Jackson v. Federal Surety Co.

228 N.W. 400, 56 S.D. 335
CourtSouth Dakota Supreme Court
DecidedDecember 31, 1929
DocketFile No. 6612
StatusPublished

This text of 228 N.W. 400 (Jackson v. Federal Surety Co.) is published on Counsel Stack Legal Research, covering South Dakota Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Jackson v. Federal Surety Co., 228 N.W. 400, 56 S.D. 335 (S.D. 1929).

Opinion

CAMPBELL, J.

Concrete Engineering 'Company, a corporation, hereinafter mentioned as the contractor, was awarded a contract for road construction work, including some culverts and bridges on Federal Aid Project No. 163, being a part of state trunk highway No. 85, in Butte and Lawrence counties, S. D.; the performance thereof being bonded by defendant Federal Surety Company. The form of the contract and. bond and the provisions thereof are identical, excepting as to description of location and specific work to ¡be performed, with those referred to' and recited in Dennis v. Enke, 55 S. D. 15, 224 N. W. 925.

The contract bears date July 28, 1924, and appears to have been formally awarded by the state highway department on July 26, 1924. The contract bond was executed by the contractor on July 29, 1924, and by the defendant surety company on September 2, 1924. Plaintiffs instituted this action again defendant surety company in April, 1926, seeking to recover $1,397.97, with interest, claimed to 'be due as an unpaid balance on the purchase price of certain structural steel furnished by plaintiffs to the contractor and used by him in the performance of the contract in question. The case was tried to the court without a jury, and findings, conclusions, and judgment were in favor of plaintiffs for the full amount asked, from which judgment and an order denying" its motion for a new trial defendant has appealed.

The performance of the contract in question required the use of certain beams and other structural steel for bridges, etc. While the formal award was not made until July 26, 1924, nor the contract executed until July 28, 1924, yet it appears from the record that bids were opened by the highway department for the work in question on June 10, 1924, and it would seem that from and after June 10, 1924, the contractor knew that his was the low bid, and that he would presently, and. in due course, receive the formal award of the contract, and he appears to have commenced to arrange for 'his materials, etc., prior to the formal award; for on date of June 23, 1924, respondents made a proposal to the contractor for the furnishing of structural steel for this particular job in the following language:

“Concrete Engineering Co., Rapid City, S. Dak. We propose to furnish all Structural Steel subject to all terms and conditions stated herein and on the reverse side of this proposal, for Law[337]*337rence-Butte Counties, S. Dak., F. A. P. 163, which were awarded purchaser at Pierre, S. Dak., June 10, 1924.
24 — 8"x33^¿ H-beams . 24' o"
32 — i8"x54.?# I-beams . 35' 9"
2 — Fabricated Struts . l8' 7"
“Above material to ship to Spearfish, S. Dak.
42 — 8"x33# H-beams ... 24' o"
8 — 15f X42.9# I-beams ... 33' 9"
50 — ii2,,x31,8^£ I-beams.,. 25' 9"
2 — Fabricated Struts .'. 18' 7"
“Above material to ship to Belle Fourche, .S. Dak.
“We agree to- furnish all of the above material, to be shipped subject to sight draft attached to Bill of Lading at following prices:
I-beams, from mill .. .. .$3.47 per cwt. base
H-beams, from our stock to ship with T from Mill .$4.21 per cwt. net
Fabricated Struts ..$5.00 per cwt.
“Prices are F. O. B. Belle Fourche' or 'Spearfish, South Dak.
“Pittsburgh-Des Moines Steel Co.
“By Gordon R. Lunt.”

The foregoing proposal was accepted by the contractor on June 26, 1924, by indorsement to that effect thereon in a form provided for that purpose, and is also indorsed under date of July 2, 1924,, with the approval of Geo. A. Smith, one of the members of respondent copartnership. It is to be observed that by the proposal the material to be furnished was to be shipped “subject to sight draft attached to bill of lading.” It is also entirely clear that the proposal and acceptance form a complete and valid contract for the purchase and sale of the merchandise therein described upon the terms therein stated.

At the time this proposal was made and accepted, by virtue of prior dealings entirely unconnected with the contract or project here involved, there was a balance due from the contractor to respondents for materials previously furnished on other jobs in the amount of $4,397.97, which had been unpaid for such a length of time as to have accumulated approximately $248 accrued interest.

[338]*338Prior to the contract evidenced by the proposal and acceptance above set forth, respondents in their dealings with the contractor had extended credit, and had not previously required the contractor to take up sight draft against bill of lading as materials were furnished. One of respondents’ witnesses states that they knew the contractor was slow with its payments, and in reply to the question, “When did you get scared of them?” answered, “About the time this contract was taken.”

Nearly a month after the execution of this contract, and under date of July 26, 1924, and at a time when it was already legally bound to furnish the materials for Federal Aid Project No. 163 upon payment therefor by sight draft for the purchase price thereof against bill of lading as embodied in the proposal and acceptance, regardless of any previous balance due, respondents wrote to the contractor the following letter:

“Pittsburgh-Des Moines Steel Co.
“D'es Moines, Iowa. July 26, 1924.
“Concrete Engineering Company, Rapid City, South Dakota. Atten: Mr. C. J. Laughlin. Gentlemen: In view of the fact that we are all striving under’very drastic conditions at the present time, we wish to be as lenient as possible, and after counseling with the Credit Manager, Mr. Elmer Murray, we have mutually agreed to present the following proposition to you.
“The amount of the sight-draft on your two new orders to Belle Fourche and Spearfish. under F. A. P. 163, Lawrence-Butte Counties, shall be approximately $7,415.00. The amount you owe us at the present is $4,379.97, which has been due for some time. There has accumulated interest in the amount of $248.00, which malees a total of $4,645,-97.
“Now, what we propose is this. Upon receipt of steel for Belle Fourche and Spearfish, it shall be necessary for you to pay the sight-draft of approximately $7,500. We wish to take this amount and apply on your old account and thus square this up, leaving a payment of approximately $3000 on the new account or a balance of the same amount that you owed us before. In case you clear up your accounts in full by October 1st, we are willing to waive the interest charge, which is $248.00 up to July 31st. ■
“We wish you to write us a letter authorizing us to handle this money in the manner as outlined above, which we consider a [339]*339mighty fair proposition to yon and sincerely 'hope that you shall appreciate the business value of such an offer, and we shall receive the authorization in a few days.
“Very truly yours,

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Dennis v. Enke
224 N.W. 925 (South Dakota Supreme Court, 1929)

Cite This Page — Counsel Stack

Bluebook (online)
228 N.W. 400, 56 S.D. 335, Counsel Stack Legal Research, https://law.counselstack.com/opinion/jackson-v-federal-surety-co-sd-1929.