Jack Eherenman D/B/A Eherenman Construction v. John M. Warren and Sandra L. Warren

CourtCourt of Appeals of Iowa
DecidedDecember 24, 2014
Docket13-1746
StatusPublished

This text of Jack Eherenman D/B/A Eherenman Construction v. John M. Warren and Sandra L. Warren (Jack Eherenman D/B/A Eherenman Construction v. John M. Warren and Sandra L. Warren) is published on Counsel Stack Legal Research, covering Court of Appeals of Iowa primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Jack Eherenman D/B/A Eherenman Construction v. John M. Warren and Sandra L. Warren, (iowactapp 2014).

Opinion

IN THE COURT OF APPEALS OF IOWA

No. 13-1746 Filed December 24, 2014

JACK EHERENMAN d/b/a EHERENMAN CONSTRUCTION, Plaintiff-Appellee,

vs.

JOHN M. WARREN and SANDRA L. WARREN, Defendants-Appellants. ________________________________________________________________

Appeal from the Iowa District Court for Black Hawk County, George L.

Stigler, Judge.

Homeowners appeal several aspects of a district court ruling foreclosing a

mechanic’s lien. AFFIRMED IN PART, REVERSED IN PART, AND

REMANDED.

Bradley M. Strouse and Bruce L. Gettman Jr. of Redfern, Mason, Larsen

& Moore, P.L.C., Cedar Falls, for appellants.

Paul W. Demro and Patrick C. Galles of Correll, Sheerer, Benson, Engels,

Galles & Demro, P.L.C., Cedar Falls, for appellee.

Heard by Vogel, P.J., and Vaitheswaran and Potterfield, JJ. 2

VAITHESWARAN, J.

Homeowners appeal several aspects of a district court ruling foreclosing a

mechanic’s lien.

I. Background Facts and Proceedings

John and Sandra Warren contracted with Jack Eherenman of Eherenman

Construction to substantially remodel a Waterloo home for their daughter and

son-in-law. The original contract price was $114,830. The contract was later

amended to provide that any “substantial changes to material or labor” would be

made by written change orders “signed and billed” biweekly and performed on a

“material plus labor” basis.

Eherenman prepared one change order to accommodate revisions John

wished to make. John signed certain paragraphs of the document but not others.

As the project progressed, the Warrens and their daughter and son-in-law asked

Eherenman to implement changes contained in the signed and unsigned portions

of the change order as well as changes not memorialized in any change order.

In time, a conflict arose concerning what work was encompassed within

the original contract and what work was not. The Warrens stopped paying

Eherenman.

Eherenman filed a mechanic’s lien for $66,781.42 plus interest and

followed it with a petition to foreclose the mechanic’s lien. After trial, the district

court entered judgment for Eherenman in the amount of $45,945 and dismissed

the Warrens’ counterclaim for breach of contract. The Warrens appealed.

II. Analysis

The Warrens contend: (A) Eherenman’s mechanic’s lien was not timely

filed, (B) Eherenman failed to substantially perform the contract, (C) their contract 3

did not provide for extra work unless authorized by change order, and (D) even if

Eherenman can recover, the district court incorrectly computed damages.

A. Timeliness of Filing

The Warrens claim Eherenman could enforce his mechanic’s lien only if it

was filed within ninety days of his last work. See Iowa Code §§ 572.8-11 (2013);

Carson v. Roediger, 513 N.W.2d 713, 715 (Iowa 1994). They assert Eherenman

performed his last work more than ninety days before the filing. The district court

found otherwise. The court’s finding is supported by Eherenman’s testimony. He

stated he “[c]lean[ed] up tools” more than ninety days before filing the lien so he

“could go to other jobs” pending clarification of what needed to be completed on

the Warrens’ project. However, he had his crew return to the dwelling within

ninety days to “start the insulation.” Because he performed work within ninety

days of the filing, we affirm the district court’s denial of the Warrens’ timeliness

objection.

B. Substantial Performance

To enforce a mechanic’s lien, a contractor must substantially perform the

work. Flynn Builders, L.C. v. Lande, 814 N.W.2d 542, 545-46 (Iowa 2012). “In

all contracts, however, ‘there is an implied term that the person for whom the

work is contracted to be done will not obstruct, hinder or delay the contractor,

but, on the contrary, will in all ways facilitate the performance of the work to be

done.’” Sheer Constr., Inc. v. W. Hodgman & Sons, Inc., 326 N.W.2d 328,

332 (Iowa 1982) (citation omitted).

The Warrens contend Eherenman did not substantially perform the

contract. Eherenman essentially concedes this point but invokes the hindrance 4

exception to the doctrine. He contends the Warrens and their daughter and son-

in-law “hindered the project and greatly slowed the progress of the work.”

The district court agreed with Eherenman, finding the Warrens did not

“pay[] for work performed per the contract and [did] not allow[] Eherenman

Construction to complete performance.” On our de novo review, we find support

for these findings. See Flynn Builders, 814 N.W.2d at 545 (setting forth the

scope of review). According to Eherenman, John Warren became concerned

about the cost of the project and curtailed payments to him. Eherenman stated,

“[T]here wasn’t a problem until John told me that he was not going to pay me or

the subs, that we were all too high. At that time obviously, I knew there was

going to be a problem.” When Warren stopped making payments, a number of

items had yet to be completed. Eherenman documented the incomplete work

and deducted $12,349.40 from his claim, adding an additional $1000 to the

deduction at a later date. There is no question Eherenman was on track to

complete the work but for John Warren’s decision to halt the project. We

conclude the hindrance exception to the substantial performance doctrine applied

to excuse Eherenman’s fulfillment of the contract. See id. at 547-48 (remanding

for determination of “whether lack of specific performance might be excused by

the conduct of the [home purchaser]”).

C. Extra Work by Change Order

The Warrens next contend Eherenman’s recovery was limited to additional

work authorized in the signed portions of the single written change order.

Eherenman counters that the change order requirement was never followed. As

this issue affects the amount of the damage award, we will address it. 5

“Generally, a builder may recover for extra work performed on a

construction project when ordered and agreed to by the parties and not covered

by the building contract.” Serv. Unlimited, Inc. v. Elder, 542 N.W.2d 855, 857

(Iowa Ct. App. 1995). Although a contract may require written change orders,

this requirement may be waived by the parties. Cent. Iowa Grading, Inc. v. UDE

Corp., 392 N.W.2d 857, 860 (Iowa Ct. App. 1986).

The district court essentially found a waiver. According to the court,

Eherenman received verbal directions from all members of the family. The court

characterized these directions as work order changes, “which caused

Eherenman Construction, on occasions, to tear out existing work and re-do that

same work solely to comply with a new work directive received from one or more

of [them.]” The court determined Eherenman was more credible than the

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Service Unlimited, Inc. v. Elder
542 N.W.2d 855 (Court of Appeals of Iowa, 1995)
Sheer Construction, Inc. v. W. Hodgman & Sons, Inc.
326 N.W.2d 328 (Supreme Court of Iowa, 1982)
Central Iowa Grading, Inc. v. Ude Corp.
392 N.W.2d 857 (Court of Appeals of Iowa, 1986)
Carson v. Roediger
513 N.W.2d 713 (Supreme Court of Iowa, 1994)
Flynn Builders, L.C. v. Matthew P. Lande and Chris Lande
814 N.W.2d 542 (Supreme Court of Iowa, 2012)

Cite This Page — Counsel Stack

Bluebook (online)
Jack Eherenman D/B/A Eherenman Construction v. John M. Warren and Sandra L. Warren, Counsel Stack Legal Research, https://law.counselstack.com/opinion/jack-eherenman-dba-eherenman-construction-v-john-m-iowactapp-2014.