J.A. Jones Management Services v. Federal Aviation Administration

225 F.3d 761, 343 U.S. App. D.C. 245, 2000 U.S. App. LEXIS 23972, 2000 WL 1345933
CourtCourt of Appeals for the D.C. Circuit
DecidedSeptember 29, 2000
Docket00-1023
StatusPublished
Cited by9 cases

This text of 225 F.3d 761 (J.A. Jones Management Services v. Federal Aviation Administration) is published on Counsel Stack Legal Research, covering Court of Appeals for the D.C. Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
J.A. Jones Management Services v. Federal Aviation Administration, 225 F.3d 761, 343 U.S. App. D.C. 245, 2000 U.S. App. LEXIS 23972, 2000 WL 1345933 (D.C. Cir. 2000).

Opinion

Opinion for the Court filed by Circuit Judge TATEL.

TATEL, Circuit Judge:

A disappointed bidder challenges the Federal Aviation Administration’s award of a contract. Reviewing the FAA’s decision pursuant to the highly deferential arbitrary and capricious standard, we deny the petition for review.

I

Following a competitive bidding process, the FAA awarded Wackenhut Services, Inc., intervenor herein, a $5 million contract to provide operations and maintenance services at the William Hughes Technical Center, a 5059 acre facility in New Jersey that serves as the national scientific test base for FAA research, de *763 velopment, and acquisition programs. Pursuant to FAA procedures, petitioner J.A. Jones Management, an unsuccessful bidder, protested the award to the agency’s Office of Dispute Resolution for Acquisition (“ODRA”). In that protest, Jones claimed both that the agency failed to follow its own procedures and that Wackenhut failed to meet the contract solicitation’s substantive requirements. After reviewing the evidence and making factual findings, ODRA recommended that Jones’s protest be denied. Adopting ODRA’s findings and recommendations, the FAA Administrator issued a final order awarding the contract to Wackenhut.

The solicitation required the contract to be awarded to the responsible, low-priced offeror deemed acceptable in each of several listed technical areas. The agency contracting officer, assisted by a contract specialist, oversaw the procurement decision. As outlined in the solicitation, an eight-member Technical Evaluation Board following a Technical Evaluation Plan was responsible for determining whether offers met the technical requirements. According to the Plan, if the Board unanimously decided that an offer failed in any one area, the offeror would be disqualified from further consideration. All agree that if the Board was not unanimous, the contracting officer would retain discretion to award the contract to the offeror.

At a July 26, 1999 meeting, the Technical Evaluation Board unanimously disqualified Wackenhut, stating in its report that the company had failed in two specific areas: demonstrating how it would remove snow from the facility and proposing an electrical engineer with the required work experience. Reviewing the Board decision, the contract specialist discovered that the individual evaluation sheet of one of the Board members — Evaluator F — indicated that he had given Wackenhut a passing grade in both areas. In particular, referring to the snow removal task, Evaluator F wrote on his scoring sheet: “I think this was addressed adequately.” When the contract specialist asked for an explanation, the Board chair pointed out that, despite his individual assessment, Evaluator F had signed the report disqualifying Wackenhut in the two areas. The chair also told the contract specialist that Evaluator F had agreed to change his individual scoring sheet to reflect the Board’s evaluation. As ODRA later found, however, Evaluator F failed to do so.

Unsatisfied, the contract specialist arranged a second Board meeting to discuss the inconsistency between the Board report and Evaluator F’s individual scoring sheet. At that meeting, which occurred on August 12, Evaluator F reiterated his belief in the acceptability of Wackenhut’s offer and refused to change his evaluation sheet. During a break in the meeting, Evaluator F, believing that his unwillingness to change his assessment of Wacken-hut had become an obstacle to agreement, telephoned the contract specialist and asked to be removed from the Board. The contract specialist denied his request.

After the break, the chair called the contract specialist to inform her that the Board was still discussing Wackenhut’s proposal. The contract specialist directed the chair to postpone any further action until she finished discussing the matter with the contracting officer and agency counsel. During that discussion, the three found Wackenhut’s offer technically acceptable and decided not to follow the Board’s assessment. Learning of this decision, the chair reconvened the Board. Under the circumstances, the Board decided it was pointless to meet further. The contracting officer later determined that Wackenhut was the responsible, low-priced offeror deemed acceptable in all of the solicitation’s technical areas. Wackenhut was awarded the contract.

After hearing testimony about these events, ODRA concluded that the contracting officer properly followed agency procedures in awarding the contract to Wacken-hut. Central to the dispute in this case, ODRA found that the Board’s decision had *764 not been unanimous and that Wackenhut had therefore not been disqualified. This determination rested primarily on the events of the August 12 meeting — in particular, Evaluator F’s continued refusal to agree that Wackenhut was unacceptable. At one point in its report, ODRA found that “[i]t is undisputed that, at the conclusion of the final Board meeting on August 12, the Board, in a non-unanimous vote, found Wackenhut’s proposal unacceptable.” Reviewing all of the evidence, ODRA concluded that the meeting “ended in a non-unanimous Board decision.”

Jones, the unsuccessful bidder, now challenges the award of the contract to Wackenhut. Jones claims that, contrary to ODRA’s finding, no non-unanimous vote occurred at the end of the August 12 meeting. As Jones views the events of August 12, the Board reached no decision at all. Accordingly, Jones argues, the contracting officer was bound by the July 26 unanimous disqualification of Wackenhut. Focusing on three of the solicitation’s technical requirements, Jones also challenges the contracting officer’s determination that Wackenhut was qualified. We consider each claim in turn.

II

We review the FAA’s non-unanimity finding under the familiar arbitrary and capricious standard. See 5 U.S.C. § 706(2)(A). Under this standard, we “may reverse only if the agency’s decision is not supported by substantial evidence, or the agency has made a clear error in judgment.” Kisser v. Cisneros, 14 F.3d 615, 619 (D.C.Cir.1994); see also 49 U.S.C. § 46110(c) (FAA “[fjindings of fact..., if supported by substantial evidence, are conclusive.”). Jones fails to appreciate the result this highly deferential standard so clearly dictates.

Jones argues that the contracting officer lacked discretion to disregard the Board’s disqualification of Wackenhut. Because Jones concedes that the contracting officer had discretion to disregard a non-unanimous Board, its claim necessarily turns on its assertion that the Board was in fact unanimous. To prevail, Jones must demonstrate that the agency’s determination to the contrary did not rest on substantial evidence. Yet as ODRA found, not only did Evaluator F declare Wacken-hut acceptable on his individual scoring sheet (which he never altered despite his apparent promise to do so), but at the August 12 meeting, he again refused to change his evaluation. This evidence is more than enough to sustain the agency’s finding of nonunanimity.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Doe v. Lieberman
District of Columbia, 2021
Strait Shipbrokers Pte. Ltd. v. Blinken
District of Columbia, 2021
Spirit Airlines, Inc. v. DOT
997 F.3d 1247 (D.C. Circuit, 2021)
Bean Dredging, LLC v. United States
773 F. Supp. 2d 63 (District of Columbia, 2011)
Breen v. Peters
474 F. Supp. 2d 1 (District of Columbia, 2007)
Multimax, Inc. v. Federal Aviation Administration
231 F.3d 882 (D.C. Circuit, 2000)

Cite This Page — Counsel Stack

Bluebook (online)
225 F.3d 761, 343 U.S. App. D.C. 245, 2000 U.S. App. LEXIS 23972, 2000 WL 1345933, Counsel Stack Legal Research, https://law.counselstack.com/opinion/ja-jones-management-services-v-federal-aviation-administration-cadc-2000.