J&A Concrete Corp. v. Dobco Inc.

District Court, S.D. New York·Decided August 6, 2026·No. 1:21-cv-11097·Unknown

Opinion

UNITED STATES DISTRICT COURT SOUTHERN DISTRICT OF NEW YORK ─────────────────────────── J&A CONCRETE CORP., 21-cv-11097 (JGK) Plaintiff,

Opinion and Order - against - DOBCO INC., Defendant. ─────────────────────────── John G. Koeltl, District Judge: This case concerns a payment dispute between a general contractor, Dobco Inc. (“Dobco”), and a subcontractor, J&A Concrete Corporation (“J&A”). Dobco alleges that J&A abandoned its job as the concrete subcontractor on the 40th Precinct Police Station and that, as a result, Dobco was forced to use its own resources to complete the work. This Court has already determined that J&A breached its subcontract with Dobco by abandoning the job. Even though Dobco has received a $3.9 million payment on a performance bond securing J&A’s performance, Dobco contends that J&A is responsible for additional damages that Dobco has sustained. Dobco has the burden of proving its dam- ages with reasonable certainty. J&A asserted six claims against Dobco; Dobco in turn asserted counter- claims for breach of contract and declaratory relief against J&A. After the parties cross-moved for summary judgment, the Court denied J&A’s motion, entered summary judgment for Dobco on its breach-of-contract counterclaim as to liability only, and dismissed J&A’s claims for breach of contract and equitable relief. J&A Concrete Corp. v. Dobco Inc., No. 21-cv-11097, 2025 WL

605252 (S.D.N.Y. Feb. 24, 2025); see also ECF No. 153. The sole remaining issue after the Court resolved the motions for summary judgment was the measure of damages Dobco suffered as a result of J&A’s breach of contract. The Court held a non-jury trial from January 20, 2026 through Janu- ary 27, 2026. Having reviewed the evidence and assessed the credibility of the witnesses, the Court now makes the following findings of fact and reaches the following conclusions of law pursuant to Federal Rule of Civil Procedure 52.

FINDINGS OF FACT I. The Parties 1. At all relevant times, including the commencement of this action, Dobco was a corporation organized under the laws of New Jersey with its prin- cipal place of business at 1 Geoffrey Way, Wayne, New Jersey 07470. Joint Pretrial Order ¶ 3, ECF No. 204.

2. At all relevant times, including the commencement of this action, J&A was a corporation organized under the laws of New York with its principal place of business at 1676 Washington Avenue, Bohemia, New York 11716. Id. 3. The damages sought by Dobco on its breach-of-contract counter- claim exceed $75,000, exclusive of interest and costs. See Ex. D-3 (Subcontract price of $3,900,000). II. The Witnesses 4. The Court heard live testimony from five witnesses: Daniel Mlad- enovic, Dobco’s president; Justin Johnson, Dobco’s Project Executive; Antonio

Martins, J&A’s president; Robert Valentin, Dobco’s Project Scheduler; and Fe- ras A. Taher, J&A’s designated expert on scheduling in the construction industry. 5. In addition, the deposition testimony of Peter Apospolidis, a repre- sentative of Arch Insurance Company, was read into the record. Tr. 468:5–20. 6. In making the findings that follow, the Court has considered each witness’s demeanor, the plausibility and internal consistency of the testimony, the witness’s interest in the outcome, and the consistency of the testimony with

the contemporaneous documentary record. Where testimony conflicted with contemporaneous documents, the Court has generally credited the documents. III. The 40th Precinct Police Station Project, the Prime Contract, and the Project Specifications 7. Dobco is a general contractor. Tr. 417:1–2; Ex. D-4.1 8. On March 8, 2018, Dobco entered into a contract (the “Prime Con- tract”) with the New York City Department of Design and Construction (the “Owner”) to construct the 40th Precinct Police Station, located in the Bronx, New York (the “Project”). See Joint Pretrial Order ¶ 7(a). 9. The value of the Prime Contract was $57,700,000. Ex. D-4; Tr. 260:11–15.

1 “Tr.” refers to the trial transcript. “Ex. D” refers to Dobco’s trial exhibits. 10. The Project architect was Bjarke Ingels Group (“BIG”). See Joint

Pretrial Order ¶ 7(b). 11. The Project construction manager was The LiRo Group (“LiRo”). See id. ¶ 7(c). 12. As the Owner’s construction manager, LiRo was the primary liai- son between Dobco and the Owner. Tr. 36:25–37:3. 13. The Prime Contract included and incorporated by reference the City of New York Standard Construction Contract (the “Standard Contract”). Ex. D-1; Tr. 261:1–12.

14. Paragraph 1.2(A)(9) of Section 03 30 00 “Cast in Place Concrete” of the Project Specifications provides: Placing in the forms all inserts, anchors, anchor bolts, bearing plates, and the like furnished by other con- tractors for casting into the concrete and cleaning of same after stripping of forms. Ex. D-5 at 1. 15. Paragraph 3.7(A) of Section 03 30 00 “Cast in Place Concrete” of the Project Specifications provides: General: Set and build into work anchorage devices and other embedded items required for other work that is attached to, or supported by, cast-in-place con- crete. Use setting drawings, diagrams, instructions, and directions provided by suppliers of items to be at- tached thereto. Id. at 25. IV. The Subcontract 16. On May 31, 2018, Dobco entered into a subcontract (the “Subcon- tract”) with J&A, pursuant to which J&A agreed to perform certain concrete

work on the Project in exchange for $3.9 million. See Joint Pretrial Order ¶ 7(d); Ex. D-3 §§ 1.1, 10.1. V. The Performance Bond 17. As a condition of the Subcontract, J&A was required to obtain a performance bond running to Dobco’s benefit that guaranteed the performance of J&A’s work under the Subcontract. See Ex. D-3 § 12.2.

18. Arch Insurance Company (“Arch”), as surety, together with J&A, as principal, issued a performance bond bearing bond number SU1144064 (the “Bond”) in favor of Dobco as obligee in connection with the Subcontract. See Joint Pretrial Order ¶ 7(g); Ex. D-10. The penal sum of the Bond was $3,900,000. Ex. D-10 at 1. 19. The Bond provided that in the event J&A fails to perform under the Subcontract, Dobco could declare J&A in default, in which case Arch would be required either to (1) arrange for J&A to complete the Subcontract; (2) un- dertake to perform and complete the Subcontract itself; or (3) obtain bids or

negotiated proposals from qualified contractors acceptable to Dobco for perfor- mance and completion of the Contract. Id. ¶ 4. 20. The Bond further provided that if Arch was unable to perform un- der paragraph 4 of the Bond in the event J&A defaulted and Dobco completed the Subcontract at a cost that “exceeds the Balance of the Contract Price,” Arch would be required to pay Dobco “such excess” up to the penal sum of the Bond. Id. {| 6. VI. The Owner Issued a Pre-Default Notice to Dobco 21. During the early stages of the Project, the Owner, based on delays on the Project, issued a pre-default notice to Dobco’s performance bond sure- ties, Liberty Mutual Insurance Company (“Liberty”) and Arch. Tr. 268:9—24. 22. Liberty and Arch in turn retained a consulting company, JS Held LLC to assist with getting the Project back on schedule. Id. 23. The issues leading the Owner to issue Dobco a pre-default notice were fully resolved by early 2021. Tr. 268:25—269:2. VII. The Change Orders 24. During the Project, Dobco and J&A agreed to several change or- ders resulting in an adjusted Subcontract price of $4,180,807.03:

Free access — add to your briefcase to read the full text and ask questions with AI

J&A Concrete Corp. v. Dobco Inc., (S.D.N.Y. 2026).

J&A Concrete Corp. v. Dobco Inc. (J&A Concrete Corp. v. Dobco Inc.) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related