Jacka v. Ouachita Parish School Board

186 So. 2d 571, 249 La. 223, 1966 La. LEXIS 2530
Supreme Court of Louisiana·Decided May 2, 1966·No. 48020·Published·Cited by 9 cases

Opinion

McCALEB, Justice.

Plaintiff brought this suit to recover $27,005.57, allegedly the balance due him by the Ouachita Parish School Board under a written contract employing him to perform architectural services in connection with the construction of an addition to the Drew School and the erection of an elementary and junior high school, in Ouachita Parish.

The school board admitted the execution of the contract and the performance of the architectural services by plaintiff. However, by way of reconventional demand, it asserted that, during the course of construction of the Riser Junior High School, it was compelled to amend its contract with the contractor (Jesse F. Heard & Sons, Inc.) to include an additional cost of $46,-913.37, which cost was attributable solely to plaintiff’s fault in preparing improper and defective specifications for the construction of the school. Hence, the board alleged the total due plaintiff for services rendered under the contract, after deducting therefrom its damages of $46,913.37, was only $13,563.51, and that since it had previously paid plaintiff $36,286.13, plaintiff was indebted unto it in the sum of $22,722.62 with legal interest thereon from date of judicial demand until paid, for which judgment was accordingly prayed.

Plaintiff in answer to this reconventional demand denied any negligence or fault. Alternatively, he averred that he was furnished a topographical map or survey of the school site by the defendant board through its member and agent, Fred Riser, upon which he relied in the preparation of the plans and specifications; that the board impliedly warranted the correctness of this map or survey and that it is now estopped from denying the accuracy of the map or from asserting negligence on his part.

After a trial in the district court on the issues thus formed by the pleadings, there was judgment for plaintiff as prayed for with interest and costs, and the reconventional demand of the school board was dismissed. On appeal to the Court of Appeal, Second Circuit, the decision was reversed, and judgment was rendered in favor of the *227 school board on its reconventional demand for $2,674.45 with legal interest thereon from judicial demand. See Jacka v. Ouachita Parish School Board, 179 So.2d 923. Plaintiff then applied here for certiorari. The writ was granted, and the case has been argued and submitted for our determination.

We find that the record establishes the following facts: On April 25,1962, plaintiff was employed by the board to furnish architectural services in connection with the building of an addition to Drew School and construction of a new elementary and junior high school to be named Riser Junior High School. The terms of this contract provide :

“ * * * The Architect’s professional services shall consist of and include, among other services which are not specifically mentioned here, the necessary conferences; the preparation of preliminary studies and plans, working drawings, specifications, large-scale detail drawings for architectural, structural, plumbing, electrical and other mechanical work, engineering services * * *
“4. The Architect agrees to stipply all engineering and other special services necessary to complete the zvork. No extra fees shall be charged for such services unless agreed to in writing by the Owner before such services are contracted for and/or rendered.” (Italics ours.)

Plaintiff, having previously secured a topographical map of the site of the Drew School addition at the school board’s expense, endeavored to contact the Superintendent and Assistant Superintendent of defendant board for the purpose of obtaining a topographical survey of the Riser construction site, but was unsuccessful. Mr. Fred Riser, the member of the school board from the ward in which the new school was to be located, made visits to the office of plaintiff for the purpose of checking on the progress of the work and requested information concerning the delay in starting the drawing of plans and letting a contract. Plaintiff informed Mr. Riser on these occasions that he was attempting to secure a topographical survey from the board and that he could not prepare his drawings without it. A day or so later, Mr. Riser appeared at plaintiff’s office with such a survey. Thereupon, plaintiff used this survey for the drawing of the plans and specifications.

After construction had begun, it was discovered by the contractor (Jesse F. Heard & Sons) that the footings shown on the working drawing and specifications could not be placed on the ground due to a discrepancy between the layout of the building and the actual topography of the existing site. The structural engineer employed by plaintiff, Lester High, was then instructed by plaintiff to prepare a topographical map in order to ascertain the dif *229 ferences between the true elevations of the existing ground and the elevations as shown on the map furnished by Mr. Riser. On the basis of Mr. High’s survey, plaintiff prepared a new grading and paving plot plan which was given to the contractor for an estimate. A supplemental estimate in the amount of $28,000.00 was submitted by the contractor, which sum represented the amount necessary to bring the existing site up to the proper grade.

In addition to this change, the school board decided to raise the elevation of the entire school one foot, and the contractor submitted a bid to the board of $46,913.37 to perform the necessary grading work and to raise the elevation of the building. This proposal was accepted by the defendant board. 1

In his written reasons, the trial judge found that plaintiff had established his contention that it was the intention of the parties to the contract that the topographical survey was to be furnished by the defendant board. The judge pointed out that, in addition to his own statement, plaintiff produced two prominent architects, who testified that it was the common practice in the Monroe area for the owner to furnish the architect with a topographical map unless the architect is requested by the owner to have someone of the architect’s choice prepare it at the owner’s expense (as was done by the board in the present case with respect to the-topographical survey of the Drew School site). Further, the judge concluded that the school board was bound by Mr. Riser’s' act in furnishing plaintiff with a topographical map, inasmuch as the board made’ no attempt to contest his apparent authority either by official action or testimonial evidence of any of its members or officers.

The Court of Appeal based its opinion exclusively on the provision of the contract, which stipulated that it was incumbent on the architect “ * * * to supply all engineering and other special services necessary to complete the work.” It stated that this, provision was clear and unambiguous and that the obligation to perform all engineering services included the furnishing of a topographical map and that, since plaintiff failed in this respect, “ * * * he cannot be excused for accepting an incorrect map from another because of custom.”

Free access — add to your briefcase to read the full text and ask questions with AI

Jacka v. Ouachita Parish School Board, 186 So. 2d 571, 249 La. 223, 1966 La. LEXIS 2530 (La. 1966).

186 So. 2d 571 (Jacka v. Ouachita Parish School Board) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

TRAINA PLUMBING & HEATING CONTRACTORS, INC. v. Palmer
580 So. 2d 525 (Louisiana Court of Appeal, 1991)
Varacalle v. Turner
556 So. 2d 836 (Louisiana Court of Appeal, 1989)
Bell v. Jones
523 A.2d 982 (District of Columbia Court of Appeals, 1987)
Matter of Succession of Dunham
408 So. 2d 888 (Supreme Court of Louisiana, 1981)
W. N. Bergeron & Sons v. Caldwell Sugar Co-op, Inc.
340 So. 2d 1054 (Louisiana Court of Appeal, 1976)
Consumer Money Order Corp. of America v. Kafati
320 So. 2d 251 (Louisiana Court of Appeal, 1975)
Gremillion v. Mouledous
309 So. 2d 897 (Louisiana Court of Appeal, 1975)
Superior Oil Company v. Cox
307 So. 2d 350 (Supreme Court of Louisiana, 1975)
Crow Drilling & Producing Co. v. Hunt
226 So. 2d 487 (Supreme Court of Louisiana, 1969)