Jack Eherenman D/B/A Eherenman Construction v. John M. Warren and Sandra L. Warren

Court of Appeals of Iowa·Decided December 24, 2014·No. 13-1746·Published

Opinion

IN THE COURT OF APPEALS OF IOWA

No. 13-1746

Filed December 24, 2014

JACK EHERENMAN d/b/a EHERENMAN CONSTRUCTION, Plaintiff-Appellee,

vs.

JOHN M. WARREN and SANDRA L. WARREN, Defendants-Appellants.

Appeal from the Iowa District Court for Black Hawk County, George L.

Stigler, Judge.

Homeowners appeal several aspects of a district court ruling foreclosing a mechanic’s lien. AFFIRMED IN PART, REVERSED IN PART, AND REMANDED.

Bradley M. Strouse and Bruce L. Gettman Jr. of Redfern, Mason, Larsen & Moore, P.L.C., Cedar Falls, for appellants.

Paul W. Demro and Patrick C. Galles of Correll, Sheerer, Benson, Engels, Galles & Demro, P.L.C., Cedar Falls, for appellee.

Heard by Vogel, P.J., and Vaitheswaran and Potterfield, JJ.

VAITHESWARAN, J.

Homeowners appeal several aspects of a district court ruling foreclosing a mechanic’s lien. I. Background Facts and Proceedings John and Sandra Warren contracted with Jack Eherenman of Eherenman Construction to substantially remodel a Waterloo home for their daughter and son-in-law. The original contract price was $114,830. The contract was later amended to provide that any “substantial changes to material or labor” would be made by written change orders “signed and billed” biweekly and performed on a “material plus labor” basis.

Eherenman prepared one change order to accommodate revisions John wished to make. John signed certain paragraphs of the document but not others. As the project progressed, the Warrens and their daughter and son-in-law asked Eherenman to implement changes contained in the signed and unsigned portions of the change order as well as changes not memorialized in any change order.

In time, a conflict arose concerning what work was encompassed within the original contract and what work was not. The Warrens stopped paying Eherenman.

Eherenman filed a mechanic’s lien for $66,781.42 plus interest and followed it with a petition to foreclose the mechanic’s lien. After trial, the district court entered judgment for Eherenman in the amount of $45,945 and dismissed the Warrens’ counterclaim for breach of contract. The Warrens appealed. II. Analysis The Warrens contend: (A) Eherenman’s mechanic’s lien was not timely filed, (B) Eherenman failed to substantially perform the contract, (C) their contract

did not provide for extra work unless authorized by change order, and (D) even if Eherenman can recover, the district court incorrectly computed damages.

A. Timeliness of Filing The Warrens claim Eherenman could enforce his mechanic’s lien only if it was filed within ninety days of his last work. See Iowa Code §§ 572.8-11 (2013); Carson v. Roediger, 513 N.W.2d 713, 715 (Iowa 1994). They assert Eherenman performed his last work more than ninety days before the filing. The district court found otherwise. The court’s finding is supported by Eherenman’s testimony. He stated he “[c]lean[ed] up tools” more than ninety days before filing the lien so he “could go to other jobs” pending clarification of what needed to be completed on the Warrens’ project. However, he had his crew return to the dwelling within ninety days to “start the insulation.” Because he performed work within ninety days of the filing, we affirm the district court’s denial of the Warrens’ timeliness objection.

B. Substantial Performance To enforce a mechanic’s lien, a contractor must substantially perform the work. Flynn Builders, L.C. v. Lande, 814 N.W.2d 542, 545-46 (Iowa 2012). “In all contracts, however, ‘there is an implied term that the person for whom the work is contracted to be done will not obstruct, hinder or delay the contractor, but, on the contrary, will in all ways facilitate the performance of the work to be done.’” Sheer Constr., Inc. v. W. Hodgman & Sons, Inc., 326 N.W.2d 328, 332 (Iowa 1982) (citation omitted).

The Warrens contend Eherenman did not substantially perform the contract. Eherenman essentially concedes this point but invokes the hindrance

exception to the doctrine. He contends the Warrens and their daughter and son- in-law “hindered the project and greatly slowed the progress of the work.”

The district court agreed with Eherenman, finding the Warrens did not “pay[] for work performed per the contract and [did] not allow[] Eherenman Construction to complete performance.” On our de novo review, we find support for these findings. See Flynn Builders, 814 N.W.2d at 545 (setting forth the scope of review). According to Eherenman, John Warren became concerned about the cost of the project and curtailed payments to him. Eherenman stated, “[T]here wasn’t a problem until John told me that he was not going to pay me or the subs, that we were all too high. At that time obviously, I knew there was going to be a problem.” When Warren stopped making payments, a number of items had yet to be completed. Eherenman documented the incomplete work and deducted $12,349.40 from his claim, adding an additional $1000 to the deduction at a later date. There is no question Eherenman was on track to complete the work but for John Warren’s decision to halt the project. We conclude the hindrance exception to the substantial performance doctrine applied to excuse Eherenman’s fulfillment of the contract. See id. at 547-48 (remanding for determination of “whether lack of specific performance might be excused by the conduct of the [home purchaser]”).

C. Extra Work by Change Order The Warrens next contend Eherenman’s recovery was limited to additional work authorized in the signed portions of the single written change order. Eherenman counters that the change order requirement was never followed. As this issue affects the amount of the damage award, we will address it.

“Generally, a builder may recover for extra work performed on a construction project when ordered and agreed to by the parties and not covered by the building contract.” Serv. Unlimited, Inc. v. Elder, 542 N.W.2d 855, 857 (Iowa Ct. App. 1995). Although a contract may require written change orders, this requirement may be waived by the parties. Cent. Iowa Grading, Inc. v. UDE Corp., 392 N.W.2d 857, 860 (Iowa Ct. App. 1986).

The district court essentially found a waiver. According to the court, Eherenman received verbal directions from all members of the family. The court characterized these directions as work order changes, “which caused Eherenman Construction, on occasions, to tear out existing work and re-do that same work solely to comply with a new work directive received from one or more of [them.]” The court determined Eherenman was more credible than the Warrens on this issue. We give weight to this credibility finding because “the trial court is in a more advantageous position than we to put credence where it belongs.” Flynn Builders, 814 N.W.2d at 545. This is particularly true where the court’s findings are supported by extensive record evidence.

Eherenman testified he discussed changes with the family by phone and e-mail. Verbal or unsigned change orders were paid “about half a dozen” times, “at least.” Eherenman cited an unsigned order to remove the fireplace, which was billed and paid by Sandra Warren. According to him, billings were submitted to the Warrens “[p]robably every week or two, maybe three weeks, . . . certain invoices would come as the draws were needed, so as we would get things done.” With respect to change orders, Eherenman testified “if that work would be completed, then I would invoice out for that.” Because the Warrens waived the right to have all changes approved by written change order, Eherenman was

entitled to compensation for work performed outside the four corners of the contract or the signed paragraphs of the written change order.

D. Damages Calculation The district court calculated damages as follows:

Free access — add to your briefcase to read the full text and ask questions with AI

Jack Eherenman D/B/A Eherenman Construction v. John M. Warren and Sandra L. Warren, (iowactapp 2014).

Jack Eherenman D/B/A Eherenman Construction v. John M. Warren and Sandra L. Warren (Jack Eherenman D/B/A Eherenman Construction v. John M. Warren and Sandra L. Warren) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

Service Unlimited, Inc. v. Elder
542 N.W.2d 855 (Court of Appeals of Iowa, 1995)
Sheer Construction, Inc. v. W. Hodgman & Sons, Inc.
326 N.W.2d 328 (Supreme Court of Iowa, 1982)
Central Iowa Grading, Inc. v. Ude Corp.
392 N.W.2d 857 (Court of Appeals of Iowa, 1986)
Carson v. Roediger
513 N.W.2d 713 (Supreme Court of Iowa, 1994)
Flynn Builders, L.C. v. Matthew P. Lande and Chris Lande
814 N.W.2d 542 (Supreme Court of Iowa, 2012)