Jackson County v. Upper Oconee Basin Water Authority

766 S.E.2d 488, 330 Ga. App. 11, 2014 Ga. App. LEXIS 818
CourtCourt of Appeals of Georgia
DecidedNovember 21, 2014
DocketA14A0805
StatusPublished
Cited by1 cases

This text of 766 S.E.2d 488 (Jackson County v. Upper Oconee Basin Water Authority) is published on Counsel Stack Legal Research, covering Court of Appeals of Georgia primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Jackson County v. Upper Oconee Basin Water Authority, 766 S.E.2d 488, 330 Ga. App. 11, 2014 Ga. App. LEXIS 818 (Ga. Ct. App. 2014).

Opinion

Boggs, Judge.

This is the second appearance of this case before this court. In our previous opinion, we affirmed the denial of the Upper Oconee Basin Water Authority’s (“the Authority’s”) motion to dismiss multiple claims filed by Jackson County (“the County”). Upper Oconee Basin Water Auth. v. Jackson County, 305 Ga. App. 409 (699 SE2d 605) (2010) (“Oconee Basin /”). In this case, the County appeals from the trial court’s grant of the Authority’s motion for summary judgment and the denial of its cross-motion for summary judgment. For the following reasons, we affirm.

It is well established that

[o]n appeal from a grant or denial of summary judgment, we conduct a de novo review of the law and evidence. In applying this standard of review, we view the evidence in the light most favorable to the nonmovant to determine whether a genuine issue of material fact exists and whether the moving party is entitled to judgment as a matter of law.

(Citation and punctuation omitted.) BAC Home Loans Servicing v. Wedereit, 328 Ga. App. 566 (759 SE2d 867) (2014); see also OCGA § 9-11-56 (c).

1. The relevant facts here are provided in this court’s prior opinion:

Pursuant to the Upper Oconee Basin Water Authority Act, the Authority was created in 1994 for the purpose of
acquiring and developing adequate sources of water supply, including but not limited to the construction of reservoirs; the treatment of such water, and thereafter the transmission of such water within the Upper Oconee Basin area, and to various counties, municipalities, and public authorities located therein; and the collection and treatment of waste water from the counties, municipalities, and public authorities within the . . . area.
Ga. L. 1994, pp. 5123, 5125, § 4. Athens-Clarke, Barrow, Jackson and Oconee Counties comprise the “Member Counties” under the Act. Ga. L. 1994, p. 5126, § 5 (a) (6).
[12]*12In 1996, the Authority and the Member Counties entered into a 50-year Intergovernmental Reservoir and Raw Water Supply Agreement (“Agreement”) to further the purposes of the Act to construct reservoirs and treat and transmit that water to the Member Counties. Pursuant to the Agreement, the Authority was to plan, build and manage the Bear Creek Reservoir, which would serve as a source of water to the Member Counties.
As is pertinent here, Article II of the Agreement states:
The Authority shall provide or cause to be provided and each Member County may take from the Authority its Entitlement Share of the Water Supply pursuant to Section 306. The Authority will be responsible for planning, negotiating, designing, financing, acquiring or constructing, contracting for, administering, operating, and maintaining the Project as necessary to effect the delivery and sale of such Water Supply to each Member County.
Section 102 (k) of the Agreement expressly assigns “Entitlement Shares” to each Member County, f[1] and Section 301 of the Agreement obligates the Authority to “cause to be delivered or make available for delivery to the Member Counties during each month of each Water Supply Year its Entitlement Share. . . .” Section 306 further specifies how much water each Member County is allowed to withdraw. Pursuant to that section, “the maximum quantity that may be withdrawn by any Member County .. . shall be limited to a quantity equal to the EPD[2] approved Established Yield of the Project multiplied by the Member County’s Entitlement Share of the Project.” “EPD approved Established Yield” is not defined in the Agreement, but subsection (a) (1) of Section 306 defines “Established Yield” to mean “the maximum rate of withdrawal which can be sustained during critical dry periods as established by a mathematical simulation of the reservoir operation as it would have occurred during the worst historic drought for which applicable stream-flow records are available.”

[13]*13Oconee Basin I, supra, 305 Ga.App. at 409-411 (1). InNovember 1996, four months after the parties entered into the Agreement, an engineer retained by the Authority submitted a hydrology report to the EPD in which he concluded that the peak monthly yield of the reservoir was 58.3 MGD (million gallons per day) using the “most critical drought period of 1986-1989.”

Upon completion of the construction of the reservoir in April 2002, the EPD concurred with the conclusions presented in the hydrology report and granted the Authority’s request for a surface water withdrawal permit not to exceed 58 MGD. The permit noted that the County was to receive a 25% entitlement share of the 58 MGD monthly average. A permit pursuant to the same conditions was issued in 2007, with an expiration date of April 2022.

In 2008, the County requested that the Authority hire an independent third party to recalculate the Established Yield____[T]he County contended that the Authority should recalculate the Established Yield to incorporate the stream-flow records for the year 2007 because those records reflect the “worst historic drought for which applicable stream flow records are available.” The County contended that recalculations based on those records would... result in a reduction of the Established Yield.3

Oconee Basin I, supra, 305 Ga. App. at 411 (1).

When the Authority denied the County’s request to recalculate the Established Yield, the County filed an action asserting breach of the Agreement by the Authority’s failure to comply with its terms. The parties later filed cross-motions for summary judgment. Following a hearing, the trial court granted the Authority’s motion for summary judgment and denied the County’s motion, finding that the Agreement did not require a recalculation of the Established Yield based upon a future drought, the EPD approved Established Yield governs the quantity of water which the Authority must make available to the County, and that “[i]t would have been illogical for the parties to have incurred the expense to construct the treatment plant had they contemplated that the yield of the Reservoir could be permanently and drastically reduced based upon one future weather [14]*14event.” We agree with the trial court’s result here, but affirm based only upon the plain language of the Agreement.

2. The County complains of the trial court’s ruling on the cross-motions for summary judgment, arguing that the court erred in finding that the Agreement does not require the Established Yield to be recalculated using the streamñow data for the new worst historic drought of 2007-2008.

To begin with, we note that the construction of a contract is a question of law for the court. And the construction of a contract involves three steps. The first step is to decide whether the language of the contract is clear and unambiguous. If so, the contract is enforced according to its plain terms, and the contract alone is looked to for meaning. Second, if the language of the contract is ambiguous in some respect, the rules of contract construction must be applied by the court to resolve the ambiguity.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

2800 CHAMBLEE DIAMOND, LLC v. YOHANNES FITSUM
Court of Appeals of Georgia, 2021

Cite This Page — Counsel Stack

Bluebook (online)
766 S.E.2d 488, 330 Ga. App. 11, 2014 Ga. App. LEXIS 818, Counsel Stack Legal Research, https://law.counselstack.com/opinion/jackson-county-v-upper-oconee-basin-water-authority-gactapp-2014.