J. K. Welding Co. v. W. J. Halloran Steel Erection Co.

178 F. Supp. 584, 1959 U.S. Dist. LEXIS 2555
CourtDistrict Court, D. Rhode Island
DecidedOctober 27, 1959
DocketCiv. A. No. 2441
StatusPublished
Cited by3 cases

This text of 178 F. Supp. 584 (J. K. Welding Co. v. W. J. Halloran Steel Erection Co.) is published on Counsel Stack Legal Research, covering District Court, D. Rhode Island primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
J. K. Welding Co. v. W. J. Halloran Steel Erection Co., 178 F. Supp. 584, 1959 U.S. Dist. LEXIS 2555 (D.R.I. 1959).

Opinion

DAY, District Judge.

This is an action to recover damages for breach of contract. The plaintiff is a corporation organized under the laws of the State of New York; the defendant is incorporated under the laws of the State of Rhode Island. Jurisdiction is. based upon diversity of citizenship and! the existence of a controversy in the requisite amount. 28 U.S.C.A. § 1332(a) d).

The complaint alleges in material part that on July 5, 1955, the plaintiff and the defendant entered into a written contract whereby the defendant agreed to perform the structural steel erection for the job designated as the “Massachusetts Turnpike Authority Contract #51-021”; that the defendant was to be paid at the rate of $31.50 per ton for its work; that, in addition, the defendant was to be paid $5 per ton for trucking and unloading steel in connection therewith; that on February 15, 1956, said contract was amended in writing in certain respects; that on October 24, 1956, the defendant notified the plaintiff of its withdrawal from said contract; that thereafter the plaintiff demanded performance on the part of the defendant; that the plaintiff’s demand was never answered by the defendant; and that the plaintiff stood ready at all times to perform all of its obligations under said contract. A copy [586]*586■of said■ contract and of the written ■ amendment thereto is annexed to the complaint.

■ The complaint further alleges that, by reason of the foregoing, the plaintiff was compelled to re-let the work; and that the lowest bid which the plaintiff then received for said work was $53.50 per ■ton, an increase of $17 per ton over the price for which the defendant had previously contracted to perform said work. The plaintiff seeks damages in the sum of $20,000, together with interest from December 1, 1956 and the costs of this action.

The defendant, in its answer, admits the execution of said contract and of the rider thereto; but alleges by way of defense that, by letter dated October 10, 1956, the plaintiff positively manifested its- intention not to perform its obligations under said contract, and that the defendant’s duty to perform thereunder was discharged thereby. The answer further alleges that the defendant was at all times ready to perform its obligations under said contract immediately upon ■the plaintiff’s first fulfilling certain conditions precedent contained in said contract. Finally, the defendant states that it is- without knowledge sufficient to form a belief as to the truth of the averments of the complaint relative to the re-letting of- the work and to the price paid therefor, and leaves the plaintiff to the proof of such facts.

■ The evidence adduced at the trial established that in June, 1955 the plaintiff •entered into"a sub-contract with a general contractor which held a contract with the Massachusetts Turnpike Aufhority for the construction of certain highways and bridges in the Commonwealth of Massachusetts. Under its subcontract, the plaintiff obligated itself to furnish and fabricate the steel for two •bridges and an overpass, and to erect them. These structures were to be erected in accordance with certain plans nánd specifications prepared by the engineers of said Turnpike Authority which were made available to and (examined by a representative of the plaintiff before it entered into said subcontract. The contract for the erection of these structures was known as “Massachusetts Turnpike Authority Contract 51-021”. These plans and specifications showed that all holes in the structural steel for the insertion of rivets to secure said steel when erected would be 1B/ie" in circumference; and provided further that the holes in the steel for the expansion dams would be tyie" in circumference when delivered on the site for erection and would be reamed to 1BAe" when placed in position. No other provision for field reaming was made in said plans and specifications.

Sometime in 1955, these plans were made available to the defendant which, after examining them, submitted a proposal to the plaintiff for doing the erection work required under the former’s sub-contract. This proposal, entitled “Re Massachusetts Turnpike Contract 51-021 Lee-Beckett” and dated July 5, 1955, was subsequently accepted by the plaintiff on January 23, 1956. In its proposal the defendant offered to do said erection work (including trucking) at the price of $36.50 per ton, in accordance with the conditions set forth therein. This proposal was in the form adopted by the New England Steel Erectors Association and contained many apparently standard and usual conditions, of which only two are pertinent here. There were the following :

“1. The Customer shall notify the Erector at least 48 hours before each erection operation is to commence.
“2. Where details are not available at the time estimate is made all material will be fabricated in a manner so as to reduce the field labor as far as possible. All prices are based on plans submitted for estimate.”

On January 23, 1956, the parties executed a rider modifying certain conditions of the proposal; but those modifications are of no import in this controversy.

[587]*587The evidence further establishes that subsequent to July 5, 1955 and before January 23, 1956 (when plaintiff executed a formal acceptance of said proposal and the rider thereto), the plaintiff began the preparation of its own shop drawings for the fabrication and erection of the steel. There is -credible evidence that these were completed by March, 1956. During the preparation of these drawings, the plaintiff apparently discovered that if the holes were punched or reamed full-size in its shop in accordance with the plans of the Turnpike Authority, a skew in the bridge would result. Accordingly, the plaintiff’s drawings as completed called for the reaming of an additional 8,700 holes- by the defendant on the job site. Although these drawings were completed by March, 1956, they were not shown or delivered to any representative of the defendant until October 2,1956. On that date the plaintiff’s chief engineer, Robert Freeman, and the defendant’s operations manager, Edward Prescott, met by chance on the job site. At this meeting a discussion occurred between them concerning the reaming of the requisite holes in the structural steel to be supplied by the plaintiff. Freeman then informed Prescott that the plaintiff had decided to send the steel to the site with all the holes punched m«"; and that said holes would have to be reamed by the defendant to 1B/is" in the field. Prescott protested that the defendant had not agreed to do any field reaming except that specified in the plans prepared by the Turnpike Authority. At this time, Freeman also produced a set of the drawings prepared by the plaintiff showing that all holes in the steel would be punched by the plaintiff to and reamed in the field to 1B/ie".

This discussion was followed by a letter from the defendant, signed by Prescott and dated October 3, 1956, which the plaintiff claims it did not receive until October 10, 1956. The pertinent paragraphs of this letter were as follows:

“At our meeting on the site yesterday, Mr. Freeman spoke of sending the beams through with the field splice holes punched undersized to 'be reamed in the field. I requested that this not be done and wish' to repeat that request. We do not have any allowance in our price for this-reaming which will be a substantial item.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Pack Brothers Paint and Body Shop v. Nationwide Mut. Ins. Co.
2003 NCBC 2 (North Carolina Business Court, 2003)
McGlothlin v. Nichoalds
212 F. Supp. 757 (D. Colorado, 1962)

Cite This Page — Counsel Stack

Bluebook (online)
178 F. Supp. 584, 1959 U.S. Dist. LEXIS 2555, Counsel Stack Legal Research, https://law.counselstack.com/opinion/j-k-welding-co-v-w-j-halloran-steel-erection-co-rid-1959.