Jack V. Heard Contractors, Inc. v. A. L. Adams Construction Co.

271 S.E.2d 222, 155 Ga. App. 409, 1980 Ga. App. LEXIS 2604
CourtCourt of Appeals of Georgia
DecidedJune 27, 1980
Docket59774
StatusPublished
Cited by9 cases

This text of 271 S.E.2d 222 (Jack V. Heard Contractors, Inc. v. A. L. Adams Construction Co.) is published on Counsel Stack Legal Research, covering Court of Appeals of Georgia primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Jack V. Heard Contractors, Inc. v. A. L. Adams Construction Co., 271 S.E.2d 222, 155 Ga. App. 409, 1980 Ga. App. LEXIS 2604 (Ga. Ct. App. 1980).

Opinion

Quillian, Presiding Judge.

Jack V. Heard Contractors (hereinafter Heard), defendant below, appeals from the grant of a motion for partial summary judgment of the plaintiff — A. L. Adams Construction Company (hereinafter Adams), and the denial of its motion for summary judgment. Held:

1. The trial court granted plaintiff Adams’ motion for partial summary judgment that its contract with the defendant was a valid contract. This was not a final judgment and leaves the action pending below but is directly appealable under Code Ann. § 81A-156 (h) without a certificate of immediate review under Code Ann. § 6-701 (a) 2 (A).

[410]*4102. Defendant’s motion for partial summary judgment — which was denied, was appealed without a certificate for immediate review. The Supreme Court has held in a situation in which a grant of a partial summary judgment was appealed with a denial of a summary judgment that “the judgment granting partial summary judgment was appealable, but the judgment denying summary judgment was reviewable only by certificate of immediate review . . .” Thomas v. McGee, 242 Ga. 441 (1) (249 SE2d 242).

Executive Jet Sales v. Jet America, 242 Ga. 307 (248 SE2d 676), and Marathon &c. Realties v. Kalb, 244 Ga. 390 (260 SE2d 85), are distinguishable from the instant case. Although Executive Jet involved a denial of a motion to dismiss, and Marathon involved a denied of a motion for summary judgment — Marathon reversed Marietta Yamaha v. Thomas, 237 Ga. 840 (229 SE2d 753) — another denial of a motion for summary judgment issue, “based upon what [the Supreme] court held in Executive Jet. . .” 244 Ga. at 393. When Executive Jet and Marathon are construed in tandem they permit denial of a motion for summary judgment to be considered on appeal without a certificate for immediate review as both were cross appeals (as was Marietta Yamaha), and Executive Jet was specifically predicated upon that factual base as the court held that an appellee “may institute cross appeal... and... present for adjudication on the cross-appeal all errors or rulings adversely affecting him, and in no case shall the appellee be required to institute an independent appeal on his own right . . .” Executive Jet Sales v. Jet America, 242 Ga. 307-308, supra. That decision was further bottomed upon the reasoning that where the appeal of an appellant “is taken under any provision of paragraph (a) [of Code Ann. § 6-701] above, all judgments, rulings or orders rendered in the case which are raised on appeal, and which may affect the proceedings below, shall be reviewed and determined by the appellate court, without regard to the appealability of such judgment, ruling or order standing alone ...” 242 Ga. at 308.

Accordingly, as the grant of the plaintiffs motion for partial summary judgment in the instant case was not a cross appeal, but was appealable only under Code Ann. § 81A-156 (h) and not Code Ann. § 6-701 (a), Executive Jet and Marathon are inapposite, and Thomas v. McGee, 242 Ga. 441, supra, controls. The denial of the defendant’s motion for summary judgment cannot be considered without a certificate for immediate review and application to this court for permission to appeal. Therefore, the denial of defendant’s motion for summary judgment is not properly before us for review.

3. The defendant contends the trial court’s grant of plaintiffs partial motion for summary judgment was error. We do not agree.

[411]*411a. Adams was the prime contractor for the construction of a building in Aiken, South Carolina — the “Croft-House.” CharrDon, Inc. executed a contract with Adams which provided for the painting and wallcovering of the building. Thereafter, Char-Don transferred and assigned its rights under the contract to Heard — the defendant and appellant herein. Heard painted approximately one-half of the interior of the building before a controversy arose as to whether the contract required Heard to paint the exterior as well as the interior. Heard “took the position that there was no binding contract between the parties because there had been no meeting of minds, and further insisted that it would proceed no further with the painting of this project until such time as the parties entered into a valid and binding contract . . .” Adams refused Heard’s request and hired another subcontractor to finish the painting. Adams filed this action anticipating it would suffer damages. However, after paying the new subcontractor for its work, it remitted the unexpended sum of the total contract price to Heard — $4,000. Heard filed an answer and counterclaim for $17,945 — claimed to be due and owing for the work it accomplished prior to leaving the job.

The contract signed by Char-Don and assigned to Heard provided for the “Painting [and] Wallcovering” of Croft House, including “painting and vinyl wallcovering as detailed on the plans and in accordance with Sections ... 09900 ... of the specifications.” Under the Specifications, “Section09900 — Painting...,” Subsection 3.06 required: “Exterior Paint Schedule: A. FERROUS METAL (NEW): 1. Doors and Frames: [1 or 2 coats] B. FERROUS METAL (PREVIOUSLY PAINTED): [touch up or 1 coat]. C. GALVANIZED METAL: 1. Wearing Surfaces: [1 or 2 coats]. 2. Non-Wearing Surfaces [1 or 2 coats]: D. ALUMINUM: [1 or 2 coats]. E. STUCCO: 2 coats. F. CONCRETE MASONRY [see section 09800].”

Construing the provisions in the contract for “painting” in pari materia with the provisions in the “specifications,” under Section 09900 “Painting,” it was established that there was a requirement for “New surfaces to be painted” which included all “wood, drywall, concrete, concrete block, and stucco.” Further, the “exterior paint schedule” required “1 to 2 coats” of paint on exterior surfaces whose composition was “ferrous metal, galvanized metal, aluminum, stucco [and] concrete masonry.”

Accordingly, we disagree with defendant’s argument that “ [t]he dispute in this case deals with whether the exterior stucco walls of the project were to be painted.” This appeal, in accordance with defendant’s amended “Notice of Appeal” and “Enumeration of Error,” deals first with the grant of plaintiffs motion for partial summary judgment that there was a valid contract, and secondly, at [412]*412issue is whether any exterior painting was required — not whether “exterior stucco walls of the project were to be painted.” If any exterior painting was required by the contract, defendant’s argument that exterior stucco was not required to be painted misses the crucial issue — e.g. whether interior painting only was required or interior and exterior surfaces both were to be painted.

b. Defendant contends “there was a justifiable failure of the minds of the parties to meet on the question of the exterior painting, or at the least, there exists genuine issues of material fact about whether their minds met, and therefore it was error to grant appellee’s motion for partial summary judgment, ruling that the contract between the parties was valid.” We disagree.

It is essential to the validity of a contract that the minds of the contracting parties meet on the same subject matter, at the same time, and in the same sense. Ga. Sou. &c. R. Co. v. Adeeb, 15 Ga. App. 831 (1) (84 SE 323); Fonda Corp. v. Sou. Sprinkler, 144 Ga. App. 287, 291 (241 SE2d 256).

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Watson v. Sierra Contracting Corp.
485 S.E.2d 563 (Court of Appeals of Georgia, 1997)
Toncee, Inc. v. Thomas
466 S.E.2d 27 (Court of Appeals of Georgia, 1995)
Georgia Glass & Metal, Inc. v. Arco Chemical Co.
410 S.E.2d 142 (Court of Appeals of Georgia, 1991)
Wilkins v. Butler
369 S.E.2d 267 (Court of Appeals of Georgia, 1988)
Malin v. Servisco, Inc.
323 S.E.2d 278 (Court of Appeals of Georgia, 1984)
Kleiner v. First National Bank of Atlanta
97 F.R.D. 683 (N.D. Georgia, 1983)
Cox Broadcasting Corp. v. National Collegiate Athletic Ass'n
297 S.E.2d 733 (Supreme Court of Georgia, 1982)
Southeast Ceramics, Inc. v. Klem
275 S.E.2d 713 (Court of Appeals of Georgia, 1980)

Cite This Page — Counsel Stack

Bluebook (online)
271 S.E.2d 222, 155 Ga. App. 409, 1980 Ga. App. LEXIS 2604, Counsel Stack Legal Research, https://law.counselstack.com/opinion/jack-v-heard-contractors-inc-v-a-l-adams-construction-co-gactapp-1980.