Jackman Construction, Inc. v. Town of Baggs

2012 WY 80, 278 P.3d 247, 2012 WL 2105907, 2012 Wyo. LEXIS 85
CourtWyoming Supreme Court
DecidedJune 12, 2012
DocketS-11-0252
StatusPublished

This text of 2012 WY 80 (Jackman Construction, Inc. v. Town of Baggs) is published on Counsel Stack Legal Research, covering Wyoming Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Jackman Construction, Inc. v. Town of Baggs, 2012 WY 80, 278 P.3d 247, 2012 WL 2105907, 2012 Wyo. LEXIS 85 (Wyo. 2012).

Opinion

HILL, Justice.

[11] Jackman Construction, Inc. (Jack-man), was awarded a contract to improve the Town of Baggs' (the Town) water treatment plant. After the project suffered significant delays, payments were submitted and accepted, and a dispute ensued as to whether or not the last payment constituted "final payment." Jackman filed a governmental claim as well as a complaint for breach of contract, both seeking damages from the Town. The Town filed its "Motion for Summary Judgment," which the district court granted. We affirm.

ISSUES

[T2] Jackman presents three issues for our consideration:

A. Whether the district court erred in finding no genuine issues of material fact and that the last payment by the Town to Jackman was "Final Payment" under the contract between the parties;
B. Whether the district court erred in finding no genuine issues of material fact and that the Town did not expressly acknowledge in writing that the issue of liquidated damages was still unsettled when it made its last payment to Jackman; and
C. Whether the district court erred in finding no genuine issues of material fact and that Jackman was required to submit, but had not submitted, a written "claim" in connection with the Town's imposition of liquidated damages.

FACTS

[T3] In September of 2006, the Town sought bids to upgrade its water treatment plant. The Town awarded one general contract to Jackman and one general contract to Westech Construction. On December 20, 2006, the Town and Jackman entered a contract detailing the work to be performed by Jackman as well as the price to be paid by the Town.

[T4] Originally, the contract required Jackman to be substantially finished with its construction within 120 days. An additional 30 days was given for finalization, including payment, for a total projected time of 150 days. A "Notice to Proceed" was sent to Jackman on March 15, 2007, effective as of March 22, 2007.

[T5] The dates of the project were affected by change orders filed by the Town. Also, the cost of the project increased. Change Order No. 3, effective July 11, 2007, altered the date of completion to 36 calendar days later, making the date for "final payment" September 26, 2007. Change Order No. 5 increased the contract price by $4,670.00, increased the contract time by 3 days, making the date for "final payment" September 29, 2007. Change Order No. 7 again increased the contract price, this time by $3,488.00 and changed the contract time as well, making the date for "final payment" April 26, 2008. Change Order No. 7 added 208 days for "approved delays." All of these change orders were submitted by Jackman. As it happened, due to project delays, the Certificate of Substantial Completion was dated September 12, 2008, and final completion occurred on October 13, 2008.

[T6] After the project was substantially completed, Jackman sought "final payment" from the Town in the amount of $187,944.08. However, the Town approved "final payment" to Jackman for a smaller amount, $154,968.08. Correspondence from the Town to Jackman incorporated Change Order Nos. 1-7 into the ultimate approval of paying the smaller amount to Jackman. The correspondence also explained that the Town purposefully would withhold $100,000.00 in liquidated damages, at the rate of $500.00 per day, for 200 days of delay by Jackman Construction, pursuant to the contract.

[17] On June 18, 2009, Jackman approved Change Order No. 7, which recognized a time delay grant of 208 days. On June 20, 2009, Jackman deposited the "final payment" check from the Town, in the amount of $154,968.08, which reflected the *250 "final payment" approved by the Town, not the amount requested by Jackman of $187,944.08. One year later, Jackman filed its "Notice of Governmental Claim under Wyo. Stat, Ann. § 1-89-118 and Itemized Statement of Claim" against the Town. In its claim, Jackman sought damages in the amount of $221, 600, 00, claiming $100, 000.00 in "unjustified assessment of Iquidated damages" and $121, 600.00 in "other damages" due to additional expenses incurred by Jack-man as a result of delay caused by the Town. Subsequent to its governmental claim, Jack-man filed its complaint for breach of contract and unjust enrichment in which it sought $221,600.00 from the Town.

[18] On July 11, 2011, the Town responded with its motion for summary judgment seeking final disposition on the grounds that: 1) Jackman failed to submit timely written notice of claims as required by the parties' contract and failed to comply with the contract regarding changes in contract price in that Jackman did not make any claim for any adjustment in the contract price; 2) pursuant to the contract, Jackman waived all claims against the Town when it accepted "final payment" from the Town; and 3) "unjust enrichment" is unavailable as a remedy because these parties have an express contract.

[T9] The district court granted the Town's summary judgment as to both the $100,000.00 in liquidated damages, and the $121,600.00 in other damages. The court stated that pursuant to the clear and unambiguous contractual terms, "Jackman Construction failed to make a written request of its claim and also waived any further claim against the ... Town after ... accept[ing] final payment." Also, Jackman's failure to notify the Town of any claim, during any time, falls far beyond the parameters of any waiver argument and cannot absolve it of its failure to abide by the clear contractual terms. This appeal followed.

STANDARD OF REVIEW

[¥10] When reviewing an order granting summary judgment, we consider the record de movo. Stone v. Devon Energy Prod. Co., L.P., 2009 WY 114, ¶ 10, 216 P.3d 489, 492 (Wyo.2009).

[Wle have exactly the same duty as the district judge; and, if there is a complete record before us, we have exactly the same material as did [the district judge]. We must follow the same standards. The pro-pricty of granting a motion for summary judgment depends upon the correctness of a court's dual findings that there is no genuine issue as to any material fact and that the prevailing party is entitled to judgment as a matter of law. This court looks at the record from the viewpoint most favorable to the party opposing the motion, giving to him all favorable inferences to be drawn from the facts contained in affidavits, depositions and other proper material appearing in the record.

Wyo. Med. Ctr. v. Wyo. Ins. Guar. Ass'n, 2010 WY 21, ¶ 11, 225 P.3d 1061, 1064 (Wyo.2010) (quoting McGarvey v. Key Prop. Mgmt. LLC, 2009 WY 84, ¶ 10, 211 P.3d 503, 506 (Wyo.2009)).

[F111] The summary judgment ruling challenged in this case arose out of the district court's determination that the parties' agreement was clear and unambiguous. We review that determination by applying the following standards:

The initial question of whether the contract is capable of being understood in only one way is a question of law for the court. If the court determines that the contract is capable of being understood in only one way, then the language used in the contract expresses and controls the intent of the parties. In such case, the next question, what is that understanding or meaning, is also a question of law.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Examination Management Services, Inc. v. Kirschbaum
927 P.2d 686 (Wyoming Supreme Court, 1996)
McGarvey v. KEY PROPERTY MANAGEMENT LLC
2009 WY 84 (Wyoming Supreme Court, 2009)
Stone v. DEVON ENERGY PRODUCTION CO., LP
2009 WY 114 (Wyoming Supreme Court, 2009)

Cite This Page — Counsel Stack

Bluebook (online)
2012 WY 80, 278 P.3d 247, 2012 WL 2105907, 2012 Wyo. LEXIS 85, Counsel Stack Legal Research, https://law.counselstack.com/opinion/jackman-construction-inc-v-town-of-baggs-wyo-2012.