J. R. Foree v. Tri-County Electric Association

227 F.2d 945, 1955 U.S. App. LEXIS 3285
Court of Appeals for the Tenth Circuit·Decided November 25, 1955·No. 5097·Published

Opinion

227 F.2d 945

J. R. FOREE, doing business as Foree Construction Company; and Western Casualty and Surety Company, Appellants,
v.
TRI-COUNTY ELECTRIC ASSOCIATION, Inc., a corporation, Appellee.

No. 5097.

United States Court of Appeals Tenth Circuit.

November 25, 1955.

A. G. McClintock, Cheyenne, Wyo. (Clyde C. Goebel, Kansas City, Mo., was with him on the brief), for appellants.

Carleton A. Lathrop, Cheyenne, Wyo. (Otis Reynolds, Sundance, Wyo., and Carl L. Lathrop, Cheyenne, Wyo., were with him on the brief), for appellee.

Before BRATTON, MURRAH and PICKETT, Circuit Judges.

MURRAH, Circuit Judge.

Appellant, J. R. Foree, instituted this action to recover the balance due under his contract for the construction of an electrical transmission line for appellee, Tri-County Electric Association, Inc.; and to recover damages for lost profits resulting from the breach of a covenant to timely deliver poles for the construction of the transmission line. Western Casualty and Surety Company, as assignee of amounts due Foree from Tri-County, was joined as party plaintiff.

Tri-County asserted a set-off against Foree in the amount of $8,822.32 for materials furnished and not used in the performance of the work under the contract. And it denied any covenant to furnish poles within a stipulated time in contradiction of their original written contract specifically relieving Tri-County of any liability because of delays in the progress of the work.

In entering judgment for the plaintiffs on the first cause of action, the court credited Tri-County with $5,100 as a set-off, based upon a specific finding to the effect that Foree had admitted and agreed with Tri-County's engineering representative that he had received excess materials in that amount not used in the construction of the transmission line. On the second cause of action the court determined that Tri-County specially covenanted with Foree to furnish twelve carloads of poles per week as a material inducement for the execution of an amendment to his contract with Tri-County for the construction of additional miles of transmission line, and that this covenant was not qualified by the provisions of the original contract between the parties. The court dismissed the second cause of action, however, concluding that although the evidence showed delays in the deliveries of the poles under the covenant, Foree nevertheless failed to prove any damages resulting from the failure to timely deliver; that the delays in the construction of the transmission line leading to increased construction costs were occasioned by the failure of Foree's machinery on the job, the condition of the terrain and the weather, and the further significant fact that one of Foree's crews had left the project for a period of approximately two months during the course of construction.

The sole question on appeal by Foree and his surety company is the sufficiency of the evidence (1) to show an admission or agreement by Foree that he owed $5,100 to Tri-County for materials not used in the construction work, and (2) to sustain the dismissal of the claim for lost profits.

The credit allowance of $5,100 by the trial court to Tri-County was based upon the direct testimony of W. H. Nixon of the engineering firm representing Tri-County, to the effect that in a conference at the home office of Tri-County in Sundance, Wyoming, on September 27, 1951 between him, Foree and the materials and work clerk of Tri-County, Foree agreed to a negotiated figure of $5,100 in settlement of the account for materials charged out to him and not used in the project. The conference was held in an attempt "to come to some settlement on final papers so that the job could be closed out." Nixon stated that "we made numerous efforts to settle this matter because we do not get paid until the job is finished out. We wrote numerous letters to Foree and then to the bonding company trying to make arrangement to meet them and settle this problem."

Foree recalled the conference at Sundance, but denied knowledge of any agreement regarding the charge-out account. On appeal he suggests that the letters referred to by Nixon were written after the Sundance conference and by their tenor irrefutably negated any final settlement at the Sundance conference on September 27, 1951; that instead they unequivocally showed that negotiations were continued for a period of a year and a half in an effort to finally settle the amount of materials charged to his account and not used in the project. He points to the failure of Tri-County to plead any agreement on an amount of $5,100 in its answer, but that instead Tri-County asserted a set-off of $8,822.32 for materials charged to Foree.

Free access — add to your briefcase to read the full text and ask questions with AI

J. R. Foree v. Tri-County Electric Association, 227 F.2d 945, 1955 U.S. App. LEXIS 3285 (10th Cir. 1955).

227 F.2d 945 (J. R. Foree v. Tri-County Electric Association) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

United States v. Waymire
202 F.2d 550 (Tenth Circuit, 1953)
Van Dreal v. Van Dreal
214 F.2d 715 (Tenth Circuit, 1954)
Wyoming Ry. Co. v. Herrington
163 F.2d 1004 (Tenth Circuit, 1947)
Payne v. Pray
173 F.2d 149 (Tenth Circuit, 1949)
Foree v. Tri-County Electric Ass'n
227 F.2d 945 (Tenth Circuit, 1955)