J&A Concrete Corp. v. Dobco Inc.

CourtDistrict Court, S.D. New York
DecidedFebruary 24, 2025
Docket1:21-cv-11097
StatusUnknown

This text of J&A Concrete Corp. v. Dobco Inc. (J&A Concrete Corp. v. Dobco Inc.) is published on Counsel Stack Legal Research, covering District Court, S.D. New York primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
J&A Concrete Corp. v. Dobco Inc., (S.D.N.Y. 2025).

Opinion

UNITED STATES DISTRICT COURT SOUTHERN DISTRICT OF NEW YORK ──────────────────────────────────── J&A CONCRETE CORP.,

Plaintiff, 21-cv-11097 (JGK)

- against - MEMORANDUM OPINION AND ORDER DOBCO INC., ET AL.,

Defendants. ──────────────────────────────────── JOHN G. KOELTL, District Judge:

This case concerns a payment dispute between a general contractor and a subcontractor, and related indemnification claims asserted by a surety company against the subcontractor. The plaintiff, J&A Concrete Corporation (“J&A”), the subcontractor, asserted ten claims against the defendants, Dobco Inc. (“Dobco”), the general contractor, and Arch Insurance Company (“Arch”), which issued a performance bond on J&A’s behalf and a payment bond on Dobco’s behalf. Dobco asserted counterclaims against J&A and a crossclaim against Arch. Arch asserted counterclaims against J&A and J&A’s contractual indemnitors (the “Indemnitors”) and a crossclaim against Dobco. Before the Court are cross-motions for summary judgment by J&A and Dobco. For the following reasons, J&A’s motion is denied, and Dobco’s motion is granted in part and denied in part. I. The following facts are based on the parties’ Local Civil Rule 56.1 statements and supporting papers, and are undisputed unless otherwise noted. A.

In March 2018, Dobco entered into a contract (the “Contract”) with the New York City Department of Design and Construction (the “Owner”), pursuant to which Dobco agreed to provide general contractor construction services for the 40th Precinct Police Station (the “Project”), located in the Bronx, New York. Dobco Rule 56.1 Statement ¶ 1, ECF No. 120; J&A Rule 56.1 Statement ¶ 1, ECF No. 116-1. On May 31, 2018, Dobco entered into a subcontract (the “Subcontract”) with J&A, pursuant to which J&A agreed to provide materials and labor for certain concrete construction work for

the Project. Dobco Rule 56.1 Statement ¶ 2; J&A Rule 56.1 Statement ¶ 3. In relevant part, section 8.1.5 of the Subcontract required J&A to “provide all labor, equipment and tools to coordinate and install all required embedded material supplied by others including but not limited to; anchor bolts, base plates, sleeves, etc. in accordance with the Subcontract Documents including, but not limited to, plans, specifications and addenda.” Dobco Rule 56.1 Statement ¶ 11; Subcontract at 16, Ex. F to Wagner Decl., ECF No. 110-6. Section 1.1 of the Subcontract incorporated by reference the entire Contract, modifications to the Contract, documents listed in Article 15 of the Subcontract, and modifications to

the Subcontract issued after the execution of the Subcontract (“Modifications”). Subcontract at 2. Section 1.4 described a Modification as “a written amendment to this [Subcontract] signed by both parties, or as otherwise described in, and in accordance with the provisions of, Article 5.” Id. Section 5.1 provided: The Contractor reserves the right, from time to time, whether the Work or any part thereof shall or shall not have been completed, to make changes, modifications, additions and/or omissions in the Work as it may deem necessary, upon written order to the Subcontractor (collectively referred to in this Agreement as “Modifications”). The value of the Work to be changed, added or omitted shall be stated in said written order and shall be added to or deducted from the Price. . . . Should the parties hereto be unable to agree as to the value of the Modification, the Subcontractor shall proceed with the Work promptly under the written order of the Contractor which order the stated value of the Work shall be omitted, and the determination of the value of the Work shall be referred to the Architect or, if required by the Prime Contract, the Owner, whose decision shall, at the Contractor’s election, be final and binding upon the Subcontractor. All Modifications in the Work ordered in writing by Contractor shall be deemed to be a part of the Work hereunder and shall be performed and furnished in strict accordance with all the terms and provisions of this Agreement and the other Contract Documents. Id. at 11–12. Section 6.1.1 required all other claims and disputes related to the Subcontract to be addressed through “mediation as a condition precedent to arbitration or the institution of legal

or equitable proceedings by either party.” Id. at 12. Section 6.2.4 required J&A to “continue to perform all of its work and/or alleged extra work pending final resolution” of any claim that was the subject of mediation or binding dispute resolution. Id. at 13. Pursuant to section 7.1, J&A could terminate the Subcontract for “nonpayment of amounts due under this Subcontract for 60 days or longer.” Id. Section 7.1 continued: In the event of such termination by the Subcontractor for any reason which is not the fault of the Subcontractor, . . . the Subcontractor shall be entitled to recover from the Contractor payment for Work executed and for proven loss with respect to materials, equipment, tools and construction equipment and machinery, including reasonable overhead, profit and damages. Id. Article 11 of the Subcontract governed the payment process. Section 11.1.3 stated: Provided an Application for Payment is received by the Contractor not later than the 15th day of a month, the Contractor shall include the Subcontractor’s Work covered by that application in the next Application for Payment which the Contractor is entitled to submit to the Architect. The Contractor shall pay the Subcontractor each progress payment no later than seven (7) business days after the Contractor receives payment from the Owner unless the Contractor asserts any offset or claim to such payments otherwise to be made to the Subcontractor.

Id. at 17. Section 11.1.7.1 provided that the amount of each progress payment should first include: .1 That portion of the Subcontract Sum properly allocable to completed Work; .2 That portion of the Subcontract Sum properly allocable to materials and equipment delivered and suitably stored at the site by the Subcontractor for subsequent incorporation in the Subcontractor’s Work . . . ; and .3 The amount, if any, for changes in the Work that are not in dispute and have been properly authorized by the Contractor, to the same extent provided in the Prime Contract, pending a final determination by the Contractor of the cost of changes in the Subcontractor’s Work, even though the Subcontract Sum has not yet been adjusted. Id. at 18. Section 11.1.7.2 provided that the amount of each progress payment should then be reduced, in relevant part, by: .2 The amount, if any, for Work that remains uncorrected and for which the Contractor has previously withheld or nullified, in whole or in part, a Certificate for Payment for a cause that is the fault of the Subcontractor; .3 For Work performed or defects discovered since the last payment application, any amount for which the Contractor may withhold payment in whole or in part, for a cause that is the fault of the Subcontractor . . . . Id. One of the documents identified in the Appendix in Article 15 of the Subcontract, incorporated by reference pursuant to section 1.1, was the Procedure for Applications for Payment (the “Application Procedure”). Id. at 32. The Application Procedure set forth the following requirements for submitting applications for progress payments: The subcontractor shall prepare Payment Application on AIA G702 format and submit it to the Contractor by the 15th of the month for approval. After Subcontractor receives approval, original executed copy of the Application for Payment shall be submitted to the Contractor with the following attachments: 1. Transmittal Letter 2. Checklist for Payments 3. Application and Certificate for Payment AIA G702 and AIA G703 executed and notarized . . . 5. Subcontractor’s executed and notarized Partial Release, Waiver and Subcontractor’s Affidavit of Payment; . . . .

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Anderson v. Liberty Lobby, Inc.
477 U.S. 242 (Supreme Court, 1986)
Ying Jing Gan v. The City Of New York
996 F.2d 522 (Second Circuit, 1993)
Consarc Corporation v. Marine Midland Bank, N.A.
996 F.2d 568 (Second Circuit, 1993)
Oppenheimer & Co. v. Oppenheim, Appel, Dixon & Co.
660 N.E.2d 415 (New York Court of Appeals, 1995)
Corsello v. Verizon New York, Inc.
967 N.E.2d 1177 (New York Court of Appeals, 2012)
Clark-Fitzpatrick, Inc. v. Long Island Rail Road
516 N.E.2d 190 (New York Court of Appeals, 1987)
Mezzacappa Bros. v. City of New York
29 A.D.3d 494 (Appellate Division of the Supreme Court of New York, 2006)
Laur & Mack Contracting Co. v. Cienzo
274 A.D.2d 960 (Appellate Division of the Supreme Court of New York, 2000)
Kellett's Well Boring, Inc. v. City of New York
292 A.D.2d 179 (Appellate Division of the Supreme Court of New York, 2002)
Harsco Corp. v. Segui
91 F.3d 337 (Second Circuit, 1996)
City of Perry v. Procter & Gamble Co.
188 F. Supp. 3d 276 (S.D. New York, 2016)
Culwick v. Wood
384 F. Supp. 3d 328 (E.D. New York, 2019)

Cite This Page — Counsel Stack

Bluebook (online)
J&A Concrete Corp. v. Dobco Inc., Counsel Stack Legal Research, https://law.counselstack.com/opinion/ja-concrete-corp-v-dobco-inc-nysd-2025.