J. Richards Indus. v. Stanley MacHining, Unpublished Decision (7-16-2004)

2004 Ohio 3804
Ohio Court of Appeals·Decided July 16, 2004·No. Court of Appeals No. L-03-1024, Trial Court No CI-00-3304.·Unpublished·Cited by 2 cases

Opinion

DECISION AND JUDGMENT ENTRY
{¶ 1} This appeal is from a judgment issued by the Lucas County Court of Common Pleas following a jury verdict awarding damages for breach of contract. Because we conclude that the trial court properly denied appellant's motions for directed verdict, judgment notwithstanding the verdict, and summary judgment, but improperly denied appellee's motion for prejudgment interest, we affirm in part and reverse in part.

Background
{¶ 2} In February 1998, appellant/cross-appellee, J. Richards Industries, LP ("J. Richards"), contracted with appellee/cross-appellant, Stanley Machining, Inc. ("SMI"), to build and deliver a drill and tap machine for a price of $105,005. J. Richards tendered a down payment of $52, 502.58. Due to a variety of problems and modifications, the machine was not completed by the original projected delivery date of May 23, 1998. Over the next two years, the parties worked together to obtain a satisfactory machine. Eventually, in early April 2000, J. Richards, no longer interested in the machine, demanded the return of its down payment. Several days later, SMI sent J. Richards an invoice for $294,368.40 which included $210, 318.19, the cost for requested modifications, and credit for the down payment. On June 30, 2000, SMI notified J. Richards that the machine was ready for delivery and requested scheduling for "run-off procedures." J. Richards did not respond to the invoice or "run-off" notice.

{¶ 3} Instead of taking delivery of the machine, in July 2000 J. Richards filed suit claiming breach of contract and requesting the return of its deposit, less amounts owed to SMI for two unrelated projects. SMI filed an answer and counterclaimed for breach of contract, seeking the remaining amount allegedly owed on the drill and tap machine and its two other completed projects. Both parties filed motions for summary judgment. J. Richards' motion for summary judgment on SMI's counterclaims was denied. SMI's motion for judgment on the undisputed amounts owed for the unrelated projects was granted; any action on these accounts was stayed until the case concluded.

{¶ 4} The case was heard by a jury. J. Richards presented testimony and documents that it had contracted with SMI in February 1998 for a drill and tap machine with certain specifications. For its witnesses, J. Richards called Garrett Gillen, an engineer employed by J. Richards; Del Drinkwater, SMI plant manager; and Stanley Tambor, Jr., president of SMI. According to Gillen, the original May 1998 delivery due date was extended because of problems with the machine. Gillen presented SMI with a second written agreement, dated in September 1999, to provide for a "final delivery date" of December 10, 1999. Gillen testified that J. Richards ended the contract in April 2000, demanding the return of its $52,502 deposit. Gillen denied that any modifications were done at J. Richards' request.

{¶ 5} For its case, SMI called Stanley Tambor, Jr., SMI's president; Greg Wiciak, an SMI machinist; Christopher Mahoney, an SMI engineer; Greg Cutcher, an engineering expert who evaluated the machine; Mike Gaydos, a metal testing lab analyst; Stanley Tambor, Sr., the owner and former president of SMI; Lawrence Weber, the president of J. Richards; and Roger Starr, an engineering expert in evaluation of machinery performance and construction.

{¶ 6} SMI presented evidence that J. Richards changed the machine's specs after accepting SMI's quote based on the initial requirements. Stanley Tambor Sr. testified that over 109 modifications were required, being caused by mistakes, suggestions, or the changes requested by J. Richards' engineers. SMI witnesses testified that J. Richards engineers were involved with the machine construction at the shop even after the "final delivery" date in December 1999. Expert testimony indicated that the rods sent from J. Richards were not consistent in form or length and that changes made by J. Richards, including the addition of the Cpk requirement1 and the hopper/feeder, caused many modifications and increased costs to the original design. One expert opined that, despite the poorly made, inconsistent rods, SMI had produced a machine which met or exceeded all the required specifications, including the Cpk tolerance. Industry practice evidence was admitted that delivery deadlines are extended and additional costs are commonly incurred when modifications are made during the construction of a custom-built machine.

{¶ 7} At the close of the case, J. Richards moved for a directed verdict on SMI's counterclaims, which the trial court denied. The jury found against J. Richards on its complaint and in favor of SMI, awarding $282,404.27 in damages.

II. Assignments of Error
{¶ 8} Both parties now appeal. J. Richards sets forth the following three assignments of error:

{¶ 9} "1. The trial court erred by denying appellant's motion for directed verdict and a motion for judgment notwithstanding the verdict because it should have held that appellee breached the contract as a matter of law.

{¶ 10} "2. The trial court erred by denying appellant's motion for summary judgment because it should have held that there is no genuine issue of material fact and that appellant was entitled to judgment as a matter of law on appellee's counterclaims.

{¶ 11} "3. The trial court erred as a matter of law by entering judgment on the jury's damages award where damages are limited to the amount necessary to place the nonbreaching party in the same position in which it would have been had the other party performed."

{¶ 12} SMI cross-appeals, arguing the following sole assignment of error:

{¶ 13} "The trial court erred as a matter of law to the prejudice of cross-appellant's motion for pre-judgment interest by finding as a matter of law that it was not in the interest of justice to award cross-appellant pre-judgment interest on its money judgment for breach of contract.

III. J. Richards' Appeal
A. Motions for Directed Verdict and Judgment Notwithstandingthe Verdict

{¶ 14} In the first assignment of error, J. Richards argues that the trial court erred in denying its motion for directed verdict and for judgment notwithstanding the verdict.

{¶ 15} A motion for directed verdict is granted if, after construing the evidence most strongly in favor of the party against whom the motion is directed, "reasonable minds could come to but one conclusion upon the evidence submitted and that conclusion is adverse to such party." Civ.R. 50(A)(4). Thus, while a motion for directed verdict requires the court to consider the evidence, such a motion presents only a question of law and requires the court to discern "whether there exists any evidence of substantive probative value that favors the position of the nonmoving party." Civ.R. 50(A)(4); Goodyear Tire RubberCo. v. Aetna Cas. Surety Co., 95 Ohio St.3d 512,2002-Ohio-2842, at ¶¶ 3-4; Ruta v. Breckenridge-Remy Co. (1982), 69 Ohio St.2d 66, 69.

Free access — add to your briefcase to read the full text and ask questions with AI

J. Richards Indus. v. Stanley MacHining, Unpublished Decision (7-16-2004), 2004 Ohio 3804 (Ohio Ct. App. 2004).

2004 Ohio 3804 (J. Richards Indus. v. Stanley MacHining, Unpublished Decision (7-16-2004)) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

C4 Polymers, Inc. v. Huntington Natl. Bank
2015 Ohio 3475 (Ohio Court of Appeals, 2015)
Local Marketing Corp. v. Prudential Insurance Co. of America
824 N.E.2d 122 (Ohio Court of Appeals, 2004)