J. Weller Co. v. Washington Gordon & Co.

14 Ohio C.C. Dec. 407, 7 Ohio C.C. (n.s.) 303
CourtOttawa Circuit Court
DecidedJanuary 15, 1903
StatusPublished

This text of 14 Ohio C.C. Dec. 407 (J. Weller Co. v. Washington Gordon & Co.) is published on Counsel Stack Legal Research, covering Ottawa Circuit Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
J. Weller Co. v. Washington Gordon & Co., 14 Ohio C.C. Dec. 407, 7 Ohio C.C. (n.s.) 303 (Ohio Super. Ct. 1903).

Opinion

HULL, J.

The defendant in error was the plaintiff below and brought its action against the J. Weller Company, to recover $700, with interest, which it claimed the J. Weller Company owed it, as a balance due for furnishing the material and constructing a certain building in the village of Oak Harbor, Ottawa county. The contract was made by correspondence, and is set forth in the petition. The answer admits the correspondence as set forth in the petition ; but avers that the $700 was fully paid by transferring to Gordon & Company a certain order for $700 on the “ citizens committee,” so called, of Oak Harbor. That order was given by the J. Weller Company to Washington Gordon & Company ; and the question in the case is whether it was accepted under the contract, by Gordon & Company, as payment of $700, or whether that was only conditional, and payment not having been made of the order and there being no funds wherewith to pay it, whether Gordon & Compan3r had the right to sue for and recover the $700. There are also somfe questions made in the case as to the admission of evidence, and especially as to the admission of some evidence which, it is claimed, varied the terms of the written contract between the parties.

It appears from the record that the J. Weller Company, in the year 1898, had built a building, and were carrying on business in Oak Harbor-They were conducting a pickling factory, and, in 1899, the3>- contemplated building a canning factory and desired the citizens of Oak Harbor to contribute toward that enterprise, and a meeting was held at which were present several citizens, just how many does not appear, and one of the members of the J. Weller Company was also present, and one of the firm, Mr. Kilmer, of Gordon & Company. Mr. Weller stated at the meeting that they would build a canning factory if the citizens would contribute $700 toward it. No formal action was taken, but several, or some, at least, of those present stated that the sum would be raised, one saying, “ We will raise the amount; there will be no doubt about it; ” another “ We will raise it.” Similar expressions were used by others, and a committee was appointed to solicit subscriptions.

Soon after that Gordon & Company solicited from the Weller Company the contract for building the building and made a bid for it along with others, and the correspondence then occurred between the parties which constitutes the contract in this case. Gordon & Company wrote to the J. Weller Company, as follows, under date, of May 12, 1899:

[409]*409“ Oak Harbor, Ohio, May 12,1899.
“ The J. Weller Company,
“ Cincinnati, Ohio.
“Gentlemen : We will furnish the lumber for canning factory, as per bill submitted by you, for $975. We will furnish lumber for erecting buildiug complete as per your letter of April 29, for $1,054.60, and will erect same for you, furnishing everything necessary according to plans, for $415.
“ Respectfully submitted,
“W. Gordon & Co.”

On the following day, May 13, the J. Weller Co. answered that letter, as follows:

“ Cincinnati, Ohio, May 13, 1899.
“ Messrs. W. Gordon & Co.,
“Oak Harbor, Ohio.
“ Gentlemen: Your letter of the twelfth received with proposition to furnish the lumber and erect building for canning factory at Oak Harbor, Ohio, according to the plans furnished you, to-wit, at $1,469.60, the lumber furnished to be of Norway pine, the flooring to the building to be two-inch pine, floor for the second floor to be one-inch yellow pine. The sliding doors you can make all one solid seven foot-sliding doors on good substantial barn rollers, the lumber to be of good merchantable quality and the work to be done in good workmanship manner; we are to furnish windows and skylights for the building and you are to put them in the building. You are to furnish the sheeting (or the building and porches, and we are to put the gravel pitch roof on same. The foundation or piers for the building must be set in the ground below the frost level, say two and one-third feet and to be not less than two feet square at the base and to project two feet above the level of the ground, we prefer the piers would come up level with tlie floor of the building, if you can do so. The building is to be completed by July 1, 1899, unless providential circumstances beyond your control should interfere, and sooner if you can possibly do so, for every day after July 1, you are to pay us $15 per day until the building is completed; we say this as we must have the building done by this time, in order to get our machinery set up in place.”
“ The citizens of Oak Harbor are to contribute $700 toward this factory, and we will give you an order on this committee for the $700 and in addition we will pay you the balance of the $1,469.60, which will be $769.60 in cash as soon as the building is completed. You are to [410]*410board up space under the main part of building and to erect out-house for the use of employes.”
“ Yours truly,
“ The J. Weller Co.
“ J. Weller, Pres.”

This letter was marked “ accepted,” or had stamped upon it the word “accepted,” and that was signed by Gordon & Company, thus making the contract complete. The building was constructed according to the contract, and after that the J. Weller Company sent Gordon & Company a check for $769.60, and also this order :

“ Cincinnati, Ohio, August 7, 1899.
“ The Citizens Committee of Oak Harbor, Ohio.
Oak Harbor Ohio.
“ Gentlemen : You will please pay to Messrs. Gordon & Company the sum of $700, the amount pledged by your committee on completion of the canning factory and greatly oblige,
“ The J. Weller Co.
“ Dictated J. W. J. Weller, Pres."

After receiving this order, Gordon & Company, through its officers( undertook to collect it. The testimony shows that there was no citizens committee that had any fund in its hands for the satisfaction of this order. The only committee appointed was one to solicit subscriptions, and subscriptions for a portion of the $700 were made, but no money had ever been turned over to the committee. Mr. Kilmer, of Gordon & Company, called on Mr. Gradolph, the mayor, who was chairman of the citizens’ meeting, but was unable to ascertain from him, or in any other way, that there was any such fund. As a matter of fact, there was, at that time no money, no fund of any kind or in any amount, out of which to satisfy this order. The evidence does show there was a deposit in a bank, at some time, of fifty dollars — twenty-five dollars deposited by the mayor and twenty-five dollars by someone else which was payable, according to the testimony, to the order of the cashier of the bank, but nothing could be collected on the order. Gordon & Company, being unable to collect it, or any part of it, brought this suit, and, in the court below recovered a verdict and judgment for $700, with interest.

Free access — add to your briefcase to read the full text and ask questions with AI

Cite This Page — Counsel Stack

Bluebook (online)
14 Ohio C.C. Dec. 407, 7 Ohio C.C. (n.s.) 303, Counsel Stack Legal Research, https://law.counselstack.com/opinion/j-weller-co-v-washington-gordon-co-ohcirctottawa-1903.