, pump, suction-pipe, and other connections worked perfectly, and that the only difficulty which arose with the machinery during that period, but which was overcome, was in the circulating pump, the pulley of which had to be changed several times. The run during these six days, however, demonstrated that the engine furnished and operated by plaintiff as part of the plant was not of thirty-five actual horsepower as provided in the contract, but of very much less power; that it was incapable of raising the quantity of water called for and incapable of raising more than a little over one fourth of the amount. This was known to the defendant at that time. After this run of six days, plaintiff saw the superintendent of the defendant company and told him that the plant had been run six days and was all right. The superintendent insisted that it had not been run six days without touching the plant, and *36 that plaintiff would, have to have his expert run it another six days. This plaintiff did, commencing on August 6th, and ran it to the twelfth day of August; the engine, pump, and connections worked perfectly, but this operation still demonstrated that the engine was incapable of lifting a greater quantity than previously pumped.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Square Deal MacHine Co. v. Garrett Corp.
275 P.2d 46 (California Court of Appeal, 1954)
Garetto v. Almaden Vineyards
257 P.2d 477 (California Court of Appeal, 1953)
Innes Food Equipment Co. v. Sanguinetti Fruit Co.
192 P.2d 83 (California Court of Appeal, 1948)
Pigott v. Clark
23 P.2d 800 (California Court of Appeal, 1933)
Pacific Commercial Co. v. Greer
19 P.2d 543 (California Court of Appeal, 1933)
The Gladium Co., Inc. v. Thatcher
272 P. 340 (California Court of Appeal, 1928)
American Steel Pipe & Tank Co. v. Hubbard
183 P. 830 (California Court of Appeal, 1919)
Imperial Gas Engine Co. v. Auteri
180 P. 946 (California Court of Appeal, 1919)
Nelligan v. Knutsen
175 P. 18 (California Court of Appeal, 1918)
Burrell v. Southern California Canning Co.
169 P. 405 (California Court of Appeal, 1917)
Fairbanks, Morse & Co. v. Nelson
217 F. 218 (Ninth Circuit, 1914)
Sherman v. Ayers
130 P. 163 (California Court of Appeal, 1912)
North Alaska Salmon Co. v. Hobbs, Wall & Co.
113 P. 870 (California Supreme Court, 1911)
Byron Jackson Machine Works v. Duff
109 P. 616 (California Supreme Court, 1910)

Cite This Page — Counsel Stack

Bluebook (online)
90 P. 122, 151 Cal. 32, 1907 Cal. LEXIS 389, Counsel Stack Legal Research, https://law.counselstack.com/opinion/jackson-v-porter-land-and-water-co-cal-1907.