J. McClure Kelly Plumbing Co. v. Minneapolis Housing & Redevelopment Authority

231 N.W.2d 289, 304 Minn. 384, 1975 Minn. LEXIS 1434
CourtSupreme Court of Minnesota
DecidedJune 20, 1975
DocketNo. 45404
StatusPublished

This text of 231 N.W.2d 289 (J. McClure Kelly Plumbing Co. v. Minneapolis Housing & Redevelopment Authority) is published on Counsel Stack Legal Research, covering Supreme Court of Minnesota primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
J. McClure Kelly Plumbing Co. v. Minneapolis Housing & Redevelopment Authority, 231 N.W.2d 289, 304 Minn. 384, 1975 Minn. LEXIS 1434 (Mich. 1975).

Opinion

Yetka, Justice.

Defendant and third-party plaintiff, Minneapolis Housing and Redevelopment Authority (HRA), appeals from denial by the Hennepin County District Court of its alternative motion for amended findings or a new trial. We affirm in part, reverse in part, and remand for a new trial on the issue of HRA’s liability for the cost of repairs in the east wing of its Housing Project No. 2-25.

Plaintiff, J. McClure Kelly Plumbing Company, was the mechanical (plumbing and heating) contractor of Housing Project No. 2-25 (hereinafter called the project) developed by HRA. The firm of Bettenberg, Townsend, Stolte & Comb, Inc. (hereinafter BTSC) was the architect of said project; Adolfson & Peterson, Inc. (hereinafter A & P) was the general contractor; and Ericksen, Ellison and Associates, Inc. (hereinafter Ericksen) was retained as the mechanical engineer.

During the months of January and February of 1970, at which time the project was still under construction, some heating pipes [386]*386and water pipes in the building were frozen on two separate occasions. In both cases, plaintiff repaired the damage and thereafter submitted an invoice to HRA in the amount of $10,922.39 for that work ($10,297.64 for the first freeze; $624.75 for the second freeze). HRA’s refusal to pay plaintiff’s invoice gave rise to the instant litigation.

Plaintiff brought action against HRA, BTSC, and A & P seeking payment of $10,922,39 for labor and materials required to effectuate the aforesaid repairs. Eventually the action involved five parties, which by stipulation were aligned as follows:

(1) Plaintiff v. HRA.1
(2) HRA (as third-party plaintiff) v. BTSC and A & P (as third-party defendants).2
(3) BTSC (as fourth-party plaintiff) v. Ericksen (as fourth-party defendant).3

On March 25, 1974, this matter came to trial before the court, sitting without a jury. In its findings of fact, conclusions of law, and order for judgment, the court found HRA liable to plaintiff in the amount of $10,922.39, plus interest and costs. BTSC was found liable to HRA in the amount of $624.75, plus interest and costs. 'Ericksen, in turn, was found liable to BTSC in the latter amount. A & P was granted judgment of dismissal.

Thereafter, HRA moved for amended findings of fact, con-[387]*387elusions of law, and order for judgment, or, alternatively, for a new trial on all issues. That motion was denied and HRA appealed.4

Although the instant litigation involves two separate incidents wherein the pipes of the project were frozen, this appeal concerns only the first such incident, which occurred on or about January 7, 1970.5

On January 30, 1968, plaintiff entered into a contract with HRA as a mechanical contractor to perform the installation of the plumbing and heating system of the project.

The building constituting the project consists of two wings. The west wing contains 144 residential units, along with the boiler room which is the source of heat for the entire structure. Boilers in the boiler room heat water which is then circulated throughout both wings by electric pumps. There are three such pumps; one serves the west wing, one serves the east wing, and one serves as a standby which may, by manually controlled valves, be utilized to serve either wing.

Construction on the project progressed to a point at which, on September 19, 1969, HRA “accepted” the west wing portion of the building.6 The specifications made part of the contract between HRA and plaintiff provided, in part:

“The Local Authority shall assume risk of loss with respect to any area occupied by it under the terms of this agreement; provided the contractor shall assume full responsibility for loss [388]*388of damage traceable to his fault or negligence in the performance of his contract.”7

The west wing was thereafter occupied by tenants.

Construction on the east wing continued into January 1970. There was testimony that the general contractor, A & P, had a considerable amount of caulking to finish, as well as some insulation to install. Most of the unfinished caulking was in the east wing.

Plaintiff’s work had been virtually completed in the west wing prior to January 1970. Additionally, the president of plaintiff company testifed that the heating system in the east wing had been virtually completed prior to the first freeze on January 7, 1970.

On January 5, 1970, an HRA building custodian discovered that the heating pump for the west wing had been switched off. However, the east wing pump was running at that time. In a short time the west wing pump was switched on, and there is no direct evidence of record of any subsequent pump stoppage.

On January 6, 1970, there were no apparent heat problems in the building. However, on the next day the custodian discovered that a domestic water pipe had ruptured in the west wing.8 He also discovered pipe leaks in the east wing.

The major ruptures in the east wing were in a heating pipe near the laundry room and in a coil of an air heating unit in the basement of the building.

In addition to the single rupture of the domestic water supply line in the west wing, other pipes, according to uncontroverted testimony, had frozen without rupturing in that part of the building.

[389]*389At trial, plaintiff’s president, LeRoy Kelly, testified that his office received a call, from an unspecified person, informing them of the frozen pipes and giving oral instructions to commence repairs immediately. Plaintiff immediately commenced around-the-clock repairs of the damage in both wings.

On January 13, plaintiff received a letter from BTSC which stated in part:

“* * * [E] ach prime contractor is hereby directed to proceed at once with the repair and/or replacement of all damaged work within the scope of his contract. * * *
“Until such time as the actual cause of this damage is determined, we recommend that each Contractor keep a separate record of labor and materials involved in such repair and/or replacement work.”

There is credible evidence in the record that this letter was sent at the behest of the HRA project construction coordinator.

The repair work was subsequently completed. However, plaintiff was notified by HRA, in a letter dated January 12,1971, that his claim for compensation for effecting the repairs was denied, since:

“1. That portion of the building where ruptures occurred [east wing] had not been accepted by the Authority [HRA].
“2. Under Section 26 of the General Conditions — Care of The Work, it is the responsibility of the Contractor, not the Authority, to furnish continuous protection to the building.”

Section 26 of the general conditions of the contract between plaintiff and HRA was read into the record as follows:

Free access — add to your briefcase to read the full text and ask questions with AI

Related

In Re Estate of Lea
222 N.W.2d 92 (Supreme Court of Minnesota, 1974)
Balafas v. Angelos
198 N.W.2d 260 (Supreme Court of Minnesota, 1972)
Winona National & Savings Bank v. Sheehan
222 N.W.2d 92 (Supreme Court of Minnesota, 1974)

Cite This Page — Counsel Stack

Bluebook (online)
231 N.W.2d 289, 304 Minn. 384, 1975 Minn. LEXIS 1434, Counsel Stack Legal Research, https://law.counselstack.com/opinion/j-mcclure-kelly-plumbing-co-v-minneapolis-housing-redevelopment-minn-1975.